UNITED
STATES OF AMERICA
OCCUPATIONAL
SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
Complainant, |
v. |
OVATION
PLUMBING, INC., |
Respondent. |
DOCKET NO. 17-0196
Appearances:
Sean J. Allen, Esq. & Timothy S. Williams,
Esq., U.S. Department of Labor, Office of the Solicitor, Denver, Colorado
For
Complainant
Stephen
B. Shapiro, Esq. & Alexis A. Reller, Esq., Shapiro Bieging Barger Otteson
LLP, Denver, Colorado
For
Respondent
Before: Administrative Law Judge
Brian A. Duncan
DECISION AND ORDER
Procedural History
Compliance
Safety and Health Officer Fred Peterson conducted an inspection of the Elevate
Wolff-Havana worksite in Englewood, Colorado on October 20, 2016. (Stip. No. 6). During the course of his inspection, CSHO
Peterson observed two of Respondent’s employees cross through a set of
guardrails onto an unprotected balcony. (Tr. 94; Ex. C-2). After observing the site of the violation and
conducting interviews, CSHO Peterson determined Respondent violated 29 C.F.R. §
1926.501(b)(1).
CSHO Peterson recommended, and Complainant
issued, a Citation and Notification of
Penalty (“Citation”) to Respondent, which alleges a single serious
violation of 29 C.F.R. § 1926.501(b)(1). Complainant proposed a total penalty of $4,811.00. Respondent timely contested the Citation,
claiming the exception found in the scope and application paragraph of 29
C.F.R. § 1926.500(a)(1). This brought
the matter before the United States Occupational Safety and Health Review
Commission (“Commission”) pursuant to Section 10(c) of the Occupational Safety
and Health Act of 1970, 29 U.S.C. § 651 et
seq. (“the Act”).
The
Chief Judge designated this matter for Simplified Proceedings. A trial was conducted in Denver, Colorado on September
25, 2017. Four witnesses testified at
trial: (1) CSHO Fred Peterson; (2) Clyde
George, Superintendent for Martines Palmeiro Construction (MPC); (3) Paul
Wilson, Respondent’s site foreman; and (4) Edward McMillan, Respondent’s owner.
Both parties timely submitted post-trial
briefs for the Court’s consideration.
Jurisdiction & Stipulations
The
parties stipulated the Commission has jurisdiction over this proceeding
pursuant to Section 10(c) of the Act. (Tr. 38–39). The parties
also stipulated that, at all times relevant to this proceeding, Respondent was
an employer engaged in a business and industry affecting interstate commerce
within the meaning of Sections 3(3) and 3(5) of the Act, 29 U.S.C. § 652(5). (Tr.
39). See
Slingluff v. OSHRC, 425 F.3d 861 (10th Cir. 2005). The parties also stipulated to other factual
matters, which were read into the record.[1]
(Tr. 38–40).
Factual Background
The
Inspection
CSHO
Fred Peterson conducted an inspection of the Elevate Wolff-Havana project
pursuant to Complainant’s construction inspection program. The construction program uses a randomly
generated list of construction sites, which are assigned to individual area
offices to be inspected within a one-month time frame. (Tr. 53). Elevate Wolff-Havana is a multi-unit
residential construction project with eleven to twelve multi-story buildings.
(Tr. 63–64). At the time of the
inspection, the individual buildings were in various stages of completion, ranging
from 10 to 85 percent complete. (Tr. 63). After he arrived, CSHO Peterson met with the
superintendent, Clyde George, and the project manager, Lisa Marini, both of
whom worked for the general contractor, MPC. (Tr. 65). George, Marini, and Chris Feagle, a
representative from Safety First,[2]
accompanied CSHO Peterson during his inspection.
During
the walkaround, CSHO Peterson saw two workers cross through a guardrail onto a
second-floor balcony of Building 5.
George and Feagle confirmed to CSHO Peterson they saw the employees cross
through the guardrail. (Tr. 72). At that
time, the guardrail was located at the entrance onto the balcony, which was
accessed through an opening designed for a sliding glass door. Wilson testified
he asked MPC multiple times to move the guardrails to the perimeter of the
balcony but received no response. (Tr. 244).
Thus, once on the balcony and beyond the guardrail, the two workers were
not protected from the fall hazard posed by the open balcony, which was more
than 10 feet above the ground below. (Tr. 72, 122; Ex. C-2, C-8). CSHO Peterson was only able to observe the
two workers enter onto the balcony, after which they remained out of sight
until he met with them inside of the building.[3]
As
he went upstairs to meet with the workers, CSHO Peterson came across a
different, unrelated violation, which he stopped to address. (Tr. 75–76). According to CSHO Peterson, work activities
were occurring throughout all of Building 5, including the second floor. By the time he reached the second floor and
actually encountered the two workers, approximately twenty minutes had passed,
at which point they had already returned to the safe side of the guardrail. (Tr.
