United
States of America
OCCUPATIONAL
SAFETY AND HEALTH REVIEW COMMISSION
1120 20th Street, N.W., Ninth Floor
Washington,
DC 20036-3457
ON
BRIEFS:
Ronald J. Gottlieb,
Attorney; Heather R. Phillips, Counsel for Appellate Litigation; Joseph M.
Woodward, Associate Solicitor; M. Patricia Smith, Solicitor; U.S. Department of
Labor, Washington, DC
Mark
A. Waschak, J. Larry Stine, and Elizabeth K. Dorminey; Wimberly, Lawson,
Steckel, Schneider & Stine, P.C., Atlanta, GA
DECISION
AND REMAND
Before: ROGERS, Chairman; ATTWOOD
and MacDOUGALL, Commissioners.
BY THE COMMISSION:
Southern
Pan Services Company, a concrete formwork contractor, installed the shoring and
formwork for a six-story concrete parking structure, which was part of a
project known as Berkman Plaza II, in Jacksonville, Florida. On December 6,
2007, part of the structure collapsed during a concrete pour, fatally injuring
one Southern Pan employee and seriously injuring another Southern Pan employee
along with more than twenty other workers involved in the project. After
conducting an inspection of the worksite, the Occupational Safety and Health
Administration issued Southern Pan two citations—a two-item serious citation
and a two-item willful citation—alleging violations of the Occupational Safety
and Health Act of 1970, 29 U.S.C. §§ 651-678. OSHA proposed a total penalty of
$125,000. Following a hearing, former Administrative Law Judge Ken S. Welsch
issued a decision in which he vacated both of the serious citation items, and
vacated one item and affirmed the other item of the willful citation, for which
he assessed a penalty of $40,000.
Only the two
willful citation items are at issue on review. The Secretary challenges the
judge’s decision to vacate Willful Citation 2, Item 1, which alleges a
violation of 29 C.F.R. § 1926.701(a) (placement of construction loads),
and Southern Pan challenges his decision to affirm Willful Citation 2, Item 2,
which alleges a violation of 29 C.F.R. § 1926.703(a)(2) (availability of
formwork plans at jobsite). For the following reasons, we set aside the judge’s
decision in full as to Item 1 and in part as to Item 2, and remand the case to
the Chief Judge for reassignment and further proceedings.
BACKGROUND
In
January 2006, construction of a new six-story parking garage and adjacent condominium
tower began at the Berkman worksite. The project owner, Berkman Plaza II, LLC,
hired architecture firm Pucciano and English, Incorporated and general
contractor Choate Construction Company to oversee the project. Pucciano and
English employed the project’s Engineer of Record, who prepared “signed and
sealed” structural drawings for the project. Choate hired various subcontractors, including A.A. Pittman and
Sons, a concrete finishing company, and Southern Pan. Southern Pan was
contractually responsible for: (1) obtaining shoring and reshoring drawings for both the garage and tower; (2) building the
formwork; and (3) placing concrete for some of the vertical pours, but not the
horizontal pours. It is undisputed that placing the concrete for the horizontal
pours—including the pour that resulted in the collapse—was Pittman’s responsibility.
Southern
Pan hired Patent Engineering to provide the signed and sealed drawings for the
shoring and reshoring that were available at the worksite. Patent’s plans show
that the formwork, which would hold the poured concrete for the garage, was to
be supported by shoring and reshoring that extended all the way down to the
ground. Once installed, the shoring and reshoring, as well as the formwork,
were subject to two levels of scrutiny. Universal Engineering Sciences was
hired by Southern Pan to inspect the shoring and reshoring to determine whether
these components were correctly constructed according to Patent’s drawings.
Synergy Structural Engineering was hired by Berkman to serve as the project’s
threshold inspector and was required to provide periodic inspections at
different stages of the construction process to ensure that: (1) the
construction of all load-bearing components complied with the permit documents;
and (2) the shoring and reshoring conformed to the shoring and reshoring plans.
Even
though Patent’s plans showed that shoring or reshoring was to extend down to
the ground until the end of the construction phase, Southern Pan removed
reshoring from the first, second, and third levels of the garage over three
different days in October and November of 2007, well before the end of
construction, but it neither made nor requested changes to Patent’s drawings to
reflect the removal. James Smith, Southern Pan’s superintendent for the
project, testified that the reshoring was removed because he believed that
Timothy Postma, Southern Pan’s senior project manager, wanted to switch the
shoring method, which instead of shoring to the ground, would shore the top
level and reshore only the two levels immediately below it (known as the
“one-over-two method”). On November 7 and 20, 2007, Choate and Pittman placed two
concrete pours in the garage without incident. However, during the next pour
(known as 6A) on December 6, 2007, the garage collapsed.
DISCUSSION
Before
turning to the two citation items at issue on review, we first address Southern
Pan’s claim that certain material redacted by the Secretary in a document
provided to the company during discovery was not, as alleged by the Secretary,
protected by the deliberative process privilege and should have been produced
in discovery.
I. Deliberative
Process Privilege
In May 2008,
a structural engineer in OSHA’s National Directorate of Construction Office
prepared a report (“Report”) for OSHA regarding the garage collapse at the
Berkman worksite. In response to Southern Pan’s discovery request for OSHA’s
entire investigative file, the Secretary produced the Report with portions of
the text redacted. The Secretary claimed that the redacted material was
protected by the deliberative process privilege. Southern Pan filed a Motion to
Compel seeking, among other things, the disclosure of portions of the redacted
material. After conducting an in camera review of the Report, the judge
issued an order denying Southern Pan’s motion. He upheld the claim of privilege
as asserted in a Declaration submitted by OSHA’s Deputy Assistant Secretary and
found that Southern Pan had not established a need for the redacted material
sufficient to overcome the privilege. The judge also stated that “there is
nothing in this [R]eport or in these conclusions . . . that I would use to form
any basis for my decision.” Therefore, he admitted the unredacted portions of
the Report into evidence but sealed the redacted portions as confidential.
On review,
Southern Pan contests the judge’s ruling, raising various challenges to the
Secretary’s assertion of the deliberative process privilege. However, we agree
with the judge that the Secretary properly invoked the privilege in withholding
the redacted information in the Report. It is well-settled that the
deliberative process privilege “allows the government to withhold documents and
other materials that would reveal ‘advisory opinions, recommendations and
deliberations comprising part of a process by which governmental decisions and
policies are formulated.’ ” In re Sealed Case, 121 F.3d 729, 737 (D.C.
Cir. 1997) (citation omitted). The purpose of the privilege “ ‘is to prevent
injury to the quality of agency decisions’ by allowing government officials
freedom to debate alternative approaches in private.” Id. (quoting NLRB
v. Sears, Roebuck & Co., 421 U.S. 132, 151 (1975)). In deciding whether
material is protected under the deliberative process privilege, courts consider
whether the material is “predecisional” and whether it is “deliberative.” Hinckley
v. United States, 140 F.3d 277, 284 (D.C. Cir. 1998). We find that the
report is both predecisional and deliberative.
The material
here is predecisional as it preceded the Secretary’s decision to cite Southern
Pan. In addition, the material is deliberative, because it does not consist of
mere factual conclusions, as Southern Pan contends, but rather contains
communications that are “part of the agency give-and-take by which the decision
itself [was] made.” Id. It contains the OSHA engineer’s personal
opinions of how certain employers performed their contractual duties, as well
as his conclusions about what caused the garage collapse. Fed. Trade Comm’n
v. Warner Commc’ns Inc., 742 F.2d 1156, 1161 (9th Cir. 1984) (finding
district court erred in ordering disclosure of agency memoranda that was
predecisional and contained analyses and recommendations at “the heart of the
deliberative and policymaking process”). The OSHA engineer provided the
information at the request of OSHA’s Region IV Administrator to assist its
Jacksonville Area Office in determining whether to issue citations in this
case. See Stone & Webster Constr. Inc., 23 BNA OSHC 1939, 1942,
2009-12 CCH OSHD ¶ 33,222, p. 55,980 (No. 10-0130, 2012) (consolidated)
(“predecisional materials pertaining to the government’s decision to cite, or
not to cite, an employer for a particular alleged violation are within the
scope of the [deliberative process] privilege”). Accordingly, the Secretary had
a substantial legal basis for applying the privilege. See Donald Braasch
Constr., Inc., 17 BNA OSHC 2082, 2086, 1995-97 CCH OSHD ¶ 31,259, p.
43,868 (No. 94-2615, 1997) (finding dismissal unwarranted where Secretary had a
substantial legal basis for failing to disclose and there was no evidence of
contumacy).
Contary to
Southern Pan’s argument, the Secretary did not waive the privilege. The Secretary
timely filed a Declaration, objecting to production of the redacted material,
just a few weeks after receiving Southern Pan’s Motion to Compel, which was the
first time Southern Pan requested production of the redacted portions of the
Report. See In re Sealed Case, 121 F.3d at 741 (stating that a
party has no obligation “to formally invoke its privileges in advance of the
motion to compel”). In addition, the judge correctly found that the information
had no bearing on whether the company was in compliance with the cited
standards. Cf. Frazee Constr. Co., 1 BNA OSHC 1270, 1274, 1973-74
CCH OSHD ¶ 16,408, pp. 21,301-02 (No. 1343, 1973) (agency’s exculpatory
information must be disclosed absent proof of privilege).
For all of
these reasons, we affirm the judge’s conclusion that the redacted material was
protected under the deliberative process privilege. We turn now to the
individual citation items.
II. Willful
Citation 2, Item 1 – 29 C.F.R. § 1926.701(a) (construction loads)
Under
this item, the Secretary alleges that Southern Pan failed to determine “based
on information received from a person qualified in structural design” that the
garage at the Berkman worksite was capable of supporting the load imposed by
pour 6A. The cited standard states that “[n]o construction loads shall be
placed on a concrete structure or portion of a concrete structure unless the
employer determines, based on information received from a person who is
qualified in structural design, that the structure or portion of the structure
is capable of supporting the loads.” 29 C.F.R. § 1926.701(a).
The judge
vacated this item, finding that based on the plain language of the cited
standard and the preamble to the final rule, the requirements of the standard
apply only to “the employers directly responsible for the concrete
operation”—in this case Choate, the general contractor, and Pittman, the concrete
finishing subcontractor. He rejected the Secretary’s claim that a clause in the
subcontract between Choate and Southern Pan made Southern Pan contractually
responsible for placing the concrete load on the structure because he found
that nothing in the clause shifted “responsibility for the concrete operations
to the formwork subcontractor.” Thus, he concluded that the cited standard did
not apply.
