United States of America
OCCUPATIONAL SAFETY AND HEALTH REVIEW
COMMISSION
SECRETARY
OF LABOR, |
Complainant, |
v. |
INSULATION-N-COATINGS
d/b/a FORCE ENTERPRISES, |
Respondent. |
OSHRC
Docket No. 16-0275
Appearances:
Jennifer A. Casey, Esq.,
U.S. Department of Labor, Office of the Solicitor, Denver, Colorado
For Complainant
Aaron A. Dean, Esq., Moss & Barnett, Minneapolis, Minnesota
For Respondent
Before:
Administrative Law Judge Peggy S. Ball
DECISION AND ORDER
I.
Procedural History
While
on their way to another inspection, CSHO Kevin McElvany and trainee Wanlipa
Quade saw an active, open trench in Bismarck, North Dakota. (Tr. 66). Pursuant to Complainant’s National Emphasis
Program (NEP) on trenches, CSHO McElvany opened an inspection of the worksite.
During the inspection, CSHO McElvany noticed the spoil pile sat at the very
edge of the trench. (Ex. C-2 at 1–2). This prompted him to take measurements,
conduct interviews, and collect samples.
Prior to leaving the worksite, CSHO McElvany asked Respondent’s foreman,
Adam Galindo, to make sure to push the spoil pile back from the edge of the
trench before any employees re-entered. (Tr. 405).
Based
on CSHO McElvany’s findings, Complainant issued to Respondent a serious,
two-item Citation and Notification of Penalty with a grouped penalty of $1,200. The Citation alleges Respondent committed two
violations of the Occupational Safety and Health Act: (1) Respondent failed to
keep the spoil pile more than two feet away from the edge of the trench, in
violation of 29 C.F.R. § 1926.651(j)(2); and (2) Respondent’s competent person
failed to remove employees from the trench when those employees were exposed to
a hazardous condition, in violation of 29 C.F.R. § 1926.651(k)(2). Respondent filed a Notice of Contest,
contending Complainant failed to prove it violated either standard, and,
alternatively, that the existence of any violation was caused by unpreventable
employee misconduct.
This
case was originally designated for Simplified Proceedings under Subpart M of
the Commission Rules. See 29 C.F.R. §
2200.200 et seq. After a pre-trial conference revealed
significant factual disputes requiring discovery, the Court removed the matter
from Simplified Proceedings on May 16, 2016.
A trial was held February 22–24, 2017, in Bismarck, North Dakota. Both parties timely submitted post-trial
briefs for the Court’s consideration.
II. Stipulations and Jurisdiction[1]
The parties’ stipulations can be found in the
parties’ Joint Stipulation Statement,
which was filed with the Court on September 13, 2016. (Tr. 11). Amongst the parties’ stipulations
and undisputed facts, the parties agreed that: (1) the Commission has
jurisdiction over this proceeding pursuant to section 10(c) of the Act, 29 U.S.C.
§ 659(c); and (2) Respondent is an employer engaged in a business affecting
commerce within the meaning of section 3(5) of the Act, 29 U.S.C. § 652(5). Slingluff v. OSHRC, 425 F.3d 861 (10th
Cir. 2005).
III.
Factual Background
Respondent
is a contractor that specializes in the installation and repair of underground
utilities, such as water, sewer, and storm sewers, for developers and municipal
entities. (Tr. 850). The particular
project at issue in this case, known as the Trillium Project, was located just
behind the Sam’s Club located at Rock Island Place and Burlington Drive in
Bismarck, North Dakota. (Tr. 85; Ex. C-3).
The Trillium project involved the installation of a new sewer line for
developers in the area. (Tr. 287). As
far as digging trenches is concerned, this was a fairly uncomplicated job: the sewer line was being dug in an open field
with very few (if any) obstructions either above or below ground. (Tr. 148). On the morning of November 3, 2015,
Respondent’s crew had already been digging and laying down sewer line for
approximately one week. (Tr. 288).
At
some point after lunch that same day, CSHO McElvany and his trainee pulled up
to the Trillium worksite. (Tr. 68). From a vantage point located roughly 200 feet
away, CSHO McElvany observed and recorded an idle excavator and a man who
appeared to be handing a piece of pipe down into a trench. (Tr. 74–75, 560; Ex.
C-1, seg. 1). In light of his
observations, CSHO McElvany decided to open an inspection pursuant to the
trenching NEP. (Tr. 66). After his
initial recording, CSHO McElvany turned off his camcorder and geared up to
conduct an inspection. (Tr. 75).
Roughly
seven minutes later,[2]
CSHO McElvany walked up to the actual worksite and began recording again. (Tr. 75;
Ex. C-1, seg. 2). The excavator was no
longer idle and was digging at one end of the trench. (Tr. 77; Ex. C-1, seg. 2). As he walked up, CSHO McElvany noted in the
video recording that he saw someone come out of the trench. (Ex. C-1, seg. 2). Shortly after, CSHO McElvany introduced
himself to Adam Galindo, who identified himself as the foreman for Respondent.
(Id.). After introducing himself, CSHO McElvany
initiated the inspection and began to discuss the excavation with Galindo, take
measurements and samples, and conduct interviews with the workers that he
observed coming out of the trench near the ladder on the west side of the
trench. (Tr. 76, 115, 119, 138–39; Ex. C-1).
The
trench was roughly 10 feet deep, 7 feet across at the bottom, and 34 feet
across the top. (Tr. 76, 123–24, 316, 738; Ex. C-2 at 11). Respondent did not use shores or trench
boxes, but instead sloped the sides of the trench, which CSHO McElvany determined
to be compliant based on the soil type.[3]
(Tr. 120, 133). Galindo told McElvany the two employees he saw
exiting the trench had been installing a section of pipe to the end of the
existing line and pointed to various tools and footprints at the bottom of the
trench to show where they had been. (Tr. 89–90; Ex. C-1, seg. 2). After that section had been installed, Galindo
testified the two employees exited the trench, and Respondent’s excavator
operator, Kyle Stewart, covered the recently installed pipe section and began
widening the immediately surrounding area to accommodate a manhole. (Tr. 484). The manhole was six feet in diameter and required
more space at the bottom of the trench than the eight-inch sewer line. (Tr. 489,
492). Stewart also had to ensure that a
tamping device, known as a sheep’s foot, was able to fit in the area
surrounding the manhole. (Tr. 803). Because the bottom was widened, Stewart
also had to push back the walls and top edge of the trench to ensure the slope
remained compliant. (Tr. 785).