77).
Once
he arrived upstairs, CSHO Peterson met with Paul Wilson and Brad Pezick, who
work for Ovation Plumbing. Paul Wilson,
Ovation’s foreman, told CSHO Peterson he went onto the balcony in order to
access the utility closet, which was designed to eventually hold a hot water
heater. At that point in the
construction process, Ovation’s crew had installed the hot and cold water taps
in the closets on all floors of Building 5, but the hot water heaters had not
yet been installed. (Tr. 192–93). Wilson
told CHSO Peterson he went onto the unguarded balcony and into the closet
solely to take measurements for the placement of a regulator vent. (Tr. 83). A regulator vent is designed to remove minute
amounts of excess gas produced by the water heaters. (Tr. 194).
Building code dictates the regulator must be placed three feet away from
an open window, so Wilson wanted to ensure proper placement. (Tr. 201).
Wilson
testified he told Pezick, a non-supervisory employee, to stay behind the
guardrail and he would demonstrate where to install the vent while Pezick
observed though the spaces between the studs separating the utility closet from
the main living area. (Tr. 201).
Instead, Pezick followed Wilson through the guardrail, onto the balcony,
and into the closet. (Tr. 72–73, 78). It
is unclear whether Pezick disregarded Wilson’s instructions or did not hear
him. (Tr. 209). Regardless, Wilson said
he was unaware Pezick was behind him until he was doing his measurements, after
which they returned to the protected side of the balcony guardrail. (Tr. 197–98). At trial, Wilson estimated they were on the
balcony/closet area for no more than 45 seconds; however, CSHO Peterson
testified Wilson told him they had been on the balcony for approximately five
minutes. (Tr. 82–85; 248).
CSHO
Peterson determined Respondent violated 29 C.F.R. § 1926.500(b)(1) when Wilson
and Pezick went beyond the guardrail to the balcony and were exposed to a
ten-foot drop without proper fall protection. According to CSHO Peterson, the
balcony was roughly six feet wide between the guardrail and the edge. (Tr. 74;
Ex. C-8A). The entrance to the closet
was closer, roughly two feet away from the edge. (Tr. 110). Due to the height of the balcony, the lack of
fall protection, and Wilson’s and Pezick’s proximity to the edge, CSHO Peterson
determined the violation was serious.
A
Coincidental Day of Training
On
the morning of the inspection, MPC held/sponsored a toolbox talk, which
addressed fall protection. (Tr. 164–69; Ex. C-7). As part of the presentation, Clyde George
discussed 29 C.F.R. § 1926.500(a)(1), which, in addition to describing the
scope of Subpart M, provides a limited exception to the general rule of fall
protection. Prior to this point, Wilson
had never heard of this exception, which applies to inspection-related
activities under certain conditions. See 29
C.F.R. § 1926.500(a)(1). Respondent
espouses a 100% fall protection policy and has never discussed this exception
in any of its training programs, manuals, or handbooks.[4]
(Tr. 208).
When
it came time to address the placement of the regulator vents in the second
floor closets, Wilson found that the guardrails had not been moved to the edge
of the balcony as requested, thereby leaving any occupant of the balcony
exposed to a fall. (Tr. 244). Wilson
determined a limited excursion onto the balcony for the sole purpose of taking
measurements for future construction activities would be within the ambit of
the exception discussed by the general contractor earlier that morning.
Equipped with nothing more than a tape measure, Wilson testified he carefully
stepped through the guardrail and stayed close to it as he moved toward the
closet. (Tr. 246–47). Once he completed
his measurements—and discovered the presence of his subordinate—Wilson returned
to the protected side of the guardrail. (Tr. 247–48). Wilson testified he had no intention of
beginning the installation of the regulators that day owing to the placement of
the guardrail and thus limited his activities to measurements. (Tr. 198–99).
Discussion
Citation
1, Item 1
Complainant alleged a serious
violation of the Act in Citation 1, Item 1 as follows:
29 CFR 1926.501(b)(1):
Each employee on a walking/working surface with an unprotected side or
edge which was 6 feet or more above a lower level was not protected from
falling by the use of guardrail systems, safety net systems, or personal fall
arrest systems.
a)
Building 5: On or
about November 20, 2016, and at times prior, two worker[s] were exposed to
falling approximately 10 feet to the ground below when they crossed the
guardrail at the entrance to a second floor balcony with an unprotected edge.