Under
Commission precedent, however, the focus of the Secretary’s burden of proving
that the cited standard applies pertains to the cited conditions, not the
particular cited employer. See, e.g. Ryder Transp. Servs.,
24 BNA OSHC 2061, 2064, 2014 CCH OSHD ¶ 33,412, p. 57,383 (No.
10-0551, 2014) (concluding “that the Secretary has failed to establish that the
cited general industry standard applies to the working conditions here”); KS
Energy Servs., Inc., 22 BNA OSHC 1261, 1267, 2004-08 CCH OSHD ¶ 32,958, p.
53,924 (No. 06-1416, 2008) (finding “the cited . . . provision was
applicable to the conditions in KS Energy’s traffic control zone”), aff’d, 701
F.3d 367 (7th Cir. 2012); Active Oil Serv., Inc., 21 BNA OSHC 1092,
1094, 2004-09 CCH OSHD ¶ 32,802, pp. 52,486-7 (No. 00-0482, 2005) (finding
“that the confined space standard applies to the cited conditions” because “the
vault was a confined space”); Arcon, Inc., 20 BNA OSHC 1760, 1763,
2002-04 CCH OSHD ¶ 32,728, p. 51,896 (No. 99-1707, 2004) (“In order to
establish a violation, the Secretary must show that the standards applied to
the cited conditions.”).
Since the Berkman project involved the placement of a load on the
garage’s concrete structure, § 1926.701(a) clearly applies to the cited
conditions. Thus, contrary to our dissenting colleague’s contention, the issue
before us has nothing to do with whether the cited standard is applicable. That
element of the Secretary’s burden has been established. What remains at issue
is determining the nature of Southern Pan’s compliance obligations under
the cited provision given the circumstances of this case.
We agree
with the Secretary’s contention on review that this question is answered by
long-standing Commission precedent holding that an employer whose own employees
are exposed to a hazard or violative condition—an “exposing employer”—has a
statutory duty to comply with a particular standard even where it did not
create or control the hazard. See Anning-Johnson Co., 4 BNA OSHC 1193,
1198-99, 1975-76 CCH OSHD ¶ 20,690, p. 24,784 (No. 3694, 1976) (consolidated)
(holding that the exposure of a subcontractor’s “employees to a condition
that the employer knows or should have known to be hazardous, in light of the
authority or ‘control’ it retains over its own employees, gives rise to
a duty under section 5(a)(2) of the Act . . . .”). Here,
the evidence unequivocally establishes that Southern Pan was an exposing
employer. Two Southern Pan employees were on the fifth floor of the garage
during the 6A pour observing the formwork to ensure it was compliant and stable.
See Jackson Constr. Co., 5 BNA OSHC 1608, 1610, 1977-78 CCH OSHD ¶
21,981, p. 26,491 (No. 13843, 1977) (finding that carpenters working on the
floor below the pour “had access to the zone of danger created by the
violation”) (citation omitted). Therefore, both employees, one of whom died as
a result of injuries sustained in the garage collapse, were exposed to the
violative condition. And as an exposing employer, Southern Pan was required to
“do what [was] ‘realistic’ under the circumstances to protect its employees
from the hazard to which a particular standard is addressed, even though
literal compliance with the standard may [have been] unrealistic.” Anning-Johnson
Co., 4 BNA OSHC at 1199, 1975-76 CCH OSHD at p. 24,784 (footnote omitted); see
also Capform, Inc., 16 BNA OSHC 2040, 2042, 1993-95 CCH OSHD ¶ 30,589, p.
42,356 (No. 91-1613, 1994) (addressing “multi-employer worksite defense” and
finding exposing employer responsible for violation it did not create or
control because it failed to take “reasonable alternative steps to protect its
employees”); Capform Inc., 13 BNA OSHC 2219, 2222, 1987-90 CCH OSHD ¶
28,503, p. 37,776 (No. 84-0556, 1989) (rejecting employer’s asserted
multi-employer worksite defense and noting that “[t]he . . . defense does not
alter the general rule that each employer is responsible for the safety of its
own employees.”) (citation omitted), aff’d per curiam, 901 F.2d 1112
(5th Cir. 1990) (unpublished); Mark A. Rothstein, Occupational Safety and
Health Law (2014 ed., § 7:7) (“Although still maintaining that a noncontrolling
employer is in violation when its employees are exposed to hazards,” the
Commission created the multi-employer worksite defense, holding that an
exposing “employer is not in violation if it did not and could not with the
exercise of reasonable diligence know of the hazard” and permitting “an
employer to escape liability by taking realistic abatement measures, even
though [they] may fall short of literal compliance with applicable
standards.”).
This has
been Commission precedent for nearly forty years, but our dissenting colleague
chooses to ignore these fundamental principles and, instead, poses what she
apparently believes is something of a conundrum—asking how Southern Pan could
violate the cited standard when, as even the Secretary concedes, only Choate
and Pittman were obligated to make the determination the standard requires. The
Commission clearly answered this long ago:
[E]ach employer has primary responsibility for the
safety of its own employees. Simply because a subcontractor cannot himself
abate a violative condition does not mean it is powerless to protect its
employees. It can, for example, attempt to have the general contractor correct
the condition, attempt to persuade the employer responsible for the condition
to correct it, instruct its employees to avoid the area where the hazard exists
if this alternative is practical, or in some instances provide an alternative
means of protection against the hazard . . . . In the absence of such actions,
we will still hold each employer responsible for all violative conditions to
which its employees have access.
Grossman Steel & Alum.
Corp., 4 BNA OSHC 1185, 1189, 1975-76 CCH OSHD ¶ 20,691, p. 24,791
(No. 12775, 1975) (footnote omitted); see Associated Underwater Servs.,
24 BNA OSHC 1248, 1251, 2012 CCH OSHD ¶ 33,198, p. 55,750 (No. 07-1851, 2012)
(“Commission precedent require[s] an employer to detect and assess the hazards
to which its employees may be exposed, even those it did not create.”)
(citation omitted); D. Harris Masonry Contracting, Inc. v. Dole, 876
F.2d 343 (3d Cir. 1989); DeTrae Enters., Inc. v. Sec’y of Labor and OSHRC,
645 F.2d 103 (2d Cir. 1981); Bratton v. OSHRC, 590 F.2d 273 (8th Cir.
1979); Cent. of Ga. R. Co. v. OSHRC, 576 F.2d 620 (5th Cir. 1978). In short, an employer’s compliance duty under the Act is
undeniable when its own employees are exposed. OSH Act § 5(a)(2), 29 U.S.C. §
654(a)(2) (“Each employer . . . shall comply with occupational safety and
health standards promulgated under this Act.”). The only question is what
measures the employer can reasonably take to protect its employees, and such
measures must be identified by the Secretary to satisfy his burden of proving
noncompliance.
Our
dissenting colleague makes a number of seemingly plausible arguments but they
are all variations of her flawed premise—that this case is about applicability
rather than compliance. Her position further suggests a fundamental
disagreement with our multi-employer precedent, but that precedent is
well-settled and firmly grounded in the statute.
Because Southern Pan exposed its employees to a hazard, it is
of no moment that Southern Pan was unable to abate the violation itself or, as
was the case here, that another employer might be charged with abating the
condition. Gregory N. Dale & P. Matthew Shudtz, eds., Occupational Safety
and Health Law (3d ed. 2013, Ch. 3.III) (“OSHA must show that a condition that
violates a standard existed. This element does not require proof that the cited
employer itself violated the standard, i.e., that the cited employer
created the violative condition; OSHA need prove only that a violative
condition existed, regardless of who or what caused it.”). An employer in
Southern Pan’s position still has an obligation to make reasonable efforts to
protect its employees from a hazard. And contrary to our
dissenting colleague’s claim, the Secretary has done nothing to upset an
exposing employer’s responsibility to its own employees when, in the preamble
to the cited provision, he explained that the concrete operator rather than an
engineer-architect is responsible for the standard’s construction-load
placement determination. Indeed, the concrete operator places the load and
bears responsibility for employee safety; it is unquestionably a “creating
employer.” The Secretary, however, did not state that the concrete operator’s
responsibility for employee safety belonged to it alone, nor did the Secretary
relieve an exposing employer of its obligation to protect its own employees.
Thus, the
issue for consideration is whether, under applicable precedent, Southern Pan
made reasonable efforts to protect the two employees exposed to the violative
condition. E.g., Associated Underwater, 24 BNA OSHC at 1251, 2012
CCH OSHD at p. 55,750. Because the judge never addressed the Secretary’s
contention that Southern Pan violated the cited provision as an exposing
employer, he did not resolve the issue of Southern Pan’s compliance obligations
under the standard. Accordingly, we remand this case for a determination of whether
the Secretary has established that Southern Pan failed to take reasonable
measures to comply with the standard as an exposing employer.
On remand,
if it is determined that Southern Pan failed to comply with § 1926.701(a),
the judge should also determine whether the Secretary has established that
Southern Pan knew or should have known of the conditions giving rise to the
violation. Contour Erection & Siding Sys., Inc., 22 BNA OSHC 1072,
1073, 2004-09 CCH OSHD ¶ 32,943, p. 53,787 (No. 06-0792, 2007) (stating that
the Secretary must prove that the employer knew or, with the exercise of
reasonable diligence, should have known of the conditions constituting the
violation). In the event the Secretary bases his case for knowledge on the
imputation of superintendent Smith’s knowledge of his own misconduct, i.e. his
failure to take steps to obtain and provide the required information, we direct
the judge to determine on remand whether this case falls within the scope of
the Eleventh Circuit’s recent decision in ComTran Grp., Inc. v. U.S. Dep’t
of Labor, 722 F.3d 1304 (11th Cir. 2013). In ComTran, the court held
that “the Secretary does not carry [his] burden and establish a prima facie
case with respect to employer knowledge merely by demonstrating that a
supervisor engaged in misconduct.” 722 F.3d at 1316. “Rather, ‘employer
knowledge must be established, not vicariously through the violator’s
knowledge, but by either the employer’s actual knowledge, or by its
constructive knowledge based on the fact that the employer could, under the
circumstances of the case, foresee the unsafe conduct of the supervisor.’ ” Id.
(quoting W.G. Yates & Sons Constr. Co. v. OSHRC, 459 F.3d 604, 609
n.8 (5th Cir. 2006)). Depending on the resolution of this issue, the judge may
allow both parties to “further develop[]” the record with evidence related to
the foreseeability of Smith’s unsafe conduct. See ComTran Grp., Inc.,
722 F.3d at 1318. If knowledge is established and the violation affirmed, the
judge must then address whether the violation was properly characterized as
willful by the Secretary and determine an appropriate penalty.