While
the trench, itself, was compliant, CSHO McElvany was concerned with the spoil
piles that were stacked along the east side of the trench. For a distance of roughly 30 feet, which
extended from the area where the employees were last working to the ladder, the
spoil pile directly abutted the sloped wall of the trench. (Tr. 140; Ex. C-2). Although he did not directly observe Johnie Shearry
and James Gorneau in the bottom of the trench, CSHO McElvany determined they
had been exposed to the hazard, because, according to the video recording and
his testimony, he observed “someone” come out of the trench as he was walking
up to the worksite. (Tr. 76; Ex. C-1, seg. 2). During that period of time, McElvany noted the
excavator did not disturb the soil above or below the east wall of the
excavation, nor did he see the excavator move from its position. (Tr. 116–17,
128–29). According to McElvany and the
photographs he took, the lion’s share of Stewart’s digging appeared to be
focused on the area immediately in front of the excavator. (Tr. 98, 126; Ex.
C-2 at 2, 4, 5, 11, 13, 15).
On
the face of it, CSHO McElvany laid out a fairly clear case that Respondent
violated the cited standard. However,
Respondent contends its employees were never in the trench when the spoil pile
was in a noncompliant condition. Galindo, Stewart, Shearry, and Ernie Miller (Respondent’s
“top man”) testified that all work in the bottom of the trench ended at least
10 to 15 minutes before McElvany and his trainee arrived at the worksite and
certainly before Stewart began altering the width of the trench. (Tr. 481, 599,
782). Depending on who was asked,
Shearry and Gorneau were either sitting on the slope of the trench at a safe
distance from the excavator and opposite from the noncompliant spoil piles, or they
were on the grass just outside the trench while Stewart was digging. (Tr. 355,
591–92, 751; Ex. R-47, R-48, R-50). At
least one witness testified that, although the spoil pile rested at the
precipice of the trench during the inspection, a gap had existed before CSHO
McElvany arrived. (Tr. 835). In support
of this claim, Stewart and Galindo testified the gap was covered when Stewart
removed dirt from the spoil pile to use as cover for the installed sewer line
and when he widened the trench for the installation of the manhole. (Tr. 487–90,
762; Ex. R-51, R-52). During this time,
Shearry and Gorneau were purportedly sitting on the slope of the trench, just
out of CSHO McElvany’s view as he approached the worksite from the west. In
essence, Respondent alleges the workers stopped working and sat on the wall of
the trench to take a break at or before the time when the excavator started up and
started to dig.
IV.
Discussion
Many
basic facts in this case are not in serious dispute. Neither party had
contradictory evidence regarding the dimensions of the trench, its slope, or
its soil composition. There is no disagreement that Shearry and Gorneau worked
in the bottom of the trench at some point prior to CSHO McElvany walking up to
the worksite. The photographs and video
reveal the spoil pile was not pushed back from the trench by the minimum
required two feet at the time of the inspection. (Ex. C-2 at 11). As illustrated above, however, the parties
dispute whether Shearry and Gorneau were inside of the trench when the spoil pile was in a
noncompliant condition. Complainant argues that Shearry and Gorneau must have
been exposed because CSHO McElvany saw them exit the trench almost immediately
before stepping onto the worksite.
Respondent, on the other hand, contends Shearry and Gorneau were out of
the trench long before McElvany arrived and that the once-compliant spoil pile
along roughly 30 feet of the east wall was undone purposefully to accommodate a
manhole.
Notwithstanding
the volume of testimony Respondent put forth on the subject, the Court finds
Complainant’s version of the facts is more credible and comports with the
objectively verifiable photographic and videographic evidence. Respondent’s theory of the case, on the other
hand, requires a fairly labored interpretation of those same facts and was
facilitated, in part, by testimony given in response to leading questions.[4] In
the end, the Court was left with a simple question: what is the more likely
explanation for CSHO McElvany’s observations? Based on what follows, the Court
finds the most likely explanation, based on a preponderance of the evidence, is
that Respondent violated the standard governing spoil piles in Item 1a. That said, the Court also finds Item 1b shall
be vacated because it is essentially a duplicate of the allegations in Item 1a.
A.
Citation 1, Item 1
Complainant alleged a serious violation of the Act in
Citation 1, Item 1 as follows:
29 CFR 1926.651(j)(2):
Employees were not protected from excavated or other materials or
equipment that posed a hazard by falling or rolling into excavations and
protection was not provided by placing and keeping such material or equipment
at least 2 feet (.61 m) from the edge of excavations, or by the use of
retaining devices that were sufficient to prevent materials or equipment from
falling or rolling into excavations, or by a combination of both if necessary.
(a) On or about November 3, 2015 for employees exposed to
struck by hazards while laying pipe in a trench with the spoil pile on the edge
of the excavation near Rock Island Place and Burlington Drive in Bismarck,
North Dakota.
Citation and Notification of
Penalty at 6.
To establish a
violation of an OSHA standard pursuant to Section 5(a)(2) of the Act, Complainant
must prove: (1) the standard applies to the facts; (2) the employer failed to
comply with the terms of the standard; (3) employees were exposed to the hazard
covered by the standard, and (4) the employer had actual or constructive
knowledge of the violation (i.e., the employer knew or, with the exercise of
reasonable diligence, could have known of the violative condition). Atlantic Battery Co., 16 BNA OSHC 2131, 2138 (No.
90-1747, 1994).
Complainant has the
burden of establishing each element by a preponderance of the evidence. See Hartford Roofing Co., 17 BNA OSHC
1361 (No. 92-3855, 1995). “Preponderance
of the evidence” has been defined as:
The greater weight of the evidence, not
necessarily established by the greater number of witnesses testifying to a fact
but by evidence that has the most
convincing force; superior evidentiary weight that, though not sufficient
to free the mind wholly from all reasonable doubt, is still sufficient to
incline a fair and impartial mind to one side of the issue rather than the
other.
Black’s Law Dictionary, “Preponderance of
the Evidence” (10th ed. 2014) (emphasis added).
i.
The Cited Standard Applies
The scope and application paragraph
for subpart P states, “This subpart
applies to all open excavations made in the earth’s surface. Excavations are
defined to include trenches.” 29 C.F.R. § 1926.650(a). Because there is no explicit dispute
regarding the application of the standard, the Court finds Respondent’s trench
qualifies as an excavation according to the definitions provided at 29 C.F.R. §
1926.650(b). Thus, the standard applies.
ii.