Citation and Notification of Penalty at 6.[5]
Undisputed Matters
To
establish a violation of an OSHA standard, Complainant must prove, by a
preponderance of the evidence, that: (1)
the cited standard applied to the facts; (2) the employer failed to comply with
the terms of the cited standard; (3) employees were exposed or had access to
the hazard covered by the standard, and (4) the employer had actual or
constructive knowledge of the violative condition (i.e., the employer knew, or with the exercise of reasonable diligence
could have known). Atlantic Battery
Co., 16 BNA OSHC
2131 (No. 90-1747, 1994).
During
trial, and also in its brief, Respondent agreed that certain matters were not
in dispute, including: (1) that Wilson
and Pezick were exposed to the fall hazard; (2) that the terms of the cited standard
were violated; and (3) that the standard applies insofar as the exception found
at 1926.500(a)(1) does not apply. (Tr. 96–103). See also Resp’t Br. at 3. The trial record supports these
conclusions. The cited standard requires
fall protection when employees are exposed to unprotected sides and edges over
six feet above the ground. Wilson and
Pezick crossed through the guardrails onto an unprotected balcony, which was
more than six feet above the ground below, and did not use any other form of
fall protection. Accordingly, the
remaining issues are: (1) whether the exception found at 29 C.F.R. §
1926.500(a)(1) applies to Wilson and Pezick’s activities on the day of the
inspection; (2) whether Respondent had knowledge of the violation; and (3)
whether Respondent established the violation was the product of unpreventable
employee misconduct.
The Standard Applies
On its face, the cited standard
applies to the facts of this case. It requires “[e]ach employee on a walking/working
surface with an unprotected side or edge which is 6 feet (1.8 m) or more above
a lower level shall be protected from falling by the use of guardrail systems,
safety net systems, or personal fall arrest systems.” 29 C.F.R. §
1926.501(b)(1). Wilson and Pezick
circumvented the existing guardrail, which placed them on a balcony with an
unprotected edge more than 6 feet above the ground. Thus, the standard mandates
the use of fall protection. In most
cases, this alone would be sufficient to establish the applicability of the
standard; however, Respondent asserts the activities of Wilson and Pezick were
covered by the exception found at 29 C.F.R. § 1926.500(a)(1).
The
Exception Found at 29 C.F.R. § 1926.500(a)(1) Does Not Apply
Located at the very beginning of
subpart M, there is a limited exception to the general rule of fall protection.
It states:
This subpart sets forth requirements and criteria for
fall protection in construction workplaces covered under 29 CFR part 1926.
Exception: The provisions of this subpart do not apply when employees are
making an inspection, investigation, or assessment of workplace conditions
prior to the actual start of construction work or after all construction work
has been completed.
29 C.F.R. §
1926.500(a)(1). Thus, even if the cited
standard applies in the most technical sense, the exception in 1926.500(a)(1)
prohibits application of the subpart M standards when employees are conducting inspections,
investigations, or assessments prior to the beginning of construction or after
it has been completed. According
to the preamble to the standard:
OSHA has set this exception because employees engaged
in inspecting, investigating and assessing workplace conditions before the
actual work begins or after work has been completed are exposed to fall hazards
for very short durations, if at all, since they most likely would be able to
accomplish their work without going near the danger zone. Also, the Agency’s
experience is that such individuals who are not continually or routinely
exposed to fall hazards tend to be very focused on their footing, ever alert
and aware of the hazards associated with falling. These practical
considerations would make it unreasonable, the Agency believes, to require the
installation of fall protection systems either prior to the start of
construction work or after such work has been completed. Such requirements
would impose an unreasonable burden on employers without demonstrable benefits.
. . . .
Therefore, OSHA has decided to reword the provision to
make it clear that the exclusion only applies when the employer establishes
that employees are inspecting, investigating, or assessing workplace conditions
prior to the actual start of work or after the work has been completed. It was
OSHA’s intent when it proposed this provision that the exclusion would only
apply at the two times stated above, not during the period when construction
work is being performed.
Safety Standards
for Fall Protection in the Construction Industry, 59 Fed. Reg. 40,672, 46,675
(August 9, 1994).
Complainant
promulgated a narrow exception that is limited to a specific subset of
activities (inspection, assessment, or investigation) and to specific points in
time (before construction starts or after it concludes). Prior to construction beginning or after it
ends, the amount of time required to install fall protection systems would
likely be greater than the length of time the inspector needs to perform his
inspection, especially, as noted in the preamble, “since they most likely would
be able to accomplish their work without going near the danger zone” or would
only be exposed to fall hazards for “very short durations”. Id.