III. Willful
Citation 2, Item 2 – 29 C.F.R. § 1926.703(a)(2) (formwork drawings)
Under this
item, the Secretary alleges that Southern Pan failed to “obtain a reshoring
drawing, including all revisions, for the reshoring design method of using two
levels of reshores, exposing employees to a structural collapse hazard.” Section
1926.703(a)(2) provides that “[d]rawings or plans, including all revisions, for
the jack layout, formwork (including shoring equipment), working decks, and
scaffolds, shall be available at the jobsite.” The judge affirmed the
violation, finding that Southern Pan removed shoring and reshoring from the
garage without having a revised plan available on site that allowed for such
removal. We find that the Secretary established Southern Pan’s noncompliance
with the cited provision, but direct the judge on remand to determine if the
issue of knowledge as presented by this item is affected by the court’s
decision in ComTran. First, however, we address Southern Pan’s threshold
arguments relating to preemption.
Preemption
Southern Pan
contends that the Secretary cannot cite it under § 1926.703(a)(2) for its
alleged failure to have on-site plans allowing for shoring removal
because, it claims, that provision governs shoring installation;
§ 1926.703(e), by contrast, specifically governs shoring removal and does
not require an employer to obtain drawings before removing formwork. In response, the Secretary maintains that there is nothing in
the cited provision that limits its requirements to installation and,
therefore, “the two provisions impose different, concurrent requirements to
address different conditions.”
We find that
the text and structure of § 1926.703 support the Secretary’s position.
Subsection (a) provides general requirements for formwork—including a requirement
that all drawings for all formwork “shall be available at the jobsite”—and
subsections (b), (c), (d), and (e) impose other specific obligations concerning
the formwork. See Unarco Commercial Prods., 16 BNA OSHC 1499, 1502,
1993-95 CCH OSHD ¶ 30,294, p. 41,732 (89-1555, 1993) (“[T]he test for the
applicability of any statutory or regulatory provision looks first to the text
and structure of the statute or regulations whose applicability is
questioned.”). The specific obligation imposed by subsection (e) addresses the
removal of formwork based either on compliance with plans or specifications
that stipulate the conditions for the removal of forms and shores, or
measurement of the concrete’s compressive strength.
In this
respect, the obligation under subsection (a) to have drawings available on the
jobsite clearly extends to any drawings or plans an employer might develop to
comply with subsection (e). As such, subsection (e) complements, but does not
preempt, subsection (a). Indeed, the requirement under § 1926.703(a)(2) to
have “[d]rawings or plans, including all revisions for the jack layout formwork
. . . available at the jobsite” complements the requirement under
§ 1926.703(e)(1)(i) that one method of removing formwork is to follow
those onsite “plans and specifications stipulat[ing] conditions for removal of
forms and shores.” Cf. McNally Constr. & Tunneling Co., 16 BNA OSHC
1879, 1883, 1994 CCH OSHD ¶ 30,506, p. 42,170 (No. 90-2237, 1994) (basing
its finding of preemption, in part, on a determination that “the two standards
are not additive and complementary, but instead directly conflicting”),
aff’d, 71 F.3d 208 (6th Cir. 1995). See generally Gade v. Nat’l Solid
Wastes Mgmt. Ass’n, 505 U.S. 88, 98-99 (1992) (instructing that “the
provisions of the whole law” guide the determination as to whether the Act
preempts a state regulation) (citations omitted). Further, subsection (b)(1)’s
requirement that employers inspect all shoring equipment before installation to
ensure the equipment meets the specifications in the formwork drawings is
facilitated by subsection (a)(2)’s requirement to have all drawings and
revisions on site. Accordingly, we conclude that the duties imposed by
§ 1926.703(a) are not preempted by those imposed by § 1926.703(e).
Compliance
Southern Pan
next claims that it had all “available” plans on site and, in any event, it
“fulfilled its responsibilities [under the standard] when . . . Synergy secured
the approval of the [E]ngineer of [R]ecord . . . by e-mail” for the shoring and
reshoring removal. We disagree with both of these contentions. An employer’s
obligation to create a drawing or plan that accurately represents the existing
formwork is clear from the language of § 1926.703(a)(2), which requires
that the “[d]rawings or plans, includ[e] all revisions.” Indeed, OSHA has
recognized that this provision is intended to prevent accidents that could
result from improperly erected formwork, and written plans enable this
protective purpose to be met. Concrete and Masonry Construction Safety Standards,
53 Fed. Reg. 22,612, 22,624-26 (June 16, 1988) (“Without the drawings or plans
immediately accessible at the job site, questions regarding the design and
integrity of the forms or shoring layout cannot be properly addressed.”). As
the judge here correctly stated in his decision: “The requirement that all
plans, including revisions, be present on site is not a mere technicality.
Formwork is designed to transfer weight from the structure. Prematurely
removing formwork without an engineer’s revisions exposes employees to
structural collapse. Without the correct plans on site, crucial information is
missing.” See Major Constr. Corp., 20 BNA OSHC 2109, 2110-11, 2004-09
CCH OSHD ¶ 32,860, p. 53,041 (No. 99-0943, 2005) (affirming violation of
§ 1926.703(a)(2) based on judge’s finding that employer lacked formwork
plans, which exposed employees to hazard of possible collapse), aff’g in
relevant part, 2001 WL 392470, at *36 (OSHRC ALJ, Apr. 19, 2001) (judge’s
decision addressing § 1926.703(a)(2)).
Other subsections
in § 1926.703 are written such that the duty to have drawings or plans
“available at the worksite” contemplates that such plans—including any
revisions—will be reduced to writing. As the Secretary points out, this duty to
have revised plans that “exist” is clarified by § 1926.703(b)(1)’s
requirement that an employer inspect the shoring equipment “to determine that
the equipment meets the requirements specified in the formwork drawings.” See
Custom Built Marine Constr. Co., 23 BNA OSHC 2237, 2239, 2013 CCH
OSHD ¶ 33,258, p. 56,310-11 (No. 11-0977, 2012) (different provisions in a
regulation should be read in context of regulation as a whole). While §
1926.703(e) creates certain exceptions to this requirement, there is no
indication that any exception applies to the facts here.
To read the
cited provision as Southern Pan urges would allow an employer to dispense with
any revisions and simply rely on outdated drawings that do not reflect actual
conditions at the jobsite. See Unarco Commercial Prods., 16 BNA OSHC at
1502, 1993-95 CCH OSHD at p. 41,732 (“It is well established that . . . a
standard must be construed so as to avoid an absurd result.”) (citing
Griffith v. Oceanic Contractors, Inc., 458 U.S. 564 (1982)); see also
Am. Fed’n of Gov’t Emps., Local 2782 v. FLRA, 803 F.2d 737, 740 (D.C. Cir.
1986) (“[R]egulations are to be read as a whole, with each part or section . .
. construed in connection with every other part or section.”) (internal
quotation marks and citation omitted); E. Smalis Painting Co., 22 BNA
OSHC 1553, 1580-81, 2009-12 CCH OSHD ¶ 33,303, p. 54,370-71 (No. 94-1979, 2009)
(interpreting cited provision in context of entire standard and its overall
purpose). Such a position is unreasonable and would render the standard
meaningless.
Contrary
to Southern Pan’s claim, we do not find a lack of notice of the requirement to
have revised plans on site. See S. G. Loewendick & Sons Inc. v. Sec’y of
Labor, 70 F.3d 1291, 1297 (D.C. Cir. 1995) (“Congress and the courts
require that agency action reflect clear, rational decisionmaking that gives
regulated members of the public adequate notice of their obligations.”)
(citations omitted). Smith and Postma both testified that they recognized the
obligation to have accurate plans available on site inasmuch as they knew not
to deviate from the original plan before a revision was received. According to
Postma, he told his superintendents all the time “that the plans had to be on
site” and emphasized that the work always needed to be done “according to the
drawings [because t]he drawings that are on site [are] the Bible of what you’re
going by.” Smith testified that Southern Pan had contracted with Universal for
one specific reason—to inspect Southern Pan’s shoring and reshoring and make
sure it complied with the drawings. Without written, accurate drawings on site,
it would have been impossible for Universal to assess whether or not the
formwork complied with the drawings. Both by the plain terms of the standard
and Southern Pan’s admission regarding its obligation, we find that Southern
Pan had prior notice of what was required for compliance with the standard. Diamond
Roofing Co. v. OSHRC, 528 F.2d 645, 649 (5th Cir. 1976) (noting
well-settled principle that a regulation should be construed to give effect to
the natural and plain meaning of its words).
Equally
unavailing is Southern Pan’s argument that it complied with the standard. The
parties stipulated that Patent provided the sole signed and sealed shoring and
reshoring drawings for the garage that were available on site and that these
drawings included a “typical reshore diagram that shows the garage to have
shoring and/or reshoring to the ground.” Contrary to the on site plans,
Southern Pan removed the reshoring on October 22 and 26, several days before
the Engineer of Record sent his e-mail to Synergy, so it is impossible that the
e-mail could have led Southern Pan to believe it was in compliance with
§ 1926.703(a)(2) at that time. In fact, there is no evidence that Southern
Pan even knew of the e-mail’s existence before the garage collapsed. When Southern Pan removed reshoring from the garage, changing
to the one-over-two method, the formwork was no longer consistent with Patent’s
on-site drawings; thus, it was not in compliance with § 1926.703(a)(2).
Exposure
and Knowledge
We turn now
to the remaining elements of the Secretary’s burden of proving a violation—that
its employees had access or exposure to the violative condition and that
Southern Pan either knew or could have known of the condition with the exercise
of reasonable diligence. See Astra Pharm Prods., Inc., 9 BNA OSHC 2126,
2129, 1981 CCH OSHD ¶ 25,578, p. 31,900 (No. 78-6247, 1981) aff’d in
pertinent part, 681 F.2d 69 (1st Cir. 1982). Exposure has been established because
Southern Pan’s employees were removing reshoring without having revised
drawings on site; therefore, they were exposed to the hazard of a possible
structural collapse. Regarding knowledge, however, the Eleventh Circuit’s
decision in ComTran could affect the judge’s finding of actual
knowledge, which he based on superintendent Smith’s admission that Southern Pan
“did not have a revised plan on site” and acknowledgment that “OSHA required it
[to] have one.” In this regard, the judge appears to have imputed Smith’s
knowledge of his own failure to obtain the required revised plan. Thus, on
remand, the judge should consider whether the knowledge issue as presented by
this citation item is affected by ComTran, and depending on the judge’s
resolution of this issue, may allow both parties to “further develop[]” the
record with evidence related to Southern Pan’s foreseeability of Smith’s
misconduct. See ComTran, 722 F.3d at 1318. Accordingly, we conclude that
Southern Pan failed to comply with 29 C.F.R. § 1926.703(a)(2), but we
direct the judge on remand to reconsider whether the Secretary has established
knowledge. If knowledge is established, the judge should reconsider whether the
violation was properly characterized as willful and determine an appropriate penalty.