The Terms of the Standard Were Violated
Though
the parties dispute whether the two employees were inside the trench when the
spoil pile was noncompliant, they do not dispute CSHO McElvany’s photographs
show a spoil pile that has no visible separation from the edge of the trench. In
order to protect employees inside the trench, Respondent is required to ensure
that spoil piles and other equipment are placed no less than two feet back from
the edge of the trench or are otherwise restrained by a device. 29 C.F.R. §
1926.651(j)(2). At the time of CSHO
McElvany’s inspection, the spoil pile on the east side of the trench was less
than two feet from the edge of the trench.
That fact, alone, is sufficient to establish that the terms of the
standard were violated, and the Court so finds.
iii.
Respondent’s Employees Were Exposed to the Hazard
A
finding that the terms of the standard were violated, however, should not to be
confused with establishing the existence of a prima facie case. The standard states “employees shall be
protected” from these hazards, which means a violation of the standard only
exists if employees are exposed to the hazard imposed by an improperly placed
spoil pile. Id. Thus, it is not enough for Complainant to
show proof of noncompliant conditions; rather, it is incumbent upon Complainant
to prove the employees were in the trench when
the terms of the standard were violated.
But this requirement only states explicitly that which is required of
every single 5(a)(2) case: proof of exposure. “The
Secretary may prove employee exposure to a hazard by showing that, during the
course of their assigned working duties, their personal comfort activities on
the job, or their normal ingress-egress to and from their assigned workplaces,
employees have been in a zone of danger or that it is reasonably predictable
that they will be in a zone of danger.” Rgm Constr. Co., 17 BNA OSHC
1229 (No. 91-2107, 1995).
Respondent
has gone to great lengths to disprove what is, on its face, a very convincing
set of facts. As CSHO McElvany arrived
in his vehicle he observed, albeit from a distance of roughly 200 feet, an idle
excavator and a person who appeared to be handing something down into the
trench. (Ex. C-1, seg. 1). Roughly seven
minutes later, CSHO McElvany recorded his walk up to the trench. (Ex. C-1, seg.
2). As he walked up, CSHO McElvany stated
aloud that he saw someone come out of the trench. (Id.). Also audible in the
background of the video is the formerly idle excavator, which was digging on
the south end of the excavation. (Id.).
According
to CSHO McElvany, the excavator’s activity was focused on the area immediately
in front of it on the south side of the trench. He testified he did not observe
the excavator dig anywhere near the area surrounding the trench rod or other
tools that were left in the bottom of the trench by Shearry and Gorneau.[5] Nor, testified CSHO McElvany, did he see
Stewart pull any material from the spoil pile on the east side of the
excavation or place any material there. Instead, he saw Stewart widening the
area immediately in front of him, and dumping material at the end of the spoil
pile, directly to the right of his location. (Tr. 127; Ex. C-2 at 20). The condition of the trench and spoil pile
from the area surrounding the trench rod to the ladder (roughly 25 feet) did
not change from the point of CSHO McElvany’s arrival on site to when he took the
photographs illustrating the trench in a noncompliant state.
When
he came in full view of the trench, CSHO McElvany encountered Galindo, who
identified the area around the tools as the location where the employees CSHO
McElvany saw exit the trench had last been working.[6]
(Ex. C-1, seg. 2). Indeed, he pointed to
footprints in the same area to confirm their location. (Tr. 89; Ex. C-1, seg. 2). Galindo did not dispute what CSHO McElvany
claimed to have just observed, and seemed to confirm as much during his
deposition. (Tr. 360, 365–66). Thus, CSHO
McElvany observed an employee, whose identified area of work and means of
egress exposed him to a roughly 30-foot long stretch of noncompliant spoil pile,
exit a trench almost immediately before CSHO McElvany discovered the spoil pile
in a noncompliant state. When coupled
with the fact that CSHO McElvany observed this employee exit the trench near
where the ladder is located—a fact echoed by Stewart—the foregoing evidence
makes a compelling case for exposure. (Tr. 752).
Respondent’s
principal argument is that Complainant cannot show its employees were in the
bottom of the trench when the spoil pile was noncompliant. In other words, there was no confluence of
violation and exposure. While
Respondent’s arguments raise an interesting question about the quantum of proof
necessary to establish exposure, they do not convincingly subvert Complainant’s
prima facie case.
To
start, Respondent makes much of the fact that CSHO McElvany did not physically
observe the employees in the bottom of the trench while the spoil pile was
noncompliant. While this is true, such is not required to establish exposure. In Gilles
& Cotting, Inc., the Commission rejected the “actual exposure” test,
which required evidence that someone observed the violative conduct, in favor
of the concept of “access”, which focuses on the possibility of exposure under
the conditions. See Gilles & Cotting, Inc., 3 BNA OSHC 2002 (No. 504, 1976)
(holding “that a rule of access based on reasonable predictability is more
likely to further the purposes of the Act than is a rule requiring proof of
actual exposure”). The Court is
permitted to make reasonable inferences based on the facts in evidence. See Okland Construction Co., 3 BNA
OSHC 2023, 2024 (No. 3395, 1976).
Included among those inferences is whether an employee could, in the
regular course of their work, be exposed to a hazard caused by a violative
condition. Gilles & Cotting, Inc.,
3 BNA OSHC 2002 (“On balance, we conclude that a rule of access based on reasonable predictability is more likely
to further the purposes of the Act than is a rule requiring proof of actual
exposure.”) (emphasis added).
Galindo,
Respondent’s foreman and competent person, was the first person CSHO McElvany
talked to when he arrived at the worksite.
In the inspection video, Galindo can be heard telling CSHO McElvany that
the employees that just exited the trench came from the area where the tools
were located, which was also marked by footprints around and on top of the
recently installed and covered pipe section. (Ex. C-1, seg. 2). Later on, during his deposition, Galindo was
more clear:
Q. All
right. So tell me, to the best of your
recollection, what were your folks doing when OSHA arrived onsite?
A. Well, I
didn’t know they [OSHA] arrived, but when I seen [sic] them, the guys were
getting ready to come out because the operator was going to start digging for
the manhole. So therefore it was going to take a lot longer to excavate it.
(Tr. 360;
Deposition of Adam Galindo at 185). In other words, Galindo’s deposition
testimony and his statements in the inspection video comport with CSHO
McElvany’s testimony and contemporaneous statements in the inspection video;
namely, that the employee CSHO McElvany saw exiting the trench just completed
his work at the end of the sewer line.
At some point, however, Galindo’s testimony
changed. Admitting that his “answers
ain’t going to be the same as it was in my deposition….my answers are going to
be similar, but they’re just not going to be exactly the same”, Galindo
testified that Shearry and Gorneau were out of the trench at least 15 to 30
minutes before OSHA arrived onsite. (Tr. 485).