Commission
ALJs have consistently applied Complainant’s interpretation. See,
e.g., Kirtley Roofing, 25 BNA
OSHC 2250 (No. 15-0613, 2015) (ALJ Gatto) (finding employees who were moving
materials to set up a lifeline and applying sealant were not engaged in
inspection, investigation, or assessment of workplace conditions); R&S Roofing, LLC, 24 BNA OSHC 2151
(No. 12-2427, 2014) (ALJ Coleman) (finding employees engaged in seam work were
engaged in “an essential part of the roofing work itself, and not part of ‘an
inspection, investigation, or assessment of workplace conditions’”); Modern Bldg. Solutions, LLC, 23 BNA OSHC
1787 (No. 10-2559, 2011) (ALJ Welsch) (finding exception did not apply to
employee examining sheathing, who was also responsible for replacing missing
nails, removing 2x4 boards, and finishing the roof with tar paper and shingles);
Cleveland Constr., Inc., 18 BNA OSHC
1648 (No. 97-1356, 1998) (ALJ Simko) (finding inspection conducted by employee
was integral to his primary activity of cutting the mezzanine floor edge, which
occurred while construction was ongoing, and, thus, exception did not apply).
Notwithstanding the foregoing,
Respondent places significant emphasis on Seyforth
Roofing Co., 16 BNA OSHC 2031 (No. 90-0086, 1994). In Seyforth,
an employer was charged with violating 29 C.F.R. § 1926.500(g)(1),[6]
because it did not have any fall protection systems installed when an employee
fell to his death. Seyforth, 16 BNA
OSHC 2031 at *1. At the conclusion of
the previous workweek, Seyforth’s employees took down the roof’s warning line
system due to high winds. Id. When they returned the following Monday, the
employees did not re-install the warning lines on the main roof because they
only planned to work on the penthouse roof, where they would not be exposed to
the main roof’s perimeter. At some point
after lunch, Seyforth’s manager asked the designated foreman whether more
roofing materials were needed for the main roof. The foreman and three other employees went to
the edge of the parapet wall around the perimeter of the roof to take
measurements. While in the process of
measuring, one of the employees fell to his death. Id.
The ALJ vacated the citation on the
grounds of unpreventable employee misconduct. Id. Although the Commission affirmed the result, it did so on
different grounds.[7]
According to the Commission, the case was controlled by 1926.500(g)(2), which states:
The provisions of paragraph (g)(1) of this section do
not apply at points of access such as stairways, ladders, and ramps, or where employees are on the roof only to
inspect, investigate, or estimate roof level conditions. Roof edge
materials handling areas and materials storage areas shall be guarded as
provided in paragraph (g)(5) of this section.
29 C.F.R. §
1926.500(g)(2) (amended Feb. 6, 1995) (emphasis added).[8] Because it was undisputed the “employees were
at the edge of the roof for the sole purpose of taking measurements”, the
Commission determined “this type of measurement is precisely the type of work that was intended to be
exempted from the standard.” Seyforth,
16 BNA OSHC 2031 at *2 (emphasis added).
The Commission was further persuaded by the Secretary’s inability to
prove other employees were working on the main roof at the time the
measurements were being taken, because the exception’s applicability appeared
to be limited to when employees “are on the roof only to inspect, investigate, or estimate roof level conditions.”
29 C.F.R. § 1926.500(g)(2) (emphasis added). In other words, the exception was
only applicable when (1) an inspection, investigation, or estimate was being
performed, and (2) the inspection, investigation, or estimate was the ONLY
activity being performed on the roof at the time.
Respondent’s reliance on Seyforth is misplaced for two
reasons. First, the exception the
Commission relied upon is materially different than the exception at issue in this
case. As previously noted, subpart M was substantially amended in 1995, roughly
six months after Seyforth was
decided. See 59 Fed. Reg. 40,672
(discussing effective date of amended subpart M). Coincident with the amendment, the exception,
which was previously found only in subparagraph (g), was broadened to address
fall hazards in construction generally, as opposed to those found on
low-pitched roofs during built-up roofing operations. Compare 29 C.F.R. § 1926.500(a)(1) (current) with 29 C.F.R. § 1926.500(g) (amended Feb. 6, 1995). Second, though
the exception was broadened in terms of whom it applied to, it was also
narrowed to the extent that it only applied at specific points in time: before the actual beginning of construction
and after construction has been completed. See
id. § 1926.500(a)(1). While application of the old exception was limited
based on the activity being performed, the exception at issue in this case
added a restriction as to when those activities can occur. Because the Commission in Seyforth did not have to address whether
the events occurred before or after construction, its precedential value is
limited.
The burden of proving an exception to the
general requirements of a standard lies with the party claiming the benefit of
the exception. See Falcon Steel Co.,
16 BNA OSHC 1179 (No. 89-2883 et al.,
1993). Exemptions from remedial
legislation should be narrowly construed and limited to effect the remedy
intended. See Pennusco Cement and
Aggregates, Inc., 8 BNA OSHC 1378 (No. 15462, 1980). Applying these
principles to the case at bar, the Court finds Respondent failed to meet its
burden.