ORDER
We vacate the judge’s decision as
to Item 1, and vacate his decision in part as to Item 2, and remand this case
to the Chief Judge for reassignment and further proceedings consistent with
this decision.
SO ORDERED.
/s/
Thomasina
V. Rogers
Chairman
/s/
Cynthia
L. Attwood
Dated: December 18,
2014 Commissioner
MacDOUGALL, Commissioner, concurring in
part and dissenting in part:
I join the
majority’s opinion with regard to its discussion of the deliberative process privilege
and Citation 2, Item 2, which alleges a violation of 29 C.F.R. § 1926.703(a)(2)
(availability of formwork plans at jobsite). However, it is clear to me that the judge’s
well-reasoned approach to Citation 2, Item 1 was correct on the merits, and he
properly vacated this item, which alleges a violation of 29 C.F.R. §
1926.701(a) (placement of construction loads), because the standard is
inapplicable to Southern Pan. Accordingly, I dissent from the
majority’s opinion regarding this citation item.
As a preliminary determination, the Secretary’s burden of
proving a violation of a cited standard, as always, is whether the
standard applies to the cited condition.
In other words, it must be possible
for the cited employer, in this case Southern Pan, to violate the standard.
Here, as the judge properly concluded, the plain language of the standard
indicates that the only employers subject to the standard are those placing the
construction loads. The preamble to the final rule clarifies that § 1926.701(a)
applies to an employer “directly responsible for the concrete operations.” That employer is not Southern Pan.
My colleagues do not disagree with my conclusion that
Southern Pan is not directly responsible for concrete operations. Rather, the
majority remands this case for a determination as to whether Southern Pan
violated § 1926.701(a) as an “exposing employer” under the multi-employer
worksite doctrine. However, the Secretary’s multi-employer citation policy
rests upon section 5(a)(2) of the Act, 29 U.S.C. § 654(a)(2), which provides
that an employer “shall comply with occupational safety and health standards
promulgated under this [Act].” As Chairman Rogers noted in her concurring and
dissenting opinion in C.T. Taylor Co., Inc. and Espirit Constructors
Inc., 20 BNA OSHC 1083, 1094, 2002-04 CCH OSHD ¶ 32,659, p. 51,347 (No.
94-3241, 2003) (consolidated), the multi-employer worksite doctrine “serves to
allocate responsibility and liability among multiple corporate actors.” What
the majority opinion fails to acknowledge here is that in promulgating §
1926.701(a), the Secretary has already determined that in the multi-employer
construction worksite the allocation of responsibility and liability under this
specific standard is limited to those placing the construction load;
specifically, “the person directly responsible for the concrete
operations.” Concrete and Masonry Construction Safety Standards, 53 Fed. Reg.
22,612, 22,617 (June 16, 1988) (preamble to final rule); see Martin v. Am.
Cyanamid Co., 5 F.3d 140, 145 (6th Cir. 1993) (holding preamble to
regulation may be consulted in determining administrative construction and
meaning of regulation); Phelps Dodge Corp., 11 BNA OSHC 1441, 1444,
1983-84 CCH OSHD ¶ 26,552, p. 33,920 (No. 80-3203, 1983) (stating standard’s
“preamble is the best and most authoritative statement of the Secretary’s . . .
intent”), aff'd, 725 F.2d 1237 (9th Cir. 1984). Extending liability to
additional employers is thus contrary to the language of the standard.
Additionally, as I discussed in my concurring opinion in Ryder Transp.
Servs., 24 BNA OSHC 2061, 2064, 2014 CCH OSHD ¶ 33,412, p. 57,383 (No.
10-0551 2014), I do not believe that the Secretary’s Multi-Employer Citation
Policy can be used as a tool to reach an
employer otherwise excluded from the application of a standard. In viewing the
facts, the plain language of the standard and its preamble, and the required
elements of proof, I conclude that the Secretary cannot meet his burden of
proving that the cited standard applies to Southern Pan.
My colleagues assert that my analysis expressed herein
ignores forty years of Commission precedent and the “fundamental principle”
that an employer always has an obligation to protect its own employees from a
known hazard. The majority’s reasoning misses the mark. This case is not about
the indisputable proposition that an employer has a duty to protect employees
under all applicable standards; rather, it is about the question of whether a
specific standard applies in the first place. Further, in claiming there is
forty years of Commission precedent in support of the majority’s opinion, my
colleagues fail to cite a single Commission case that holds an employer
responsible, even as an “exposing employer,” for violating a specific-duty
standard that charges only certain, specifically identified employers with
responsibility for the working conditions addressed by it. My colleagues depart
from long-standing Commission precedent that it is the Secretary’s burden to
prove the standard applies to the cited condition (see footnote 2, supra);
further, “there can be no violation of the Act by a respondent for failure to
comply with a standard which charges some other employer with the duty of
implementing the standard.” Se. Contractors, Inc., 1 BNA OSHC 1713, 1716, 1973-74 CCH OSHD ¶ 17,787, p. 22,149 (No. 1445, 1974) (dissent by
Chairman Moran adopted on appeal, 512 F.2d 675 (5th Cir. 1975) (per curiam)). See also Unarco Commercial Prods., 16 BNA OSHC at 1499, 1993-95 CCH OSHD at p. 41,729
(vacating citation based on the plain language of the standard, and stating
that “the test for the applicability of any statutory or regulatory provision
looks first to the text and structure of the statute or regulations whose
applicability is questioned”) (citations omitted). Thus, I conclude that the
judge correctly found that the cited standard is inapplicable to Southern Pan.
Given the plain language of the cited standard and the
preamble to the final rule, which clearly contemplated but then rejected
a broader application of the standard, I would find it fundamentally unfair to
apply the cited standard to Southern Pan.
An employer lacking fair notice of a
standard cannot be found in violation of the Act for failure to comply with
that standard. E.g., S.G. Loewendick & Sons
Inc. v. Sec’y of Labor, 70 F.3d 1291, 1297
(D.C. Cir. 1995) (“Congress and the courts require that agency action reflect
clear, rational decision making that gives regulated members of the public adequate
notice of their obligations.”); Diebold, Inc. v. Marshall, 585 F.2d
1327, 1335-1339 (6th Cir. 1978); Cardinal Indus., 14 BNA OSHC 1008,
1011, 1987-89 CCH OSHD ¶ 28,510, p. 37,801 (No. 82-427, 1989). To the extent
that the Secretary’s choice of language does not effectuate what the Secretary
may have intended, the remedy lies in further rulemaking by the Secretary
rather than the adoption by this Commission of an interpretation that is not
supported by the standard and its preamble as promulgated. See Diamond
Roofing v. OSHRC, 528 F.2d 645, 650 (5th Cir. 1976) (regulations cannot be
construed to mean what an agency intended but did not adequately express).
For these reasons, I conclude that Citation 2, Item 1 was
properly vacated.
/s/
Heather
L. MacDougall
Dated: December 18, 2014 Commissioner
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1924 Building - Room 2R90, 100 Alabama Street, SW
Atlanta, Georgia 30303-3104
Appearances:
Dane Steffenson, Esq., U. S. Department of
Labor, Office of the Solicitor, Atlanta,
Georgia
For Complainant
J. Larry Stine, Esq., and Mark Waschak,
Esq., Wimberly, Lawson, Steckel, Schneider & Stine, P. C.,
Atlanta, Georgia
For Respondent
Before:
Administrative Law Judge Ken S. Welsch
DECISION
AND ORDER
Southern Pan Company (SP) is a concrete
formwork contractor. General contractor Choate Construction Company
subcontracted SP to install the shoring and formwork for a new six-story garage
and adjacent condominium tower, known as the Berkman Plaza II project, in
Jacksonville, Florida. On December 6, 2007, the garage collapsed as
subcontractor A. A. Pittman and Sons poured the concrete for the sixth level
roof. More than 20 workers were seriously injured, and SP employee Willie
Edwards was killed.
Occupational Safety and Health
Administration (OSHA) compliance officer Henry Miller conducted an inspection
of the worksite after the collapse. As a result of the inspection, the
Secretary issued serious and willful citations to SP on June 2, 2008. SP timely
contested the citations.
Item 1 of citation no. 1 alleges a serious
violation of 29 C. F. R. ' 1926.21(b)(2), for failing to instruct each employee
in the recognition and avoidance of unsafe conditions. Item 2 of citation no. 1
alleges a serious violation of 29 C. F. R. ' 1926.703(b)(7), for subjecting
shore heads and similar members to eccentric loading for which they had not
been designed. The Secretary proposed a penalty of $ 2,500.00 for item 1 and $
5,000.00 for item 2.
Item 1 of citation no. 2 alleges a willful
violation of ' 1926.701(a), for failing to determine, based on information
received from a person who was qualified in structural design, that the
structure or portion of the structure was capable of supporting the loads. Item
2 of citation no. 2 alleges a willful violation of 29 C. F. R. ' 1926.703(a)(2)
for failing to have drawings or plans available at the worksite. The Secretary
proposed a penalty of $55,000.00 for item 1 and $ 70,000.00 for item 2.
The court held an eight day hearing in
this matter, from May 18 to May 22, and from July 7 to July 9, 2009, in
Jacksonville, Florida. The parties stipulated jurisdiction and coverage (Exh.
J-A). Each party has filed a post-hearing brief.
SP denies the violations and contends the
Secretary failed to present a prima facie case for each of the alleged
violations. In its answer, SP asserted the affirmative defense of unpreventable
employee misconduct. SP no longer asserts that defense (Exh. J-A, & 23).
For the reasons discussed in this
decision, the court vacates both items of citation no. 1, and item 1 of
citation no. 2. The court affirms item 2 of citation no. 2, as willful, and
assesses a penalty of $ 40,000.00.
