United
States of America
OCCUPATIONAL SAFETY AND
HEALTH REVIEW COMMISSION
1924
Building - Room 2R90, 100 Alabama Street, SW
Atlanta,
Georgia 30303-3104
Secretary
of Labor, |
|
Complainant, |
|
v. |
OSHRC
Docket No. 12-1496 (REMAND) |
Action Electric Company, Inc., |
|
Respondent. |
|
Appearances:
Melanie L. Paul, Esq.
Office
of the Solicitor, U. S. Department of Labor, Atlanta, Georgia
For
Complainant
J. Larry Stine, Esq. and Mark A. Waschak,
Esq.
Wimberly
Lawson Steckel Schneider & Stine, P.C., Atlanta, Georgia
For Respondent
Before: Administrative Law Judge Sharon
D. Calhoun
DECISION AND ORDER ON
REMAND
On
May 31, 2012, the Secretary of Labor (Secretary) issued a two-item serious
Citation and Notification of Penalty (Citation) to Action Electric Co., Inc.
(Action Electric) located in Smyrna, Georgia.
The Citation was issued following an inspection of Gerdau Ameristeel’s (Gerdau)[1]
facility in Cartersville, Georgia, conducted by the Occupational Safety and
Health Administration (OSHA) by Compliance Safety and Health Officer (CSHO)
Francine Cruz on December 9, 2011 (Tr. 185).
The Citation alleged a serious violation of 29 C.F.R. § 1910.147(c)(7)(i) (Item 1) for failing to train its employees on the
purpose and function of an energy control program. Item 1 was withdrawn by the Secretary as
confirmed during the hearing held on December 18 and 19, 2012, before
Administrative Law Judge Ken S. Welsch, now retired
from the Commission (Tr. 3). The
Citation also alleged a serious violation of 29 C.F.R. § 1910.147(f)(3)(ii)(D)
(Item 2) for failing to affix personal lockout or tagout (LOTO) devices on the
group lockbox before the employees began maintenance and service work on the
fans. The Secretary proposed a penalty
of $7,000.00 for Citation 1, Item 2. Action
Electric denied applicability of § 1910.147(f)(3)(ii)(D) on the basis that at
the time of the accident the employees were not servicing the fans and the
counterweight was not connected to or associated with the operation of the
fans.
Following
the hearing, on May 10, 2013, Judge Welsch issued a decision
vacating Citation 1, Item 2 and its proposed penalty, finding that §
1910.147(f)(3)(ii)(D) was not applicable. Action
Elec. Co., 25 BNA OSHC 2138 (No. 12-1496, 2013) (ALJ). [2]
As set forth in the procedural history below,
the United States Court of Appeals for the Eleventh Circuit found the cited
standard was applicable and remanded the decision to the Commission with
instructions to reinstate the Citation. Pursuant to the instructions on remand,
the Court reinstates Citation 1, Item 2, affirms it as serious and assesses a $7,000.00
penalty.
Procedural
History
On June 4, 2013, pursuant to 29 U.S.C. §
660(a), the Secretary filed with the Commission a Petition for Discretionary Review of Judge Welsch’s
decision. The Petition was granted on
June 14, 2013. On July 6, 2016, then Chairman
Cynthia L. Attwood and then Commissioner Heather L. MacDougall issued a
decision on review. The two were divided
regarding applicability of the LOTO standard, and resolved
to jointly vacate the direction for review with instructions to allow the
decision to become the final appealable order of the Commission, with the
precedential value of a non-reviewed ALJ decision. Action
Elec. Co., 25 BNA OSHC 2120 (No. 12-1496, 2016). The Commission thereby adopted the decision
of Judge Welsch vacating Citation 1, Item 2, alleging
a violation of 29 C.F.R. § 1910.147(f)(3)(ii)(D).[3]
Thereafter,
the Secretary appealed the Commission’s decision to the United States Court of
Appeals for the Eleventh Circuit, which rendered a decision on July 13, 2017,
vacating the adopted ruling of the Commission, and remanding the case to the
Commission “with instructions to reinstate the Secretary’s citation.”[4]
Action Elec. Co., 26 BNA OSHC 1727,
1735 (No. 16-15792, 2017). By
mandate filed September 20, 2017, this case was remanded to the Commission. In turn, the Commission remanded this case to
the Chief Administrative Law Judge to proceed pursuant to the instructions of
the Eleventh Circuit.