The plain language of 1926.500(a)(1)
is sufficient to divine its meaning.
There are only two times when an employer is excused from complying with
subpart M: (1) inspections occurring
“prior to the actual start of
construction work”, and (2) inspections occurring “after all construction work has been completed.” Id. § 1926.500(a)(1) (emphasis added). The time-related restrictions on the
exception are framed in absolute terms, not as a series of interim “starts” and
“finishes” that may occur during the course of a construction project. This understanding is clarified in the
discussion of the standard provided in the preamble to the final rule, which
states:
OSHA has decided to reword the provision to make it
clear that the exclusion only applies when the employer establishes that
employees are inspecting, investigating, or assessing workplace conditions
prior to the actual start of work or after the work has been completed. It was
OSHA’s intent when it proposed this provision that the exclusion would only apply at the two times stated above, not
during the period when construction work is being performed. As explained
in the preamble to the proposed rule, the exception would apply where an
employee goes onto a roof in need of repair to inspect the roof and to estimate
what work is needed. During such an inspection, guardrails, body belts, body
harnesses, safety nets, or other safety systems would not be required. However,
if inspections are made while construction operations are underway, all
employees who are exposed to fall hazards while performing these inspections
must be protected as required by subpart M. The intent of the provision is also
to recognize that after all work has been completed, and workers have left the
area, there may be a need for building inspectors, owners, etc. to inspect the
work. OSHA recognizes that in these situations, all fall protection equipment,
such as perimeter guardrail systems, may have been removed. OSHA is not
requiring the installation of the systems for a second time for inspectors,
because the Agency recognizes it would be unreasonably burdensome to require
the reinstallation of fall protection equipment after all the work has been
completed.
59 Fed. Reg. at
40,675 (emphasis added). The examples in
the preamble illustrate the absolute nature of the time restrictions and the
reason for their implementation. According
to the preamble, the installation of fall protection during an initial
assessment or after the completion of all construction would impose an
unnecessary burden on the employer. In
both examples, the act of installing the fall protection for the sole purpose
of conducting an inspection would likely expose the installer to far greater
hazards for a longer period of time than the person conducting the inspection,
who will be “exposed to fall hazards for very short durations, if at all, since
they most likely would be able to accomplish their work without going near the
danger zone.” Id. That the preamble
refers specifically to “the two times stated above” further buttresses the
Court’s conclusion the limitation is absolute.
Although Wilson was engaged in
inspection/assessment when he and Pezick entered onto the balcony, the Court
finds the exception does not apply because the inspection did not occur prior to
the actual start of construction, nor after all construction had been
completed. Respondent had started
construction in the water heater closets long before Wilson and Pezick entered
onto the balcony to perform their inspection. Even though Respondent’s crew had not yet
installed the regulator vents on the second floor, it had already installed the
plumbing for the water heaters throughout Building 5 and was in the process of
installing regulator vents on the first floor. (Tr. 195). Wilson’s measurements were simply a part of
the ongoing project to install regulator vents throughout the building, which,
itself, was part of the process of installing water heaters in the utility
closets. His ‘inspection’ did not occur
“prior to the actual start of construction”, nor was there any sense that it
occurred “after all construction ha[d] been completed
Nor
does this situation fit into the underlying rationale for the exception in the
first place—the exposure was entirely unnecessary. Unlike a roof repair,
wherein an on-site assessment is necessary to ascertain required materials and
anchor point locations at the outset, fall protection was already installed on
the balcony, just incorrectly for the purposes of Respondent’s necessary work
on the balcony. In other words, we are not talking about employees that did not
use fall protection because it was more hazardous or unduly burdensome to
install; rather, we are talking about employees circumventing existing fall
protection because it was incorrectly placed and inconvenient. It was not more hazardous nor unduly
burdensome to properly re-install the guardrails because many construction
projects were still scheduled to occur on or about the balcony. The installation of the regulator vent, the
water heater, and the door to the balcony would all eventually require fall
protection.
Based on the foregoing, the Court
finds Respondent failed to establish it is entitled to the exception found in
29 C.F.R. § 1926.500(a)(1). Accordingly,
the Court finds the standard applies and was violated.
Respondent Had Knowledge of the
Violation
As described above, Wilson crossed
through the guardrails onto the balcony and was followed shortly after by
Pezick. Wilson testified he told Pezick
to remain behind the guardrails and proceeded towards the closet, where he took
measurements and planned the installation of the regulator vent. Wilson claims he did not recognize Pezick went
beyond the guardrails until he completed his measurements and turned around to
go back inside the building. At that
time, Wilson recalled, he told Pezick to return to the other side of the
railing. Thus, the Court is confronted with the issue of knowledge from the
standpoint of Wilson’s awareness of Pezick’s misconduct, as well as Wilson’s
knowledge of his own misconduct.