Facts
The parties stipulated to a number of
facts which are the primary source of the following facts, rearranged for
narrative purposes (Exh. J-A):
SP=s corporate headquarters are located in
Lithonia, Georgia. Choate hired SP to install the shoring and formwork on the
Berkman Plaza II project. The Berkman Plaza II project, located at 500 E. Bay
Street in Jacksonville, Florida, consists of a 23-story condominium tower and a
six-story parking garage. Both structures are constructed with poured-in-place
(also referred to as Acast-in-place@) concrete. Construction on the project
began in January 2006.
SP began work on the project in March
2006. SP was responsible for obtaining shoring and reshoring drawings for both
the garage and the tower, building the formwork, and placing the concrete for
some of the vertical pours. SP was not responsible for placing the concrete for
the horizontal pours, which included Pour 6A (6th level, A section),
the pour being made at the time of the collapse.
Various participants were involved in the
development and construction of the Berkman Plaza II project. They include the
following:
1. Berkman Plaza II, LLC
Berkman Plaza II, LLC (BPII), is the owner
of the project. BPII hired the architect, Pucciano and English, and the general
contractor, Choate. Under the Florida Building Code, BPII is responsible, as
owner, for ensuring that structures pass threshold inspection before proceeding
with safety-critical operations, as determined by state law (Exh. J-18).
2. Choate Construction Company
Choate is the general contractor on the
project. Choate=s project manage for the Berkman Plaza II project was Lawrence
Gilbert. Choate hired the subcontractors, including SP, and the threshold inspector
(Tr. 29).
3. Synergy Structural Engineering
Choate hired Synergy Structural
Engineering to meet Florida=s threshold inspection law. Synergy employed the
threshold inspectors Eric Cannon and Tim Frazier (Tr. 94-95).
4. Pucciano and English
Pucciano and English is the architecture
firm hired by BPII to create the design of the parking garage. Pucciano and
English is responsible for the project manual and specifications, and for the
general construction drawings. The firm hired the project=s engineer, Soheil
Rouhi (Tr. 35-36).
5. Soheil Rouhi
Soheil Rouhi is the engineer of record for
the project. Rouhi prepared the structural drawings, and signed and sealed
them. He drafted and/or approved the threshold inspection plan. Rouhi expected
the threshold inspector to verify the inspected structure to comply with the
approved plans and drawings, including the shoring and reshoring plans provided
by Patent Engineering.
6. Patent Engineering
As the formwork contractor, SP hired
Patent Engineering to provide its plans and drawings for shoring and reshoring
on the project. Patent provided the only signed and sealed drawings for the
shoring and/or reshoring. The drawings consisted of ten pages, eight of which
were full-size and the last two (pertaining to approval of replacing the
aluminum beams with 4x4 wood beams) were on 8.5-inch by 11.5-inch sheets of
paper. These drawings were available at the worksite. There were no other
written plans or drawings pertaining to the shoring and/or reshoring for the garage.
Patent=s drawings included a typical reshore diagram that shows the garage to
have shoring and/or reshoring to the ground.
7. Universal Engineering Sciences
SP hired Universal Engineering Sciences, a
professional engineering firm, to inspect the shoring and reshoring to
determine whether components were correctly constructed according to the plans
prepared by Patent (Tr. 83).
8. A. A. Pittman and Sons
Choate hired A. A. Pittman and Sons, a
concrete finishing company. Pittman and Choate were responsible for placing the
horizontal pours, including Pour 6A. Pittman poured the concrete slabs in the
garage at depths of 8 inches, 16 inches, and 20 inches (Exh. J-11). It poured
slabs in the tower at depths of 8 or 9 inches (Tr. 371).
On October 22, 2007, SP, when placing
shoring under the fifth level of the garage, began to remove some of the
shoring and reshoring from the first level in the section where there were no
20-inch slabs. On October 26, 2007, SP removed some shoring and reshoring from
the second level in the section where there were no 20-inch slabs. On November
19, 2007, SP started removing some of the shoring and reshoring between the
ground and the third level (referred to as the Ahigh bay area@).
Pittman performed Pour 5A on November 7,
2007; Pour 5B on November 20; and Pour 6A on December 6. Pour 6A was for the
sixth level roof of the garage. On December 6, at approximately 6:15 a.m., the
parking garage from column line GA to column line GG (approximately 70% of the
garage), collapsed to the ground (Apancaked@) as the concrete was poured. SP
employees Willie Edwards and Roland Hawkins were on the fifth level, below the
pour, ready to clean off any excess concrete. The collapse killed Edwards and seriously injured Hawkins and other
contractor employees.
OSHA=s assistant area director Jeff Romeo
and a compliance officer arrived at the site the day of the collapse. At that
time, and for the next several days (the body of Edwards was not recovered for
three days), only rescue personnel were allowed in the garage area. Compliance
officer Henry Miller arrived at the site the following Monday or Tuesday. He
was accompanied by Mohamed Ayub, OSHA=s director of engineering. Miller and
Ayub observed the collapsed area from a manlift on the north side of the
garage. They took photographs of the collapsed area. Miller also conducted
interviews and obtained documents from SP (Tr. 772).
As a result of the OSHA inspection, the
serious and willful citations were issued to SP on June 2, 2008.
Citation No. 1
The Secretary has the burden of proving
the violation by a preponderance of the evidence.
In order to establish a violation of an occupational safety or
health standard, the Secretary has the burden of proving: (a) the applicability
of the cited standard, (b) the employer=s noncompliance with the
standard=s terms, (c) employee access to the violative conditions, and (d) the
employer=s actual or constructive knowledge of the violation (i.e., the
employer either knew or, with the exercise of reasonable diligence could have
known, of the violative conditions).
Atlantic Battery Co., 19 BNA OSHC 2131, 2138 (No. 90-1747,
1994).
Item 1: Alleged Serious Violation of '
1926.21(b)(2)
The citation alleges SP
Adid not instruct the laborers on how to read the plans and drawings to
recognize hazards when removing reshores from a concrete structure.@ Section 1926.21(b)(2) provides:
The employer shall instruct each employee in the recognition and
avoidance of unsafe conditions and the regulations applicable to his work
environment to control or eliminate any hazards or other exposure to illness or
injury.
SP stipulated that '
1926.21(b)(2) applies to the work SP was performing at the worksite (Exh. J-A,
& 13). SP also stipulated it Adid not instruct the laborers on how to read
the plans and drawings@ (Exh. J-A, & 26). SP contends that the concrete
formwork industry does not recognize the duty to instruct laborers in how to
read plans and drawings. SP also contends any violation for failing to train
Roland Hawkins is barred by the six-month statute of limitations for OSHA
violations.
Section 1926.21(b)(2)
requires an employer to Ainstruct its employees in the recognition and
avoidance of those hazards of which a reasonably prudent employer would have
been aware.@ Pressure Concrete Constr. Co., 15 BNA OSHC 2011, 2015 (No.
90-2668, 1992). AAn employer=s instructions are adequate under ' 1926.21(b)(2)
if they are specific enough to advise employees of the hazards associated with
their work and the ways to avoid them.@ Model Continental Construction Co., 19
BNA OSHC 1760 (No. 00-1629, 2001).
Compliance officer
Henry Miller testified he recommended the Secretary issue the citation based on
his questioning of SP president Ken Dickey. Dickey told Miller he did not train
SP laborers how to read plans and drawings. Miller did not research whether
other formwork contractors train their employees in reading plans and drawings,
and he did not know what the industry standard for training laborers in reading
plans and drawings is (Tr. 953).
In determining the duty
of a Areasonably prudent@ employer,
Reasonableness is an objective test which must be determined on
the basis of evidence in the record. Industry standards and customs are not
entirely determinative of reasonableness because there may be instances where a
whole industry has been negligent . . . . However, such negligence on the part
of a whole industry cannot be lightly presumed. Diebold Inc. v. Marshall, 585
F.2d 1327, 1336 (6th Cir. 1978). It must be proven.
Ray Evers Welding v. OSHRC, 625 F.2d 726, 732 (6th
Cir. 1980).
Patrick Marchman, SP=s
safety director, testified it is not the construction industry=s standard to
teach laborers how to read plans and drawings (Tr. 1058). SP president Ken
Dickey also stated it is not the industry standard (Tr. 1124).
Dr. Stanley Lindsey is
a professor of environmental and civil engineering at Georgia Tech Savannah. He
has a Ph.D. in Structural Engineering from Vanderbilt University (Exh. R-8).
The court qualified Dr. Lindsey as an expert in structural engineering and
cast-in-place concrete (Tr. 1222). Dr. Lindsey addressed the issue of
training people in how to read plans and drawings:
You know, at Tech, in order to familiarize a student to be able to
really use Auto CAD, to read drawings and to do that sort of thing, we take
them for two semesters and teach them the basis of engineering drawings and
engineering calculations. And, to think that you=re going to take a laborer out
in the field and within ten hours or a week teach him how to read drawings,
that=s not going to happen. If you could, we certainly wouldn=t be spending two
semesters at Tech doing that. I=ll tell you that right now. We have more
important things to do (Tr. 1187).
The Secretary adduced
no evidence establishing it is the formwork industry=s standard to train
laborers to read plans and drawings. Research on this issue failed to turn up a
single case where the Secretary cited an employer for failing to train its
laborers to read plans and drawings. Such training usually requires a certain
degree of education and technical training that is beyond what an employer can
reasonably be expected to provide to laborers. The Secretary has failed to
establish ' 1926.21(b)(2) requires employers to train their laborers to read
plans and drawings.
Although the citation
specifies SP=s alleged violation is not instructing its laborers Aon how to
read the plans and drawings,@ the Secretary attempts to broaden the alleged
violative conduct. In her post-hearing brief, she states, ASP violated this
standard by not training its laborers on all formwork standards and hazards
applicable to their work@ (Secretary=s brief, p. 14, emphasis added).
James Borders is OSHA=s
area director of the Jacksonville office (Tr. 843). When asked if OSHA was
contending there is a recognized hazard for failing to train laborers to read
plans and drawings, Borders replied:
No, sir, not so much plans and drawings, but I think the intent
here was that they should be familiar that they do exist and what is the
purpose of those things. The employer does have an obligation, as the standard
says, to educate their employees about what standards apply to their work. As
you know, plans and drawings are very important to this type of work. I think
the intention here was that the employer had an obligation to make sure that
their laborers were aware that plans existed, that they had to be followed,
they had to be approved and things of that nature (Tr. 866).
Later, Borders was
asked if the Secretary cited SP for failing to train its laborers to read plans
and drawings. Borders stated, AI believe the intent was more broader than that.
But, yes, that=s what the alleged violation description said, and it could have
been written better than that@ (Tr. 889).