The Chief Judge assigned this case to the undersigned Judge to carry out
those instructions.
Action
Electric has not challenged the findings of the Eleventh Circuit on
the reinstatement of the Secretary’s Citation.
The Citation included a proposed penalty of $7,000.00 which was not
addressed by the Eleventh Circuit. Therefore,
only that $7,000.00 proposed penalty is at issue. The undersigned held a conference call with
the parties’ counsel on November 1, 2017, to determine whether the parties would
like a hearing and the opportunity to brief the penalty issue. The undersigned also inquired whether they
would like an opportunity to confer regarding settlement of the penalty
issue. Counsel for the parties advised
that neither a hearing nor further briefing was necessary, and they would rely
on the briefs previously filed in this matter.
They did not agree to confer regarding settlement. Accordingly, the undersigned advised the
parties that a decision would be rendered on the record already developed.
Background
Action
Electric provides electrical service and repair support, and
has worked as a contractor for Gerdau at its Cartersville, Georgia location
since 2004. Action Elec. Co., 26 BNA
OSHC at 1727. The facility is a
structured mill which operates twenty-four hours a day, melting and casting
scrap metal into billets to form structural materials including angles,
channels, flats, and I-beams (Tr. 24). The
process involves the use of a cooling bed system, through which the billet goes
into a reheating furnace, where it exits upon the cooling bed for the fan to
cool the structural form in several cycles (Tr. 24). This cooling bed process alone takes
approximately forty-five minutes to an hour to bring the structural form from
one side of the cooling bed to the other before the form is introduced into a
straightener (Tr. 25).
In approximately September or October
of 2011, Gerdau requested that Action Electric service and replace as needed
the approximately one hundred cooling bed fans at the facility. Action Electric determined seventeen fans
needed to be replaced. Id. at 1728
(Tr. 243, 356-57). To replace the fans,
Action Electric needed access to the cooling bed basement. When servicing and maintenance work is
scheduled in the cooling bed basement, Gerdau requires that the machine and
equipment be locked out by Gerdau’s cooling bed maintenance technician. The process takes approximately twenty
minutes and involves locking out the machines and equipment at various
locations around the bed (Tr. 233, 247).
On December 9, 2011, at
approximately 7:00-7:15 a.m., Action Electric leadman
Michael Harrison and an apprentice met with Christopher Chad Hughes, the
cooling bed maintenance technician, to make preparations
to replace the final three fans (Tr. 290, 397).
The maintenance technician told the leadman he
would lock out the cooling bed and meet him later. The leadman
understood they were to meet at the north end entrance to the cooling basement
(Tr. 290, 350, 366-67). The leadman and apprentice then proceeded into the cooling bed
basement from the north entrance to conduct an inspection prior to the fan
replacement (Tr. 402). Once they left
the meeting with him, the maintenance technician moved the three new fans by
forklift to the north end of the cooling bed before initiating the mill’s
cooling bed lockout procedures (Tr. 74, 290, 292-93, 388, 413; Exhs. C-12A, R-3). While
the leadman and apprentice were in the cooling bed
basement, the maintenance technician initiated the LOTO procedure to first
activate the cooling bed rake E-stop which allows counterweights to rotate to a
zero energy state, moving the counterweights from a
one o’clock position to a de-energized six o’clock position. As a result, the counterweight struck and
killed the apprentice, and barely missed the lead supervisor (Tr. 289, 383; Exh. C-10).
Penalty Assessment
The
Commission is the final arbiter of penalties in all contested cases. See
Valdak Corp., 17 BNA OSHC 1135, 1138 (No.
93-0239, 1995) (“The [OSH] Act places limits for penalty amounts but places no
restrictions on the Commission’s authority to raise or lower penalties within those
limits”), aff’d, Valdak Corp., 17 BNA OSHC 1492 (No. 95-2194, 1996).[5] The Commission has wide discretion in penalty
assessment. E.g., Hern Iron Works, Inc.,16 BNA OSHC 1619, 1621-23 (No. 88-1962,
1993).