In an attempt to explain why CSHO McElvany saw someone come out of the
trench, Galindo testified the two employees were sitting on the slope of the
trench just below the edge, so as to place them out of McElvany’s line of sight
on his approach to the worksite. (Tr. 364–67;
Ex. C-2 at 3a). Thus, when they rose
from their resting place, it gave the appearance of emerging from the trench
bottom. Shearry, Stewart, and Miller all
echoed this testimony in one way or other, stating that Shearry and Gorneau
were not in the trench bottom and had not been for at least 15 minutes.
Galindo’s
testimony is a marked departure from both his recorded statements and his
deposition testimony, which placed the employees in the bottom of the trench
just prior to OSHA’s arrival at the worksite. The photographs of the worksite
support Galindo’s former testimony. In
the bottom of the trench, near the location of the last installed pipe section,
there were two shovels, a roll of green tape, a pry bar, a trench rod, and a
bucket of lubricant. (Ex. C-2 at 3). CSHO
McElvany observed footprints, confirmed by Galindo, in the area surrounding
those tools, including in the dirt covering the recently installed pipe
section. (Tr. 89). Although these
implements, of themselves, do not indicate the time at which they were left at
the bottom of the trench, their presence in the trench leads to the reasonable conclusion
that employees were there recently. Respondent attempts to discount the
importance of these tools by providing explanations for their presence in the
trench.
At
least two different tools—a shovel and a pry bar—were purportedly left in the
trench to mark the end of the pipeline for the excavator operator. (Tr. 104,
169, 482; Ex. C-2 at 3). In fact,
Galindo testified he threw one of the shovels into the trench for that very
purpose, notwithstanding the presence of the other markers. (Tr. 482). The tape roll, Galindo explained, is used to
mark the existence of the line for future excavations, so that they can avoid
hitting the pipe. (Tr. 524–25). While
the Court understands the purpose of the tape, it was also the Court’s
understanding that it needed to be rolled out in order to be effective as a
warning device for the entire length of the sewer line, else the putative
future excavator would need to be digging in the exact spot of the roll for it
to work. (Tr. 750). It makes even less
sense that all of those tools, including a laser level/trench rod, would be
left in the bottom of the trench when the area directly above it was set for
reconfiguration, which would cause that area of the trench, and everything in
it, to be covered.
The
Court is more convinced by Galindo’s video recorded statements and deposition
testimony. His understanding of the facts was more or less consistent during
the inspection and his deposition, and yet that understanding changed at trial.[7] Indeed, even at trial, Galindo’s estimates of
the amount of time that transpired ranged anywhere from 15 to as many as 45
minutes. (Tr. 485). Perhaps, as Galindo
implied when he said his testimony would be “similar” but “not . . . exactly
the same”, his change in testimony was due to the passage of time and fading
memory. Given that Galindo’s two prior statements were consistent with each
other and with CSHO McElvany’s testimony, and were given closer in time to the
events of this case, the Court finds Galindo’s trial testimony to be the
outlier. Accordingly, the Court gives
his trial testimony on this topic no weight.
While
the Court realizes Galindo was not the only one who testified that the two
employees were sitting outside the trench for a period of 10 to 15 minutes
prior to the arrival of OSHA, the Court finds such estimates to be equally problematic. To illustrate, a review of the timeline of
events is helpful. As illustrated in the
first video segment, the excavator was idle; a fact to which all parties agree.
While the excavator was idle, CSHO
McElvany saw a man, Miller, hand something down into the excavation and remarks
as such to the camera. (Tr. 74; Ex. C-1, seg. 1). Seven minutes later, the excavator is in
operation, and CSHO McElvany sees someone walk out of the excavation. Thus,
even Stewart, who estimated he was digging at least 15 minutes prior to OSHA’s
arrival, admitted that he could not have been digging for more than seven
minutes. (Tr. 799). While seven minutes
is nonetheless a long enough span for an excavator to do some damage to the
walls of a trench, the point is that the estimates of time provided by
Respondent’s employees varied wildly, from no time at all to 15 or even 45
minutes between Shearry and Gorneau’s departure from the trench and OSHA’s
arrival.
Although
the timing of Shearry and Gorneau’s exit from the trench is important, equally
important is the work allegedly performed by the excavator during that period
of time. According to Galindo, the John Deere 270 excavator had a
four-foot-wide bucket. (Tr. 487; Ex. C-1, seg. 2). In addition to moving a lot of earth, the
four-foot bucket also served as the means by which Respondent created the necessary
buffer between the trench and spoil pile. (Tr. 735). Galindo, Stewart, and Chip Stroschein, one of
Respondent’s co-owners, all testified this was standard practice.[8]
(Tr. 567, 735, 870). Thus, according to
practice, prior to Stewart widening the trench, a four-foot gap existed between
the trench and spoil pile along the 30-foot stretch where Shearry and Gorneau
affixed the succeeding sections of pipe. Based on Stewart’s testimony about
when he began digging, the alleged disappearance of the four-foot gap must have
occurred during the seven-minute lapse in CSHO McElvany’s video segments.
Stewart
testified the first thing he did after Shearry and Gorneau left the trench was take
a scoop from the spoil pile and place it over the top of the last pipe section
to hold it in place. (Tr. 756). This is curious
for a couple of reasons. First, as
testified to by CSHO McElvany, there were tools in the area surrounding that
pipe section, indicating work had recently occurred in that area. Stewart, the excavator operator, and Ernie
Miller, the top man, who had the best views of the trench, could have easily
instructed Shearry and Gorneau to retrieve their tools from the trench before digging
began in the area. They did not. This
failure is intriguing because it either suggests nearly everyone on the
worksite was negligent with respect to leaving tools behind, or perhaps neither
Stewart nor anyone else was concerned because he was not going to be digging in
that area.[9] Second,
CSHO McElvany identified footprints in the dirt that had been placed over the
top of the pipe. (Tr. 103, 228). While
it is standard practice to tamp cover material after it has been placed on the
pipe, the presence of these particular footprints does not make sense given the
timeline provided by Stewart, because they would have been made after Shearry and Gorneau purportedly exited
the trench.
After
he placed cover on the pipe section, Stewart testified he needed to widen the
trench to accommodate a manhole and the equipment required to install it. (Tr. 753).
According to Stewart, the sheep’s foot attachment and payloader required an
additional four to eight feet around the manhole, itself six feet wide, in
order to properly install it. (Tr. 803–804, 810). In a series of exhibits,
Stewart illustrated the areas where they expanded the trench to accommodate the
manhole and the sheep’s foot. (Tr. 786–91; Ex. R-50, R-51, R-52). While some of
Stewart’s testimony on this topic makes sense, some of his statements were
inconsistent with the photographs of the worksite, and, in some cases, were
plainly contradicted.