In her post-hearing
brief, the Secretary argues SP knew Athat the basis of this training citation
was that SP employees were not >trained about the standards that apply to
their work=@ (Secretary=s brief, p.15, footnote 10). The Secretary declined to
amend the citation to allege SP failed to train its laborers on all formwork
standards and hazards applicable to their work.
SP did not impliedly consent to try the
broader issue of training laborers in all formwork standards and hazards.
Indeed, SP expressly and repeatedly objected to broadening the scope of the
citation (Tr. 279, 384, 627). Counsel for SP stated, AWe=ve stipulated to the
language in the citation that we had not trained our hourly employees on any of
the blueprints and drawings. We want to preserve our objections that we=re not
trying this by consent, any other issue as to the training@ (Tr. 277). An amendment
under Rule 15(b)(2) of the Federal Rules of Civil Procedure Ais proper only if
two findings can be made-that the parties tried an unpleaded issue and that
they consented to do so.@ McWilliams Forge Co., 11 BNA OSHC 2128, 2129
(No. 80-5868,1984). The Secretary did not move to amend the citation to allege
SP failed to train its laborers on all formwork standards, and the court
declines to do so now sua sponte.
The Secretary has failed to establish a violation of '
1926.21(b)(2). Item 1 is vacated.
Item 2: Alleged Serious Violation of '
1926.703(b)(7)
The citation alleges the wood blocks SP placed
on top of the scaffold jack screw plates Awere not plumb, exposing employees to
a structural collapse hazard.@ Section 1926.703(b)(7) provides:
Eccentric
loads on shore heads and similar members shall be prohibited unless these
members have been designed for such loading.
SP stipulates ' 1926.703(b)(7) applies to
the work it was doing at the Berkman Plaza II site (Exh. J-A, & 13). SP
argues the Secretary offered no evidence establishing the wood blocks were not
plumb prior to the garage collapse.
Shoring is placed on the level that
currently is being built. It is used to hold the formwork prior to pouring the
concrete (Tr. 467). Reshoring is placed on the completed levels below the
current level being built. Reshoring does not support the structure itself; its
purpose is to carry the load of the wet concrete placed on the upper level (Tr.
1452).
SP=s shoring consisted of frame scaffolds
of different heights (3 feet, 6inches; 5 feet; and 6 feet) with screw jacks on
top of each of the frame=s four corners. Employees could adust the height of
the screw jacks. On top of the screw jacks were shore heads, and on top of the
shore heads were aluminum I-beams that supported 4"x4" laminates
placed perpendicular to the I-beams. SP employees placed plywood on top of the
laminates, onto which the concrete was poured (Tr. 238-239).
For SP=s reshoring, employees would remove
the plywood, the 4"x4" laminates, and the aluminum I-beams. They
would replace these materials with Apost-shore heads@ (PSHs) or Apost header extensions.@
These are 12- inch long 4"x4" wood blocks that employees placed
either upright or lying flat on top of the shore heads. The employees would
then adjust the screw jack so that the PSHs were snug up beneath the previously
poured concrete levels (Tr. 270-272).
SP received most of its 4"x4"
blocks from SP=s yard in Atlanta, where they were cut with a table saw. The
table saw made a single cut all the way through the wood, so that the cut
surface was smooth and flat. SP superintendent James Smith testified his
employees had to cut some 4"x4"s in the field, using a Skil saw.
Smith explained the method for cutting with a Skil saw: AYou take a speed
square, mark it all the way around so you have a line, a pencil line, all the
way around on square, cut it through, flip it over and cut it through following
the line@ (Tr. 274). Sometime this method left the cut surface uneven. Smith
testified he discarded those blocks:
There were
a few of them like that on the job, but I would have those taken away. We
wouldn=t use them. [Labor foreman] Drew [Linderman] knew that we couldn=t use
those and would discard them to the side. If some of his laborers had used
them, they would be swapped out and replaced with the correct ones
. . . .
If it was
a sixteenth of an inch, I would let it go. If it=s three-sixteenths of an inch,
it got discarded (Tr. 275).
SP=s employees would set aside the
rejected 4"x4" blocks. The clean-up crew routinely ran late on this
project, so the rejected blocks were not removed immediately: AProbably not at
that particular moment, no. When the cleanup crew came through, then, yes.
Anything lying down, 4"x4"s or any trash or material that had been
cut, laying on a slab, then they would be discarded by the clean-up crew@ (Tr.
275). Smith stated that not all of the wood blocks were used as PSHs. Some were
used as Akickers@ to keep the forms in place, some were used for bracing, and
some were used for dunnage (Tr. 342-342).
The Secretary contends SP used some of
these double-cut blocks as PSHs. Because the surfaces of these PSHs were
uneven, the Secretary argues, they did not fit plumb on the shore heads,
causing them to carry an eccentric load. The Secretary relies primarily on the
testimony of three witnesses, John Czerepka, Roland Hawkins, and Mohamed Ayub,
to establish SP violated the terms of ' 1926.703(b)(7).
John Czerepka is a project engineer with
Bracken Engineering (Tr. 462). After the garage collapse, Bracken was hired to
Acome up with a demolition protocol on how to take apart the collapsed debris
and also the standing portion, and how to save evidence and documentation of
that evidence. . . A(Tr. 463). Czerepka worked with other Bracken employees to
remove reshoring from the structure on the east side of the garage (Tr.
466-467).
Bracken=s employees removed the reshoring
assemblies, marked them, and attached them to the scaffold frames with zip
ties. Bracken then placed the units in a storage container (Tr. 468). Czerepka
testified he uncovered hundreds, perhaps thousands, of 4"x4" wooden
blocks in the rubble (Tr. 470). He retained approximately 20 of these blocks,
chosen at random, as a representative sample of blocks on the site (Tr. 473).
Exhibit C-6 is a copy of a photograph
showing eleven of the blocks, standing on their ends (Tr. 476). Czerepka
brought two of the blocks to the hearing on May 20, 2009. Using a tape measure,
Czerepka demonstrated a difference of 3 inch on the surface of one block, and
of c inch on the other (Tr. 485). Czerepka could not say that these two blocks,
or the blocks shown in Exhibit C-6, were used as PSHs. He conceded the two
blocks he brought in appeared to be waterlogged, indicating they were stored on
the ground (Tr. 496).
Roland Hawkins was the SP=s lead carpenter
on the vertical crew for the garage. He began working for SP approximately four
months before the collapse (Tr. 616). At the time of the collapse, Hawkins was
standing next to Willie Edwards on the fifth level of the garage, Awatching the
forms for leakage or blowouts@ (Tr. 617). Hawkins was seriously injured in the
collapse.
Hawkins testified he observed some of the
double cut 4"x4" blocks used by SP employees (Tr. 630-631): AI would
say that there were uneven cut boards used as reshoring; not the majority of
them, but maybe a small percentage, you know. It=s just grab what you can and
stick it in there and go.@ Hawkins worked on the leading edge at the top level
of the structure most of the time, but he did occasionally help erect or
dismantle reshoring. He also observed the reshoring on the lower levels as he
walked up and down the ramps (Tr. 631, 635). He stated that, as he went up and
down the ramps, he sometimes observed reshoring that was not plumb, Abut not to
the point where I was afraid to go to work@ (Tr. 632). Hawkins was not
questioned as to the date or dates he observed the PSHs that he thought were
out of plumb.
Hawkins testimony regarding to the
condition of the wooden blocks is not given weight because he did not identify
the dates of his observations and his memory apparently has been affected by
his injuries and treatment. He candidly discussed his personal problems and
when asked if his memory had been affected since the collapse, Hawkins
responded, AAbsolutely, yes. . . . It doesn=t have anything to do with my
recollection@ (Tr. 636-637, 664).
Superintendent Smith, carpenter foreman
James Ferrell, and Synergy threshold inspector Eric Cannon all testified that
the reshoring was constantly checked for plumbness. If any reshoring was found
out of plumb, it would be corrected immediately (Tr. 340, 740, 1242).
Smith gave detailed testimony regarding the loads placed on the
PSHs. He testified that the PSHs would on occasion come loose:
If the slab above is being poured and they=re vibrating from the
concrete, hitting the deck from the pump, the vibrators themselves, and they
were only snug tightening them by hand anyway, and there=s no gauge saying how
tight you had to have these or have them torqued down to a certain strength,
there were occasions where there would be one or two here or there that would
work themselves loose and you had to go back.
You know, that was part of the inspection. You checked these
things. This is part of why they had to go through and inspect these, to make
sure. There were things like that that happened. It happens on every job (Tr.
338-339).
To ensure the PSHs were put back in plumb, Smith stated:
I had one
particularBI usually had one man and I would instruct Drew to send one man
through, ACheck all your reshore posts. Make sure they=re plumb and make sure
they=re snug and tight.@ (Tr. 340).
Smith testified that as of December 5,
2007, the PSHs had been checked by Univesal and found to be plumb. To ensure
the PSH=s remain plumb, Smith testified:
You go by and you grab it and if it don=t move, it=s good. If it
moves, it=s going to come out of plumb. I mean, it=s real simple (Tr. 340).
. . . .
We used levels, torpedo levels, two-foot levels, check out our
plumbness. Drew would toteBlike I said, when he was with Universal walking
through, he kept a torpedo in his pocket. If he had a question about something
not being plumb, the torpedo level goes on it to find out (Tr. 341).
Ferrell corroborated Smith=s account. He
testified that he, Smith, and Linderman all participated in the walk-around
inspection for Pour 6a. At that time, immediately before the December 6 pour,
all the PSHs Awere plumb and straight@ (Tr. 1244).
The testimony of Smith and Ferrell
specifically addresses the condition of the site Aon or about December 6,
2007,@ as alleged in the citation. It is given more weight regarding the
condition of the PSHs than Hawkins=s testimony, because there is no indication
of the date or dates Hawkins observed the PSHs out of plumb.
The Secretary adduced evidence it obtained
after the collapse in an attempt to show the PSHs were eccentrically loaded
before the collapse. Miller took photographs from the manlift of various PSHs
that appeared to him to be out of plumb (Exh. C-10). The Secretary rejects any suggestion the
garage collapse may have shaken the PSHs out of plumb. Ayub stated:
This is not a seismic event. This is not a ground motion which
relates to the whole event of acceleration, and vertical acceleration and the
rotation of the building.
Here,
we are dealing with a collapse. A collapse has taken place, essentially five
bays on the north, and there is damage done to three bays with the main
collapse upward.
That line of shoring which is very close to the fractured slab
surface . . .there could be some distortion and some movement on the line of
the shoring which is closest to where the fracture took place on the unfailed
part.