Under
§ 17(j) of the Act, the Commission must give “due consideration to the
appropriateness of the penalty with respect to the size of the business of the
employer being charged, the gravity of the violation, the good faith of the
employer, and the history of previous violations.” The principal factor in a penalty
determination is gravity, which “is based on the number of employees exposed,
duration of exposure, likelihood of injuries, and precautions against injuries.” Siemens
Energy and Automation, Inc., 20 BNA OSHC 2196, 2201 (No. 00-1052, 2005).
Although
the record does not provide specific evidence of Action Electric’s size, CSHO
Cruz testified the number of employees employed by Action Electric at the time
of the incident was “[p]robably in the hundreds” (Tr.
456). The purpose of considering employer size in a penalty determination is
“to avoid destructive penalties” due to the size of a company and its financial
status. Colonial Craft Reprods., Inc., 1 BNA OSHC 1063 (No. 881, 1972). There is no evidence in the record that
Action Electric would face undue hardship should the full proposed penalty be assessed.
The
gravity of the violation alleged in Citation 1, Item 2 is high.[6] An Action Electric employee died from the
failure of Action Electric to properly implement LOTO procedures for inspection
of the cooling machine and counterweight components. The leadman and
apprentice were directly exposed to the hazard of counterweight de-energization
through their service and maintenance on the fans for approximately forty-five minutes.[7] In addition, two other Action Electric crew
members were present on site to complete the fan installation and potentially were
at risk (Tr. 289, 337, 343, 383; Exh. C-11).
Although
only a few employees were exposed for a relatively short period of time, the
violation warrants a higher penalty in consideration of the strong likelihood
of injury and few precautions taken by Action Electric to prevent injury. Exposure to counterweights in completing the
fan inspection was inevitable. In
inspecting the fans from the cooling bed basement, the leadman
and apprentice walked outside of the designated walkway towards the location of
the counterweights and fans.[8] The LOTO procedures had not been performed,
and as a result, the counterweights to which the employees were exposed had not
been de-energized (Tr. 265-66). With the
LOTO procedures not implemented, the counterweights would and did fall down to
a zero degree position, making the likelihood of
injury very high for any individual present and off the designated walkway during
the counterweight de-energization process [9]
(Exh. C-10).
Although
the fans and counterweights had separate lockouts, Gerdau safety manager Ecky Hall testified the cooling bed needed to be locked out
before working on the fans, and more generally that there was "not any
place underneath the cooling bed that you [could] go off of that designated
walkway without locking everything out" (Tr. 119-20). The maintenance technician similarly
explained that pieces of cooling bed equipment "overlap so much that you can't
work on one specific piece without locking out other equipment as well,"
and that employees must “physically…crawl up in between the rakes in order to remove the fans” (Tr. 228-29, 322-23, 408). Even in the event the counterweights were
de-energized, the maintenance technician testified “several hazards” existed
away from the designated walkway, including numerous pinch points, moving
chains, turning sprockets, rotating equipment, and dim lighting (Tr. 232). Action Electric took few precautions against
injury, necessitating a higher penalty.
There is nothing in the record to
reflect a prior history of OSHA violations by Action Electric.[10]
And although Action Electric took several post-accident measures implemented in
response to this Citation, such as placing “Danger” tape on the north side gate
basement entrance that previously only featured
an “Authorized Personnel Only”
sign; erecting a chain link fence over the previous chains lining the
designated basement walkway to further deter individuals to stray from the
designated walkway, modifying its work permit language;[11]
and re-training leadman Harrison on Action Electric’s
LOTO procedures (Tr. 215-16, 370-71, 380-81), these ameliorative efforts in
response to the Citation do not warrant a penalty reduction for good faith. Having considered the evidence in
the record regarding the four penalty factors, the undersigned finds the high
gravity-based penalty factor far outweighs any other factors in this case. See State Sheet Metal, 16 BNA OSHC 1155,
1162 (No. 90-1620 and 90-2894, 1993) (finding no reduction in proposed penalty
when gravity of the violation was high),
citing Natkin, 1 BNA OSHC 1204, 1205 (No. 401,
1973); Kus-Tum Builders, Inc., 10 BNA OSHC 1128
(No. 76-2644, 1981) (finding no reduction in penalty proposed is proper when
the violation is of high gravity). Accordingly,
the undersigned finds the Secretary’s full proposed penalty to be appropriate. Citation 1, Item 2 is affirmed as serious and
the proposed penalty of $7,000.00 is assessed.