Respondent
contends it did not, indeed could not, have knowledge of the violation for three
primary reasons: (1) Wilson did not know Pezick had followed him onto the
balcony even after he told him not to do so; (2) Wilson’s knowledge of his own
misconduct cannot be imputed to Respondent under Tenth Circuit precedent
because his misconduct was not foreseeable; and (3) Wilson had a good faith
belief his actions were in conformity with the exception found at
1926.500(a)(1). In response, Complainant
argues Wilson was actually aware of Pezick’s presence on the balcony and that
Respondent should be charged with Wilson’s knowledge as Respondent’s
supervisory agent. See John H. Quinlan d/b/a
Quinlan Enters. v. Sec’y of Labor, 812 F.3d 832, 841 (11th Cir. 2016). Further, Complainant argues Respondent should
be charged with knowledge of Wilson’s misconduct because it was foreseeable in
light of Respondent’s deficient fall protection program. The Court agrees with
Complainant.
In
order to prove Respondent had knowledge, Complainant must show that Respondent
knew or, with the exercise of reasonable diligence, could have known of the
violation. Dun-Par Engineered Form Co.,
12 BNA OSHC 1962, 1965 (No. 82-928, 1986).
The key is whether Respondent was aware of the conditions constituting a
violation, not whether it understood the conditions violated the Act.[9] Phoenix Roofing, Inc., 17 BNA OSHC 1076,
1079–80 (No. 90-2148, 1995). Complainant
can prove knowledge of a corporate employer through the knowledge, actual or
constructive, of its supervisory employees. Dover
Elevator Co., 16 BNA OSHC 1281, 1286 (No. 91-862, 1993). If a supervisor is, or should be, aware of
the noncomplying conduct of a subordinate, it is reasonable to charge the
employer with that knowledge. See
Mountain States Tel. & Tel. Co. v. OSHRC, 623 F.2d 155, 158 (10th Cir.
1980). But, if the misconduct is committed
by the supervisor, a different situation is presented. Id.
“When the law of
the circuit to which a case would likely be appealed differs from
the Commission’s case law, we apply the law of
that circuit . . . .” Brooks Well Serv., Inc., 20 BNA OSHC 1286,
1292 (No. 99-0894, 2003). In the
Tenth Circuit, to which this case could be appealed, a supervisor’s knowledge
of his own misconduct is not imputable to his employer unless it can be shown
the misconduct was otherwise foreseeable. Mountain
States, 623 F.2d at 158. Like other
circuits, the Tenth Circuit requires Complainant to show foreseeability under
these circumstances to prevent what it perceives to be a misappropriation of
the burden of proof. See id.
The court found that imputing to the employer the supervisor’s knowledge
of his own misconduct would be to remove Complainant’s burden to establish one
of the prima facie elements and, consequently, place the risk of nonpersuasion
on Respondent. Id.
Respondent’s Knowledge of Pezick’s Actions
After reviewing the entire record,
the Court finds Respondent’s argument that Wilson was unaware of Pezick’s
presence on the balcony is unconvincing.
Wilson may have told Pezick to remain behind the guardrail, but he also
testified he intended to provide instructions to Pezick through the closet
studs inside the apartment unit while he was taking measurements inside the
closet. (Tr. 201). The Court finds it
hard to believe Wilson was unaware Pezick was standing behind him—when he was
supposed to be in an adjacent room looking through gaps in the studs—given the
relatively small amount of space inside the closet, which CSHO Peterson
testified was no more than four-feet wide by four-feet deep.
From this set of facts, the Court
finds it is reasonable to infer Wilson knew or, at the very least, should have
known Pezick was right behind him on the balcony. If the purpose of Wilson’s trip into the
closet was, as he testified, to both take measurements and “line out”[10]
to Pezick the process for installing the regulator vents, then one of two
conclusions is possible: (1) either
Wilson was instructing Pezick inside the closet, or (2) Wilson should have been
aware that Pezick followed him, because Pezick was not on the other side of the
closet studs where he was supposed to be to receive instructions. According to CSHO Peterson, he observed two
employees, one after another, cut through the guardrail and walk across the
balcony out of sight. (Tr. 73). The only
location that would place them out of sight is the area immediately adjacent to
or in utility closet, which only measured four feet by four feet, square. In fact, CSHO Peterson testified that Wilson
and Pezick both told admitted they were in the closet while Wilson was taking
measurements, which explains why CSHO Peterson lost sight of them after they
entered the balcony. (Tr. 78). Even though Wilson estimates he spent less than
a minute inside the closet, this was more than enough time for him to realize
Pezick was not where he was supposed to be, especially when he started “lining
out” the project. See ComTran Group, Inc.