For
context, the parties agree that the area of concern extended from the ladder to
the area where the tools and footprints were identified. (Tr. 98). Beyond that point was the location where the
manhole would be installed. Although the lion’s share of Stewart’s digging
appeared to be located directly in front of the excavator, Stewart testified he
reached a significant distance down the trench on the east wall to widen the
“entire” trench. (Tr. 789). In the process, Stewart testified he scraped
away the existing space between the trench and spoil pile, and managed to do so
without damaging or otherwise impacting the trench rod that was propped against
the east wall. (Tr. 788–89). What makes
this testimony so difficult to believe is the condition of the trench bottom. In one exhibit, Stewart pointed to all of the
places he dug in order to widen the trench. (Tr. 762; Ex. R-51). While the Court does not take issue with the
scoops taken directly in front of the excavator, the Court is somewhat dubious
about Stewart’s claim that he dug in the area beyond the trench rod as shown in
Exhibit R-51, or at least to the extent he claims.
The
pictures reveal Stewart did most of his digging in the area where the manhole
was set to be installed. The bottom of the trench in the area closest to the
excavator revealed as much, because it had a significant amount of material
that had sloughed off of the east wall. (Ex. C-2 at 4). However, moving north away from the
excavator—where the employees had been working—there is a notable lack of sloughed
material in the bottom of the trench. (Id.). If, as Stewart claimed, he dug along the east
wall beyond the trench rod, the Court is confused as to how virtually no
material fell into the trench on that side.
Footprints were still visible, and the tools only showed signs of
sloughing from the west side of trench. (Ex. C-2 at 3). As noted by
Complainant, Respondent would have the Court believe Stewart was able to remove
a four-foot gap between the spoil pile and the trench for a span of at least
thirty feet and do so without spilling any material onto the tools or work area
below where he was digging. While the Court has no doubt Stewart is a skilled
operator, it is not convinced he was able to move such a large amount of earth
without having some fall into the excavation, especially when sloughing
occurred on the west side of the excavation without any apparent intervention.
(Tr. 113; Ex. C-2 at 9).
The
Court also finds Stewart was less than credible when it came to describing
where he placed the dirt he removed from the trench. On direct examination,
Stewart claimed he put the material he removed from the trench on top of the
existing spoil piles. (Tr. 773; Ex. R-52).
This, he and Galindo claimed, also contributed to the disappearance of
the four-foot gap. (Tr. 396–97, 567–68, 773, 783). Under cross-examination, however, when
Stewart was shown photographs of the excavator turned sideways and adding spoil
to the end, not the top, of the spoil pile, he had to admit that he “was
placing it back behind the spoil pile, yes.” (Tr. 784; Ex. C-2 at 20).
Equally
confusing to the Court is Stewart’s explanation for digging beyond the trench
rod. Stewart testified he needed to widen the area that stretched from the trench
rod to the excavator. (Tr. 786; Ex. C-2 at 4). Then, he testified he in fact dug past the
trench rod in order to make the “entire trench” wider. (Tr. 789). After explaining how he was able to avoid
striking the trench rod with the excavator, Stewart attempted to describe why
he was digging in that area of the trench:
Q.
Okay. And so eventually, if you actually expanded
the slope in the manner that you're talking about and
that you've drawn here, you would dig considerably farther
into the slope; correct?
A.
Not back there. I was just making the top wider
up here [indicating] and here [indicating]. And, yeah, and then I -- you could see where I started to dig here [indicating] and here
[indicating].
Q. And why did you need to make the top wider? If your intent was to actually widen the entire trench, why just widen the top?
A. I was
widening the entire trench.
Q. Okay. So eventually you were
going to work your way down from the top to the bottom of the trench and widen that whole area; correct?
A. Correct.
Q. And that would have been the area where you see the shovel.
A. No.
Q. You're not going to widen from the grade rod working towards the excavator, Mr. Stewart?
A. I'm going
to widen the whole excavation from where this is
[indicating] all the way up here [indicating]. This
is all going to be widened. And I'm widening it up here
[indicating] because the -- because the amount of dirt
that I have was becoming too much on top of the spoil
pile to where it was becoming incompliant with
OSHA. That's why I took this [indicating] swipe here, and then once I was complete digging everything out, I was going to move my machine on top of the spoil pile and dig back that spoil pile and pull it back.
Q.
Okay. So I want to be clear, Mr. Stewart. From the area where the grade rod is located
and angled on a slope, your intent was to widen that area from the grade rod towards the excavator.
A. Yes.
Q.
Okay. And you would agree with me that between
the grade rod and the excavator, you have a crow bar or a
pry bar and a shovel; correct?
A. Correct.
(Tr.
789–90). The foregoing colloquy
illustrates the shifting and labored explanations provided by Respondent. First, Stewart is widening the entire trench
to allow for the introduction of the manhole and associated equipment. Then, he
is merely taking a strip from the east side to widen the top of the excavation,
but not the entire slope. Then, his
rationale shifts again—the reason he took the strip on the upper east side of
the excavation was to prevent the spoil pile from becoming overloaded and,
therefore, noncompliant. This, perhaps, is his most confusing explanation. In
order to prevent the spoil piles from becoming noncompliant, Stewart testified
he removed the existing four-foot gap separating the spoil pile from the trench
wall in a single swipe. (Tr. 790, 917). But, if Stewart was planning on reestablishing
the gap after he finished widening the trench, it is unclear to the Court why
it would matter if that particular portion of the trench was noncompliant when
there were not any employees in the trench at the time. For that matter, it is
unclear to the Court, as it was to Assistant Area Director Scott Overson, why
Respondent would remove the strip from between the spoil pile and the trench,
as such a swipe would cause the contents of the spoil pile to spill into the
trench. (Tr. 657).
To
further illustrate this inconsistency, AAD Overson made an interesting
observation about the mark made by the excavator in its attempt to widen the
trench beyond the trench rod. (Tr. 655).
According to Overson, the photograph in Exhibit C-2 at 8 shows an upside
down V-shaped mark directly above the trench rod. As noted by Overson, this is not a deep cut;
it did not change the position of the spoil pile or the bank. (Tr. 654). Instead, the cut appears to be on the surface
and is surrounded on either side by a flush transition from spoil pile to
trench, which illustrates that the spoil pile was in essentially the same
condition as it was prior to the scoop being taken from that area. (Tr. 654–55;
Ex. C-2 at 8c).