FINDINGS
OF FACT AND CONCLUSIONS OF LAW
The foregoing decision constitutes the
findings of fact and conclusions of law in accordance with Rule 52(a) of the
Federal Rules of Civil Procedure.
ORDER
Based upon the foregoing decision, it is ORDERED
that:
Citation
1, Item 2, alleging a violation of 29 C.F.R. § 1910.147(f)(3)(ii)(D) is reinstated
and a $7,000.00 penalty is assessed.
SO
ORDERED.
/s/
Date:
April 23, 2018 SHARON D. CALHOUN
Administrative
Law Judge
Atlanta,
Georgia
[1] Gerdau Ameristeel’s
company name has been changed to Gerdau since this incident (Tr. 228).
[2] In
his Decision, in addition to finding the standard was not applicable, Judge Welsch addressed the remaining elements of the Secretary’s
burden of proof to establish a prima
facie case and set forth findings that the cited standard was violated;
employees were exposed to the hazard of the counterweight falling from stored
energy; and that the leadman knew the cooling bed was
not locked out when he entered the basement.
Action Elec. Co.,
25 BNA OSHC 2138 (No. 12-1496, 2013) (ALJ)
[3] The Commission held that the cooling bed counterweights and fans were independent machines rather than subsystems of the cooling bed for LOTO purposes, and Action Electric employees were not servicing the fans at the time of the incident, rendering the LOTO standard inapplicable. Action Elec. Co., 25 BNA OSHC at 2130-38.
[4]The Eleventh Circuit vacated the
Commission’s decision on the grounds that the
counterweight and fan components of the steel mill’s cooling bed were part of
one “machine,” and that in surveying the machine, Action Electric employees
were performing servicing and maintenance activities on the fans that would
require implementation of LOTO procedures due to their potential exposure to
hazardous energy outside of normal production operations. Action Elec. Co., 26 BNA OSHC at 1730-34.
[5] On November 5, 1990, section 17 of
the OSH Act, 29 U.S.C. § 666 was amended to increase the maximum penalty for a
serious violation from $1,000 to $7,000. Thereafter, new penalties were
established for violations that occurred after November 2, 2015 pursuant to the
Federal Civil Penalties Inflation Adjustment Act of 2015. Pub. Law 114-74 §
701, 129 Stat. 559-602 (2015). 81 Fed. Reg. 43430 (July 1, 2016). See Penalty- Act’s Penalty Provisions
Outlined. The citations in this
case were issued on May 31, 2012.
Accordingly, the old penalty structure implemented prior to 2015 with a
maximum penalty of $7,000 for a serious violation applies for this case.
[6] CSHO Cruz testified that the
severity and probability of injury were both high, warranting the gravity-based
penalty of $7,000.00 (Tr. 428).
[7]
Harrison testified that he
met Hughes in his office to go over service and maintenance of the fans
immediately prior to his basement fan inspection at 7:00 a.m., while Hughes
testified that he met Harrison at approximately 7:15 a.m. (Tr. 290, 397). CSHO Cruz testified that based upon documents
and interviews, the accident occurred around 7:53 a.m. thereafter (Tr. 452).
[8] CSHO Cruz testified that per her
investigation, the apprentice was found 20-25 feet from the designated walkway
(Tr. 423).
[9] Action Electric’s “Incident
Inspection Form” additionally listed the probability of injury as “Moderate-
Occasionally, chance for weekly to monthly exposure.” (Exh.
C-10). Safety manager Hall additionally testified he usually goes through
300-400 permits at Gerdau’s Cartersville plant per month for contractors,
showing contractors including Action Electric employees frequently come in and
out of the facility for a variety of inspections (Tr. 32).
[10] CSHO Cruz noted she did not
believe there was any record of any prior history of OSHA violations prior to this
incident involving Action Electric (Tr. 456).
[11] Following the December 9, 2011
incident, Action Electric modified its work permit language to include bold
language that “no work or entry to the work area may be permitted until the
permit is completely signed off by both parties, Gerdau, and the contractor,”
and added the cell maintenance worker and leadman
into the permit language (Tr. 215-16).