v. U.S. DOL, 722 F.3d 1304, 1308 (11th Cir. 2013) (“An example of
constructive knowledge is where the supervisor may not have directly seen the
subordinate’s misconduct, but he was in close enough proximity that he should
have.”). Accordingly, the Court finds
Respondent, through Wilson, had constructive knowledge of Pezick’s violation of
29 C.F.R. § 1926.501(b)(1).
Respondent’s Knowledge of Wilson’s
Actions
The key to establishing employer knowledge
in this context is foreseeability. In order to prove foreseeability,
Complainant must show Respondent’s safety program is deficient in a way that
would show the supervisor’s misconduct was preventable.[11] This
burden can be met through proof of “inadequacies in safety precautions,
training of employees, or supervision.” Capital
Elec. Line Builders of Kansas Inc. v. Marshall, 678 F.2d 128, 130 (10th
Cir. 1982). In the context of fall
protection, Respondent’s safety program was deficient in all three areas.
In the particular arena of fall protection,
Respondent’s safety program was inadequate. Respondent has multiple safety
program documents, including an Employee Handbook, a printed Safety Program, and
a safety program specific to the Elevate Wolff-Havana project, but the only discussion
of fall protection relates specifically to the use of scaffolds, which are
covered by subpart L and were not part of Wilson’s work on the day of the
inspection. (Ex. C-12 at 16, C-14, C-15).[12] The
Employee Handbook does not discuss fall protection, and the site-specific safety
program appears to be little more than a reproduction of Respondent’s general
safety program, with no additional measures regarding fall protection outside
of scaffolds. (Compare Ex. C-12 with C-15). The lack of any fall protection rules, let
alone a comprehensive program, is a substantial deficiency.
Respondent claims, though there is
no documentation, that it has a 100% fall protection rule. (Tr. 208). The only documentation of Respondent’s fall
protection “program”, other than that related to scaffolds, consists of a
single worksite safety meeting on June 6, 2016, which covered fall protection on
roofs. (Tr. 219–20; Ex. R-33). The
remaining weekly training topics covered other safety issues, ranging from GFCIs
to forklifts. (Ex. R-25). The only other
documented training sessions for fall protection were the MPC toolbox talk,
which discussed the disputed exception, and the fall protection training
Respondent provided after the inspection occurred. (Ex. R-16, R-24). McMillan testified Wilson and Respondent’s
other foreman were required to take the OSHA 10-hour course, which purportedly
discusses fall protection, but no documentation of the course materials was
submitted into evidence. (Tr. 263; Ex. C-20).
While the absence of a written rule
does not, itself, prove Wilson’s actions were foreseeable, verbal rules, such
as Respondent claims here, must be clearly and effectively communicated to
employees. See Aquatek Systs. Inc.,
2006 WL 741751 (No. 03-1351, 2006) (citing Capform,
Inc., 16 BNA OSHC 2040, 2043) (No. 91-1613, 1994)). The only fall protection training provided by
Respondent prior to the inspection was specific to roofing and did not address
the hazards confronted by its crew at Building 5 on the day of the inspection.
(Tr. 220). With a workforce of 149
employees, the Court is not convinced that Respondent’s verbal rule was
effectively communicated given that its fall protection program was little more
than an ad hoc compilation of
training modules that only tangentially addressed the hazards present at the
Elevate Wolff-Havana project. Cf. Aquatek
Systs., Inc., 2006 WL 741751 at *2 (No. 03-1351, 2006) (“Indeed, Aquatek’s
small size—a total of four employees, including owner Ken Morris and his
brother, foreman Morris—makes it an unlikely candidate for a formal written
safety program of the kind typically associated with larger companies.”).
Respondent presented evidence of a
disciplinary program and a safety committee, which is comprised of five
different members of management. (Tr. 262–63).
The committee is charged with developing safety programming and
training. (Id.). According to McMillan, Respondent’s general
superintendent, Bill Lund (who is also a member of the safety committee) is
responsible for overseeing all project foremen at the job sites Respondent is
working on. (Tr. 265). McMillan
testified that Lund monitored various worksites and served as “an extra set of
eyes”, but there was no evidence regarding how, when, or the frequency at which
such monitoring occurs. See Burford’s
Tree, Inc., 22 BNA OSHC 1948 (No. 07-1899, 2010) (determining monitoring
efforts were inadequate when audits of equipment were performed sporadically
and only involved brief walk-around inspections);
L.E. Meyers Co., 16 BNA OSHC 1037,
1042 (No. 90-945, 1993) (finding safety program inadequate, in part, because
company safety officials failed to monitor supervisor’s adherence to safety
rules during “the month or more” he was assigned to cited worksite). But see Stahl Roofing, Inc., 19 BNA OSHC
2179 (No. 00-1268 et al., 2003)
(finding adequate supervision where supervisors visit sites once per day,
safety manager visits 10 to 15 sites per week, and company president makes
unannounced visits to various worksites).