Based
on the foregoing, the Court finds Shearry and Gorneau were exposed to the
hazard imposed by the improperly set back spoil piles. Even if the Court were
to accept that Stewart was able to dig in the area near the trench rod, the
lack of dirt in the bottom of the trench below belies any argument that enough
dirt was moved to obscure a four-foot setback over a distance of 30 feet. Based
on the impressions left by the excavator in the area surrounding the trench
rod, however, the Court finds Stewart was digging into an already noncompliant
spoil pile. For that matter, the
noncompliant spoil pile ran from the location where Shearry and Gorneau were
working back to the ladder. Thus, even
if the area to the south of the trench rod (towards the excavator) was widened
after the employees’ departure from the trench bottom, that still left them
exposed as they exited the trench along the portion of the spoil pile north of
the trench rod until they reached the ladder. Accordingly, the Court finds
Respondent’s employees were in the zone of danger while working in the bottom
of the trench.
iv.
Respondent, Through its On-Site Foreman, Knew of the
Hazardous Condition
“To
establish knowledge, the Secretary must prove that the employer knew or, with
the exercise of reasonable diligence, should have known of the conditions
constituting the violation.” Central
Florida Equip. Rentals, Inc., 25 BNA OSHC 2147 (No. 08-1656, 2016). To satisfy this burden, Complainant must show
“knowledge of the conditions that
form the basis of the alleged violation; not whether the employer had knowledge
that the conditions constituted a hazard.” Id. “Although the Secretary has the burden to
establish employer knowledge of the violative conditions, when a supervisory
employee has actual or constructive knowledge of the violative conditions, that
knowledge is imputed to the employer, and the Secretary satisfied his burden of
proof without having to demonstrate any inadequacy or defect in the employer’s
safety program.” Dover Elevator Co.,
16 BNA OSHC 1281 (No. 91-862, 1993); see
also Dana Container, 25 BNA OSHC 1776 (No. 09-1184, 2015) (citing Dover for same proposition).
The
parties agree Galindo was the foreman and competent person. Galindo, himself, testified he was the only
acting supervisor on site and that it was his responsibility to ensure the
conditions of the trench were safe for his employees to enter. (Tr. 252, 254). This
was confirmed by his boss, Chip Stroschein. (Tr. 873). Galindo was not only obligated to ensure
trench conditions were safe and compliant, but he was also physically in
position to view the conditions of the trench. (Ex. C-1, seg. 2). As noted above, Galindo testified in
deposition that, just as OSHA arrived, his employees were exiting the trench.
Thus, Galindo permitted his employees to work in a noncompliant trench and was
directly aware of their exposure to the violative condition. According to Commission
precedent, Galindo’s knowledge of his employees’, as well as his own,
misconduct is properly imputed to Respondent.[10]
Respondent,
however, has argued the conduct of Shearry, Gorneau, and Galindo was the
product of unpreventable supervisory misconduct. In order to prove this
defense, an employer must show it: “(1) established work rules designed to
prevent the violative conditions from occurring; (2) adequately communicated
those rules to its employees; (3) took steps to discover violations of those
rules; and (4) effectively enforced the rules when violations were discovered.”
Manganas Painting Co., 21 BNA OSHC 1964, 1997 (No. 94-0588, 2007). The burden of establishing this affirmative
defense is “more rigorous” because the supervisor’s duties include
“protect[ing] the safety of employees under his supervision” and the
supervisor’s misconduct is “strong evidence that the employer’s safety program
is lax.” CBI Servs., Inc., 19 BNA
OSHC 1591, 1603 (No. 95-0489, 2001), aff’d
per curiam, 53 Fed. Appx. 122 (D.C. Cir. 2002) (unpublished).
Complainant
does not dispute Respondent had a specific work rule requiring daily
inspections, which included a requirement that equipment and spoil materials be
placed at least two feet back from the edge of the trench. (Ex. R-4 at 31). Respondent also introduced evidence
illustrating how that rule, as well as others, was communicated to its
employees. Specifically, Chip Stroschein
testified that safety rules are communicated to employees through weekly
workshop safety meetings and daily toolbox talks. (Tr. 852–53; Ex. R-9). As regards regular, full-time employees such
as Galindo and Stewart, the Court agrees.
But, as regards Shearry, who was a temporary employee on loan from Command
Center, Respondent’s training regime fell short of what is required.
According
to Shearry, who had no prior trenching experience, he attended a single safety
meeting of approximately 15–20 minutes before being assigned to work in the
bottom of the trench. (Tr. 587, 595–97).
Galindo testified he trained Shearry but could not remember whether he
had reviewed the safety program or project manual with Shearry prior to the
beginning of the day’s work. (Tr. 420).
This much appeared evident when Shearry testified at trial that he
believed spoil material should be placed somewhere between 10 and 15 feet back
from the trench wall. (Tr. 597). Thus, with respect to Shearry, at least, the
Court finds Respondent failed to prove the defense of unpreventable employee
misconduct.
The
Court also finds Respondent failed to prove the supervisory misconduct with
respect to Galindo, albeit for different reasons; namely, its failure to both
take adequate steps to discover violations and to enforce the rules when such
violations are found. An effective
safety program requires “a diligent effort to discover and discourage
violations of safety rules by employees.” Paul
Betty d/b/a Betty Bros., 9 BNA OSHC 1379, 1383 (No. 76-4271, 1981). In the
absence of such evidence, the Commission has held that the employer “could not
have enforced its work rules effectively.” Am.
Sterilizer Co., 18 BNA OSHC 1082 (No. 91-2494, 1997) (citing Tampa Shipyards, Inc., 15 BNA OSHC 1533,
1539 (No. 86-360, 1992)).
Stroschein
testified he conducted random inspections of Respondent’s worksites to ensure
compliance; however, he also admitted he does not document the results of his
inspections, nor does he review the daily inspection sheets completed by
Galindo as part of his audit process. (Tr. 866, 900). This was particularly problematic in
Galindo’s case, because it appears that Galindo had been improperly filling out
daily reports, which identify hazards, protection methods, and other safety
issues during the entire period of his work at the Trillium worksite. (Tr. 321–43;
Ex. C-8). Though Stroschein claims he
was at the worksite almost every other day, he did not take the opportunity to
review Galindo’s daily logs to ensure they tracked the actual conditions at the
worksite. (Tr. 898–900). For example, on
the form, Galindo indicated he used multiple forms of cave-in protection,
including trench boxes and shores, even though sloping was used as the primary
form of protection. (Tr. 321–43; Ex. C-8).
Further, he also failed to accurately record the conditions as they existed,
or as they changed throughout the day. According to Stroschein, it was not
until after he read Galindo’s
deposition transcript, nearly eight months after the inspection, that he
determined Galindo was failing to properly evaluate his worksite and was, in
fact, using the wrong worksheet for excavation worksites. (Tr. 899).