I was at the site, I observed the unfailed base. There was not
rotation, there was no tilting. It was all standing plumb (Tr. 1570-1571).
Dr. Lindsey disagreed with Ayub=s analysis.
He testified, A[W]hen the structure collapsed, . . .what I would consider to be
a large amount of force, and very difficult to calculate the exact quantity of,
was exerted on the garage, and it caused the garage to move. And, in moving, it
had the potential and probably the result of that movement, was to displace
some of those 4"x4"s that were in place@ (Tr. 1321-1322). He stated
there is no scientific basis to say the PSHs were not plumb prior to the
collapse (Tr. 1323). He also stated an engineer could not observe the
conditions of the PSHs post-collapse Aand make any viable conclusions about the
status of those blocks prior to the collapse@ (Tr. 1434).
Upon consideration of the evidence, the
court concludes the Secretary has fallen short of proving it was more likely
than not that PSHs were eccentrically loaded on or about December 6. The only
eyewitness who stated he observed PSHs out of plumb (that were not corrected
immediately) did not give a specific date for his observation. The record
establishes SP checked the PSHs constantly and immediately corrected any that
were out of plumb. The threshold inspector inspected the reshoring before the
December 6 pour and found the PSHs to be plumb. Smith, Ferrell, and Linderman
also inspected the reshoring prior to Pour 6A, and observed the PSHs were
straight and plumb.
The evidence gathered post-collapse also
fails to establish the PSHs were eccentrically loaded pre-collapse. There is no
evidence the double cut 4"x4" blocks recovered by Czerepka were used
as PSHs. Smith=s testimony establishes the blocks could have been used as
kickers, or bracing, or dunnage, or were discarded blocks set aside for the
clean-up crew to collect. The photographs admitted as Exhibit C-10 are
insufficient to establish the violation on two counts: first, it is not
possible, based on the photographs, to prove the plumbness or out-of-plumbness
of any of the PSHs. Second, even if the PSHs were conclusively established as
being out-of-plumb, the Secretary cannot establish this condition did not
result from the collapse itself. The court does not give weight to Ayub=s
opinion that the collapse could not have generated forces that would cause the
PSHs to shift. Smith testified the PSHs would shift during concrete pours, due
to vibrations from the pump and the vibrators (Tr. 338). Vibrations created by
pouring concrete do not exert the force of vibrations created by the collapse
of 70% of the parking garage. In the report Ayub submitted following his
investigation, he states, AThe collapse was massive . . .@ (Exh. C-15). The
enormity of the collapse, as amply demonstrated in the photographs, supports
the expert opinion of Dr. Lindsey, who stated the collapse most likely caused
the PSHs to move. Hawkins, the only witness who was actually in the garage at
the time of the collapse, stated the collapse Awas like being in a tornado of
steel and concrete. It was like being in a hurricane of steel and concrete@
(Tr. 666).
The Secretary has not established SP
failed to comply with the terms of ' 1926.703(b)(7). Item 2 is vacated.
Citation No. 2
Item 1: Alleged Willful Violation of ' 1926.701(a)
The original citation
alleged SP Adid not have a qualified person determine if the formwork with the
additional height added, would be capable of supporting the additional load of
the wet concrete, exposing the employees to a structural collapse hazard.@ Upon
the Secretary=s motion
(and over SP=s objection), the court amended the citation to
allege SP Adid not determine, based on information received from a person who
was qualified in structural design, the concrete garage structure or portion of
the concrete garage structure was capable of supporting the weight of the wet
concrete for pour 6A, exposing employees to a structural collapse hazard.@
Section 1926.701(a) provides:
No
construction loads shall be placed on a concrete structure or portion of a
concrete structure unless the employer determines, based on information
received from a person who is qualified in structural design, that the
structure is capable of supporting the load.
The parties stipulate the Secretary has
not issued any interpretations of ' 1926.701(a), other than the preamble to the
final rule (Exh. J-A, & 25). SP argues ' 1926.701(a) does not apply to it
because SP did not place the load of concrete on the structure.
In 1988, OSHA revised its regulations
concerning concrete formwork in order to eliminate redundancies, ambiguities,
and gaps resulting from prior regulations and the incorporation of ANSI
standards, and to establish a clear set of operating principles for employers
in the concrete construction industry. In the preamble to the final rule, the
Secretary states:
After
carefully considering all the comments and testimony received, OSHA has decided
to delete the requirement for the specified engineer-architect services. This
decision is based on the comments and testimony received which indicates that
engineer-architects frequently do not consider construction loads in the
design, nor do they approve their placement on partially completed structures.
However, OSHA believes that it is still important that someone be responsible
for performing this service. Therefore, OSHA is requiring that the employer
make the determination that the structure or portion of the structure is
capable of supporting the construction loads. The employer must make this
determination on the basis of information received from a person qualified in
structural design. This revision also places responsibility for employee
safety with the person directly responsible for the concrete operations.
Concrete and Masonry Construction Safety Standards, Final Rule, 53 FR 22612, 22617
(emphasis added) (Exh. J-20).
In this instance, the employers directly
responsible for the concrete operation are Choate, the general contractor, and
Pittman, the concrete finishing subcontractor. The Secretary concedes that
Choate Awould typically be responsible for making sure that a person qualified
in structural design provided information upon which contractors could
determine that it was safe to place construction loads on the structure being
built@ (Secretary=s brief, p. 30). The Secretary argues, however, that ASP
agreed and was contractually obligated to perform this responsibility for
Choate by being the contractor responsible for hiring the shoring engineer, who
would provided the information upon which this determination could be made via
the signed and sealed shoring and reshoring plans@ (Id.).
The
Secretary relies on paragraph 12 of Exhibit B of SP=s subcontract with Choate
to support her argument that the contract shifts the obligation of compliance
with ' 1926.701(a) from Choate to SP. Paragraph 12 states:
Furnish,
install, and maintains all necessary shoring and reshoring. Furnish all necessary
shore and reshore inspections. Furnish shoring and reshoring drawings, sealed
by engineer.
SP argues that the obligation to comply
with ' 1926.701(a) remained with Choate and Pittman, and further argues that
the employers fulfilled that obligation when Choate hired Synergy as its
threshold inspector.
The court agrees that SP was not
responsible for the placement of the concrete load on the structure. The
contents of paragraph 12 of the subcontract do not shift responsibility for the
concrete operations to the formwork subcontractor. Paragraph 12 of the
subcontract essentially paraphrases the requirements of ' 1926.703(a)(1), with
which SP is obligated to comply.
The Secretary stipulated, AA. A. Pittman
was the concrete finisher and along with Choate was responsible for placing the
horizontal pours, including Pour 6A@ (Exh. J-20 & 9). With this
stipulation, the Secretary has undercut her case that ' 1926.701(a) applies to
SP. The plain language of the standard indicates the employer placing the
construction load is the employer to whom the standard applies. The preamble to
the final rule further clarifies that the ' 1926.701(a) applies to the employer
Adirectly responsible for concrete operations.@ In the present case, that
employer was not SP.
Item 1 of citation no. 2 is vacated.
Item 2: Alleged Willful Violation of '
1926.703(a)(2)
The citation alleges SP Adid not obtain a
reshoring drawing, including all revisions, for the reshoring design method of
using two levels of reshores, exposing employees to a structural collapse
hazard.@
Section 1926.703(a)(2) provides:
Drawings
or plans, including all revisions, for the jack layout, formwork (including
shoring equipment), working decks, and scaffolds, shall be available at the
jobsite.
SP stipulates ' 1926.703(a)(2) applies to
the work it was doing at the Berkman Plaza II site (Exh. J-A, & 13). SP
argues it had all existing plans and drawings available at the site. The
dispute is whether SP was required to have a revised plan on site once it
removed reshoring from the lower levels, which was contrary to the plans on
site.
The stipulations pertinent to this issue
are (Exh. J-A):
1. Southern
Pan was responsible for obtaining shoring and reshoring drawings for both the
garage and tower, building the formwork and placing the concrete for some of
the vertical pours. (& 7)
2. Southern
Pan hired Patent to provide it plans and drawings for shoring and reshoring.
(& 14)
3. Patent
provided the only signed and sealed drawings pertaining to the shoring and/or
reshoring for the garage. These drawings consisted of 10 pages, eight of which
were full-size and the last two (2) pertaining to approval of replacing the
aluminum beams with 4x4 wood beams were on 8.5" by 11.5" sheets of
paper. These drawings were available at the worksite. There were no other
written plans or drawings pertaining to the shoring and/or reshoring for the
garage. (& 15)
4. The
Patent drawings included a typical reshore diagram that shows the garage to
have shoring and/or reshoring to the ground. (& 16)
5. Southern
Pan removed some of the shoring and reshoring from the first level in the
non-20" section of the garage beginning on or about October 22, 2007.
(& 17)
6. Southern
Pan was removing some shoring and reshoring from the second level of the
non-20" section of the garage on or about October 26, 2007. (& 18)
7. Southern
Pan started removing some of the shoring and reshoring between the ground and
the third floor, which is referred to as the high bay area, on or about
November 19, 2007. (& 19)
8.
Subsequent to the start of construction of garage, Southern Pan provided Choate
multiple copies of the shoring plan described above, but Choate misplaced at
least some of the copies. (& 22) (Exh. J-A)
Doug Rose is the Patent shoring engineer
who designed the shoring and reshoring plans for SP (Tr. 110-112). He testified
that for all of Patent=s designs, all levels of a structure are shored and
reshored (Ato the ground@) (Tr. 118). If SP decides not to shore to the ground,
then a separate engineering firm (SP used Dansco when it requested revised
plans for the tower) must calculate and create an new reshore plan to be signed
and sealed. Patent does not create reshore plans that do not go to the ground
(Tr. 122).
Rose stated that reshoring could not be
removed from the structure and still be in compliance with Patent=s plans
because Aof Patent=s policy, and that=s the way it was designed@ (Tr. 134).
Rose testified Patent=s plans called for the reshoring to be kept in place to
the ground until Athe end of the construction phase@ (Tr. 142).
Tim Postma, SP=s project manager,
testified the Patent drawings that showed reshoring going to the ground were
Awhat was intended to be used@ (Tr. 546). Superintendent Smith recognized SP
was required to follow Patent=s plans (Tr. 242): AYou don=t deviate from the
drawing sets that you have unless another engineer provides adequate, I guess,
paperwork or plans to change things. You never deviate from the plans, the
original things you got, until something else, a revision comes in.@ Despite
this recognition, Smith ordered his employees to remove reshoring from the
lower levels of the garage, beginning on October 26, 2007. Smith testified he
assumed Postma had requested Dansco to create a revised reshoring plan, in
which, instead of reshoring to the ground, SP would shore the top level and
only the two lower levels (A1-over-2" shoring) (Tr. 243).