This
failure appears to have had a trickle-down effect. On cross-examination, Galindo admitted that
he was “not positive about all this paperwork.” (Tr. 419). “All this paperwork”, as it turns out, was
the employee safety manual, project manual, and disciplinary program, all of
which he was responsible for implementing as a manager. (Tr. 416–19). Galindo’s lack of familiarity with the
documents governing his work as a foreman, coupled with Stroschein’s admitted
failure to effectively review Galindo’s daily work logs, call into question how
effective Respondent could have been in its attempts to discover and correct
violations. Indeed, had Stroschein been thorough in his review, he would not
have needed to wait until many months later, during Galindo’s deposition, to
find out Galindo had not been fulfilling his job duties. Thus, even though Stroschein made regular
visits to his worksites, the Court finds such checks were not effectively performed.
Finally,
the Court finds Respondent’s disciplinary program was lacking. Although Galindo and Stroschein both stated
they had terminated and disciplined employees in the past, there is a notable
dearth of any formal disciplinary actions. (Ex. C-16). Indeed, the only “disciplinary” records
admitted into evidence appear to be related to job performance, attendance, and
a probationary period for a new hire. (Ex. C-16). More problematic, however, was the general
attitude towards discipline. According
to Stroschein, though he was aware Respondent required verbal disciplinary
actions to be documented, he had not been adhering to that policy. (Tr. 903;
Ex. C-11 at 15–16). Further, he also
testified that Wes Kroh, another owner of Respondent, had not been documenting
those instances either. (Tr. 903). Thus,
as pointed out by Complainant, Respondent did not have a way to track
progressive discipline for the same issue, which Stroschein admitted could
result in someone being verbally reprimanded multiple times by a manager
without the other managers knowing about it. (Tr. 903). Indeed, this seems to have been the case with
Galindo, who testified to being verbally reprimanded twice for safety
violations and yet not one of those instances was documented. (Tr. 423, 446,
903).
To
prevail on the affirmative defense of employee misconduct, Respondent cannot
simply rely on testimony that people were disciplined. There must be evidence that the program is
effective. See Centex Rooney Constr. Co.,
16 BNA OSHC 2127, 2130 (No. 92-0851, 1994). “The conventional way to prove the enforcement
element is for the employer to introduce evidence of a disciplinary program by
which the company reasonably expects to influence the behavior of employees”,
such as a progressive disciplinary program.
Precast Svcs, Inc., 17 BNA
OSHC 1454 (No. 93-2971, 1995); see also Asplundh Tree Expert Co.,
7 BNA OSHC 2074 (No. 16162, 1979) (employer introduced evidence of company
policy calling for a stern oral or written reprimand for the first violation,
followed by discharge for a second violation). The progressive disciplinary program must be
more than a “paper program”, requiring “evidence of having actually
administered the discipline outlined in its policy and procedures.” See,
e.g., Connecticut Light & Pwr. Co., 13 BNA OSHC 2214 (No. 85–1118,
1989) (reprimand letters issued); Pace Constr. Corp., 14 BNA OSHC 2216
(No. 86–758, 1991) (perennial verbal warnings ignored on a widespread basis).
Notwithstanding
its rather thorough paper policy, there is no evidence Respondent effectively
enforced it. Indeed, Stroschein admitted that neither he, nor Wes Kroh,
documented disciplinary actions, whether they were minor or were so serious as
to require termination. The only disciplinary records introduced do not appear
related to safety matters, and are instead performance-related. (Ex.
C-16). The lack of consistency, as well
as Respondent’s apparent inability to track progressive disciplinary problems,
show that Respondent’s disciplinary program is just a document. Because it does
not adhere to that policy, Respondent cannot reasonably be expected “to
influence the behavior of [its] employee[s].” Precast, supra. Accordingly, the Court finds Respondent
failed to establish the affirmative defense of unpreventable employee (or
supervisory) misconduct.
v.
The Violation Was Serious
A violation is “serious” if there was a substantial
probability that death or serious physical harm could have resulted from the
violative condition. 29 U.S.C. § 666(k).
Complainant need not show that there was a substantial probability that
an accident would actually occur; he need only show that if an accident
occurred, serious physical harm could result.
Phelps Dodge Corp. v. OSHRC,
725 F.2d 1237, 1240 (9th Cir. 1984). If
the possible injury addressed by a regulation is death or serious physical
harm, a violation of the regulation is serious.
Mosser Construction, 23 BNA
OSHC 1044 (No. 08-0631, 2010); Dec-Tam
Corp., 15 BNA OSHC 2072 (No. 88-0523, 1993).
The Court finds the violation alleged in Citation 1,
Item 1a is serious. According to CSHO
McElvany, an improperly set back spoil pile poses a couple of different
hazards, including spoil material sliding into the excavation or a cave-in
caused by additional weight on the trench wall. (Tr. 79). McElvany described how trench cave-ins
represent a large number of the accidents and fatalities that OSHA investigates.
(Tr. 78). AAD Overson provided
additional details outlining the serious nature of this hazard. According to Overson, an average cubic yard
of dirt can weigh over three-thousand pounds. (Tr. 622). Thus, “when you look at the size of these
spoil piles, you’ve got tens of thousands of pounds of soil sitting on the edge
. . . .” (Tr. 622). Those thousands of
pounds of soil can cause serious damage.
Overson testified about one such case wherein an employee was struck by
soil that had sloughed off of the spoil pile, rolled into the trench box, and
broke his leg. (Tr. 615). The evidence
convincingly establishes that an accident involving these spoil piles could
cause a serious injury or possibly death.
Based on the foregoing, the Court finds Complainant
has established a violation of 29 C.F.R. § 1926.651(j)(2). Accordingly, Citation 1, Item 1a shall be
AFFIRMED.
B.
Citation 1, Item 1b
With respect to Citation 1, Item 1b,
Complainant alleges a violation of 29 C.F.R. § 1926.651(k)(2), claiming Galindo
failed to remove employees from the hazardous area caused by the improperly
placed spoil pile. Although not specifically addressed by Respondent, the Court
finds this violation to be duplicative of Citation 1, Item 1a.
According
to the Commission, violations are considered duplicative “where the standards
cited require the same abatement measures, or where abatement of one
citation will necessarily result in the abatement of the other item as well.”
Rawson Contractors, 20 BNA OSHC 1078 n.5 (No. 99-0018, 2003) (emphasis
added) (citing Flint Eng. & Constr.
Co., 15 BNA OSHC 2052, 2056–57 (No. 90-2783, 1992)).
To prove a violation of 29 C.F.R. §
1926.651(k)(2), Complainant must establish that “the competent person found
evidence of a situation that could result in a possible cave-in, indications of
failure of protective systems, hazardous atmospheres, or other hazardous
conditions.” To prove a violation of 29
C.F.R. § 1926.651(j)(2), Complainant must establish employees were not
protected from the hazardous condition posed by the spoil piles. The hazard faced by employees under either
scenario is the same. Depending on the
situation, however, the abatement could be different. When viewed in isolation, the proper
abatement for a violation of 1926.651(k)(2) would be removal of the employee
from the excavation until such time as the hazard has been removed, as opposed
to 1926.651(j)(2), which would require the proper setback of the spoil piles. Under the facts of this case, however, if
Respondent had properly set back the spoil piles, there would have been no need
to remove the employee from the excavation.
A nearly identical issue was addressed by ALJ
Frye in Pentecost Contracting Corp.,
17 BNA OSHC 1429 (No. 92-3789 et al.,
1995). Similar to this case, the
respondent company was cited for violating both 1926.651(k)(2) and
1926.652(a)(1). Citing favorably to the
Commission’s holding in Capform, 13
BNA OSHC 2219 (No. 84-556, 1989), ALJ Frye held, “If the Respondent had
complied with the first standard and used proper shoring techniques to avoid
the danger of cave-in, he would have also been in compliance with the second
standard, because without the hazard of a cave-in, there is no need to remove
the employees from the excavation.” Pentecost, 17 BNA OSHC 1429. This case is no different. If Respondent had complied with the setback
requirements for spoil piles, there would have been no need to remove the
employees from the trench because there would be no hazard in the first
instance. Thus, abatement of Item 1a
would necessarily abate Item 1b.
Accordingly, Citation 1, Item 1b is hereby VACATED.
V.
Penalty
In
calculating appropriate penalties for affirmed violations, Section 17(j) of the
Act requires the Commission give due consideration to four criteria: (1) the size of the employer’s business, (2)
the gravity of the violation, (3) the good faith of the employer, and (4) the
employer’s prior history of violations.
Gravity is the primary consideration and is determined by the number of
employees exposed, the duration of the exposure, the precautions taken against
injury, and the likelihood of an actual injury. J.A. Jones Construction Co.,
15 BNA OSHC 2201 (No. 87-2059, 1993). It
is well established that the Commission and its judges conduct de novo penalty determinations and have
full discretion to assess penalties based on the facts of each case and the applicable
statutory criteria. Valdak Corp., 17 BNA OSHC 1135 (No. 93-0239, 1995); Allied Structural Steel, 2 BNA OSHC 1457
(No. 1681, 1975).
Complainant
proposed a penalty of $1,200, which is premised on CSHO McElvany’s
determination that the severity of any possible injury was low and the
likelihood of any accident also being low. (Tr. 152). McElvany came to this conclusion because the
trench was properly sloped and the spoil material was very sandy, making it
unlikely that large chunks would fall into the trench. (Tr. 152–53). Further, though Complainant did not provide
any discounts for history or good faith, it still provided a 60% discount on
the originally assessed penalty due to the size of Respondent’s business, which
only had seven employees. (Tr. 153–54).
The Court agrees with Complainant’s assessments of gravity and the
application of the appropriate reductions. Accordingly, the Court finds the
penalty of $1,200 is appropriate and shall be assessed.
ORDER
The foregoing Decision constitutes the Findings of Fact and
Conclusions of Law in accordance with Rule 52(a) of the Federal Rules of Civil
Procedure. Based upon the foregoing
Findings of Fact and Conclusions of Law, it is ORDERED that:
1.
Citation
1, Item 1a is AFFIRMED as a serious violation of the Act, and penalty of $1,200
is ASSESSED.
2.
Citation
1, Item 1b is VACATED.
SO ORDERED
/s/
Peggy
S. Ball
Judge, OSHRC
Date: August 2, 2018
Denver, Colorado
[1]. For the sake of brevity, the remaining stipulations and undisputed facts will not be reproduced herein; however, subsequent references to stipulations and undisputed facts will take the following form: (Stip. No. ___) and (UF No. __).
[2]. This time frame is predicated on the stop time from the first video segment in CSHO McElvany’s recording to the start time of the second segment. (Tr. 656; Ex. C-1). Although the time stamp on the video is clearly incorrect, nobody questioned whether the time elapsed was inaccurate.
[3]. The parties independently determined the soil was Type C but did not stipulate to such.
[4]. A leading question is “one which puts the answer in the mouth of the witness by suggesting the desired answer.” Charles B. Gibbons, Federal Trial Objections 326 (4th ed. 2012) (citing Roy v. Austin Co., 194 F.3d 840 (7th Cir. 1999)). The following transcript pages reflect a small sample of such questions during Respondent’s case-in-chief: 492, 590–93, 742–44, 747, 835.
[5]. According to Galindo, he threw a shovel into the bottom of the excavation to mark the end of the sewer line for Stewart. (Tr. 482). Whether or not this is the case, the Court finds it interesting that so many different tools and implements were used to do the exact same thing. (Ex. C-2 at 3).
[6]. There was some discussion about whether a particular finger doing the pointing in segment two of CSHO McElvany’s video belonged to CSHO McElvany or Galindo. (Tr. 89–90, 139, 237, 366). Irrespective of who pointed and to what, the Court finds both Galindo and CSHO McElvany agreed on the location under discussion.
[7]. Even on a topic as benign as when the Trillium project started, Galindo wavered on the estimate of time involved. (Tr. 288).
[8]. They also testified that, in some instances, the excavator would drive onto the spoil pile and pull the material back from the edge of the trench. (Tr. 488).
[9]. Regarding those tools, Galindo testified they had an opportunity to retrieve the tools before Stewart began digging: “I said, ‘Why did you forget the grade stick and you didn’t mark the end of the pipe? He’s going to end up burying it once he starts digging for a manhole.’” (Tr. 482). If digging had not yet commenced, the Court is somewhat confused as to why Galindo did not just send Shearry and Gorneau back into the trench to retrieve the tools. Unless, of course, there was no real reason to be concerned about them being buried.
[10]. The Eighth Circuit, one of the circuits to which this case may be appealed, has not yet addressed the question of knowledge in the context of supervisory misconduct; however, the D.C. Circuit, another court to which this case may be appealed, cites favorably to Commission precedent. See Daisy Const. Co., 527 Fed. Appx. 1 (D.C. Cir. 2013) (unpublished opinion).