Smith explained how his misunderstanding
arose:
There was a discussion among Tim Postma and Tim Marlow, the
superintendent of the tower, and myself. His drawings, original drawings from
Dansco, had got misplaced through the mail. There was a reordering process
going on with Tim Postma.
In discussing the drawings, I assumed he was doing mine at the
same time because when he was speaking to us, I felt like he was speaking to
both of us at the time and that my drawings were going to be with that second
set of drawings for the tower as well when they came in.
. . . .
[T]hat=s typical on every job. I mean, every job that we=ve done
since I=ve been with Southern Pan, that was the typical procedure (Tr. 244).
. . . .
Patent=s drawings always showed shoring or scaffolding to the
ground, the ground all the way up, whether it=s three stories or fifteen stories.
And, it was typical procedure to have it recalibrated where you
could use one floor of shoring and two floors reshoring, one over two. I had
worked with high-rises. That was the typical standard thing that was done (Tr.
245).
Postma testified Smith should have checked
Patent=s plans that were available at the site before he removed the reshoring
on the lower floors:
Jim Smith
should have looked at the drawings and, yes, if Jim Smith made a mistake and
took something out he shouldn=t have taken out, that was a mistake. And, that=s
the reason the other layer of Universal is there to catch those mistakes, and
at that point, if the mistake was caught, the shoring would have been put back
in place and we would have been back in accordance with the drawings that were
on the site (Tr. 552).
Postma agreed that Smith was qualified to
understand the need for shoring plans on site. He said ANo, he=s a qualified
superintendent. I have every faith in him to have done exactly as he should have.
It was a mistake.@
SP contends it did not violate the terms
of ' 1926.703(a)(2) because Synergy, the threshold inspector, Aby e-mail,
secured the approval of Rouhi, the engineer of record, for the removal of
reshoring from lower levels except for one area where Rouhi stated that the
reshoring should be retained@ (SP= brief, p. 35). This argument is rejected.
Synergy emailed Rouhi after SP began removing the reshoring because
Synergy wanted to clarify whether SP should be doing so (Exh. J-7). Furthermore, there is no evidence SP knew of
the existence of this email prior to the collapse (Tr. 759-760).
SP also argues it was not required to have
any plans in addition to the Patent plans already available on site. SP
contends, somewhat confusingly, it was not required to provide Amental plans,@
(Tr. 942). It is perhaps best to quote SP verbatim on this point (SP=s brief,
p. 36, emphasis in original):
Complainant=s
position appears to be that Southern Pan violated 29 C.F.R. ' 1926.703(a)(
2) not because all plans and drawings in existence were not available at
the site, but rather because plans and drawings that did not existBhad
not been created, but in OSHA=s opinion should have beenBwere not available.
Specifically, Complainant appears to be arguing that: (1) Patent=s reshoring
plans showed reshoring going all the way to the ground; that (2) Jim Smith was
using the A1-over-2"standard industry practice method, so Jim Smith must
have had a Amental plan@ which would, in the Secretary=s view, require him to
stay on site at all times in order to have the Aplan in his head@ on site; that
(3) Jim Smith had an obligation to revise the written plans to show removal of
reshoring in order to allow him to leave the site as he did; and that (5) [sic]
Smith=s alleged failure to either remain on site, or in the alternative, create
a drawing constitutes a willful violation of the standard. Such an
interpretation impermissibly contorts the natural meaning of the words in the
cited standard.
SP=s argument is rejected. The Secretary
is only arguing point (1) listed above, which is a fact stipulated to by both
parties. The Secretary is not arguing Smith was required to stay on site at all
times so that his Amental plan@ was available, nor is she arguing Smith should
have drawn up some plans himself. What she is arguing (and what Smith and
Postma both understood at the hearing) is that SP needed to have revised
shoring and reshoring plans on site before it began removing the reshoring.
Section 1926.703(a)(2) plainly states, ADrawings or plans, including all
revisions@ for shoring equipment must be available on site. Patent created
a set of plans for SP, showing reshoring going all the way to the ground. SP
decided to alter the way the reshoring was installed, which required a revised
plan to be on site. Both Smith and Postma understood this. Smith stated, AYou
never deviate from the plans, the original things you got, until something
else, a revision comes in@ (Tr. 242). Postma conceded Smith made a mistake in
removing the reshoring without a revised plan (Tr. 565): AWe discuss [plans
required to be on site] all the time. It=s an ongoing discussion. It=s an
ongoing discussion even on my job sites with my superintendents when I=m on the
job site. Always according to the drawings. The drawings that are on the site
is the Bible of what you=re going to go by.@
The Secretary has established SP violated
the terms of ' 1926.703(a)(2). The requirement that all plans, including
revisions, be present on site is not a mere technicality. Formwork is designed
to transfer weight from the structure. Prematurely removing formwork without an
engineer=s revisions exposes employees to structural collapse. Without the
correct plans on site, crucial information is missing.
SP had actual knowledge of the violation.
Smith was the SP=s superintendent for the garage. Smith admitted SP did not have
a revised plan on site, and that he knew OSHA required it have one. Item 2 of
citation no. 2 is affirmed.
Willful Classification
The Secretary classifies this violation as
willful. A willful violation is one Acommitted with intentional, knowing or
voluntary disregard for the requirements of the Act, or with plain indifference
to employee safety.@ Falcon Steel Co., 16 BNA OSHC 1179, 1181 (No.
89-2883, 1993). A showing of evil or malicious intent is not necessary to
establish willfulness. A willful violation is differentiated from a nonwillful
violation by an employer=s heightened awareness of the illegality of the
conduct or conditions and by a state of mind, i.e., conscious disregard
or plain indifference for the safety and health of employees. General Motors
Corp., Electro-Motive Div., 14 BNA OSHC 2064, 2068 (No. 82-630, 1991).
The court finds the Secretary has
established SP=s violation of ' 1926.703(a)(2) was willful. Superintendent
James Smith was responsible for removing the reshoring without having a revised
plan on site. Smith admitted he knew he was not permitted to continue work if
he did not have the revised plans on site. Smith admitted he never saw any
revised plans, yet he ordered the reshoring removed anyway (Tr. 247). AThe
hallmark of a willful violation is the employer=s state of mind at the time of
the violation- - an intentional, knowing, or voluntary disregard for the
requirements of the Act or ... plain indifference to employee safety.@ Kaspar
Wine Works, Inc., 18 BNA OSHC 2178, 2181 (No. 90-2775, 2000) aff=d 268
F.2d 1123 (D.C. Cir. 2001). Smith=s testimony demonstrates his state of mind at
the time he ordered his employees to remove the reshoring . He knew he did not
possess revised plans on site, he knew he was not supposed to deviate from the
existing plans, and yet he did so. Smith knowingly disregarded the requirements
of the standard.
Smith=s claim he mistakenly assumed the
revised plans were in the mail from Dansco, along with the replacement drawings
for the tower is, rejected. Even if the plans were in the mail, Smith should
not have removed the reshoring until the revised plans were on site. No one
specifically told Smith that revised reshoring plans had been ordered or were
in the mail. Smith=s mistaken assumption does not show good faith.
A willful violation is not justified if an
employer has made a good faith effort to comply with a standard or eliminate a
hazard, even though the employer=s efforts were not entirely effective or
complete. L.R. Willson and Sons, Inc., 17 BNA OSHC 2059, 2063 (No.
94-1546, 1997), rev=d on other grounds, 134 F.3d 1235 (4th Cir. 1998).
SP=s contract with Universal Engineering
Service to inspect the shoring/reshoring does not show good faith. The test of
good faith for these purposes is an objective one; whether the employer=s
efforts were objectively reasonable even though they were not totally effective
in eliminating the violative conditions. Williams Enterp., Inc., 13 BNA
OSHC 1249, 1256-57 (No. 85-355, 1987). SP cannot contract away its responsibility
under the standard. Universal was never given the Patent plans and was only
shown the shoring plans SP asked it to inspect. Greg Holtz was the project
engineer for Universal (Tr. 398). He inspected the garage on December 4, 2007,
in preparation for Pour 6A. Holtz testified he never saw reshoring plans, only
the shoring plans (Tr. 408). Smith would verbally tell Holtz what he
wanted Holtz to look at. Smith carried what were purported to be shoring plans.
Holtz states, A[T]here was no need to bring out the plans. He had them rolled
up and said, >These are the plans= and he quickly rolled them back up@ (Tr.
409). The inspections by Universal were not in accordance with the plans on
site.
The violation is properly classified as
willful.
Penalty Determination
The Commission is the final arbiter of
penalties in all contested cases. In determining an appropriate penalty, the
Commission is required to consider the size of the employer=s business, history
of previous violations, the employer=s good faith, and the gravity of the
violation. Gravity is the principal factor to be considered.
The record does not disclose the size of
the employer. The Secretary has previously cited SP for OSHA violations and
therefore SP is not entitled to credit for history (Exh. C-11). The Secretary
adduced no evidence of bad faith.
The gravity of the violation is high. The
parties stipulated, AThe Secretary does not allege that any of the alleged violative
conditions in this case caused the collapse of the garage,@ (Exh. J-A, &
24). However, had the reshoring been in place in accordance with the only
reshoring plan on site, it may have lessened the damage caused by the collapse.
A penalty of $ 40,000.00 is assessed.
FINDINGS
OF FACT AND CONCLUSIONS OF LAW
The foregoing decision constitutes the
findings of fact and conclusions of law in accordance with Rule 52(a) of the
Federal Rules of Civil Procedure.
ORDER
Based upon the foregoing decision, it is
ORDERED that:
1. Item 1 of citation no. 1, alleging a
serious violation of ' 1926.21(b)(2), is vacated, and no penalty is assessed;
2. Item 2 of citation no. 1, alleging a
serious violation of ' 1926.703(b)(7), is vacated, and no penalty is assessed;
3. Item 1 of citation no. 2, alleging a
willful violation of ' 1926.701(a), is vacated, and no penalty is assessed; and
4. Item 2 of citation no. 2, alleging a
willful violation of ' 1926.703(a)(2), is affirmed as willful, and a penalty of
$40,000.00 is assessed.
\s\ Ken S. Welsch
KEN S. WELSCH
Administrative Law Judge
Date: March
8, 2010