Indeed, in this case there was no testimony or evidence indicating Wilson’s
crew—or any Ovation crew for that matter—had ever been audited or monitored
during its time at Elevate Wolff-Havana prior to the inspection on October 20,
2016. Because Respondent (1) had no
written fall protection rule applicable to the conditions in this case; (2) had
a verbal, vague, non-specific 100% tie-off policy; and (3) failed to establish
that it took reasonable steps to discover violations or monitor compliance with
safety requirements, the Court finds Respondent’s safety program was inadequate.
See Stanley Roofing Co., Inc., 21 BNA
OSHC 1462 (No. 03-0997, 2006).
Finally, the Court also rejects Respondent’s
argument that the training Wilson received on the 1926.500(a)(1) exception was
unforeseeable and his subsequent trip over the guardrail was unpreventable. The
question of whether Respondent had knowledge is directed at the conditions
constituting a violation, not whether the law characterizes those conditions as
such. See Phoenix Roofing, 17 BNA
OSHC at 1079–80. That fact
notwithstanding, the Court finds it unsurprising Wilson acted upon the fall
protection exception information he received during the MPC toolbox talk. To
that point in time, Wilson’s conduct was not governed by any specific Respondent-generated,
written fall protection rules or programs; the training he (and Pezick)
received did not govern the specific hazards present at the worksite; and Respondent
had no discernible program for monitoring fall protection compliance at this
location. Under these circumstances, Wilson’s
violative actions were foreseeable and preventable.
Further, the Court notes that the
guardrails had been installed “incorrectly” for a long time. Clyde George
testified the orientation of the guardrails at the entry to the balcony was
determined in a pre-construction meeting with his framers. (Tr. 177–78). Prior
to his foray onto the balcony on the day of the inspection, Wilson testified he
and the other crew members entered into the closet through the spaces between
the interior studs. Subsequent
installation of plumbing and electrical wiring, however, impeded their ability
take that route. (Tr. 209). According to Wilson, he asked MPC to move the
guardrails “[a]bout three or four” times, but he received no response. (Tr.
244). Instead of requiring MPC to move
the guardrails to the perimeter of the balcony prior to performing additional
work—or refusing to work in the area until the guardrail condition was
corrected—Wilson’s crew continued to walk onto the balcony to get to the
closet, even though there was no protection from the unprotected edge of the
balcony only a couple of feet away. Wilson
and crew had been on site for 6 months, 5 days a week, during which time Wilson
testified he was the highest ranking official for Respondent on the worksite. (Tr.
190). During that time, Respondent
installed roughly 90 percent of the plumbing on all floors of Building 5,
including the closets, even though the fall protection on the balconies was
inadequate. (Tr. 192). Given that the guardrails
were situated at the entrance to the balcony for a substantial period of time, Respondent
could have insisted that the problem be corrected before its employees were
exposed to the hazard. The length of the
time the condition existed, the lack of explicit fall protection rules, and the
lack of an effective worksite monitoring program, cause this Court to conclude
that Wilson’s actions on the day of the inspection were foreseeable and
preventable. Respondent is charged with constructive knowledge of the
violation.
Respondent
Failed to Prove the Affirmative Defense of Unpreventable Employee Misconduct
In order to prevail on a claim of
unpreventable employee misconduct, Respondent must show: (1) it has established
work rules designed to prevent the violation; (2) it has adequately
communicated those rules to its employees; (3) it has taken steps to discover
violations of the rules; and (4) it must effectively enforce the rules when
violations are detected. Am. Eng’g &
Dev. Corp., 23 BNA OSHC 2093, 2096–97 (No. 10-0359, 2012). As noted above in footnote 11, the
analysis of foreseeability closely tracks the elements of a claim for unpreventable
employee misconduct. As such, the Court will
not revisit the foregoing elements in depth; rather, it shall herein
incorporate by reference the previous section’s findings of fact and
conclusions of law. The foregoing
analysis illustrates Respondent failed to establish its claim of unpreventable
employee misconduct with respect to Wilson or Pezick.
Respondent failed to implement
effective work rules designed to prevent the violation. Prior to the inspection
in this case, Respondent’s written fall protection program consisted of a
patchwork of training modules (undetailed in court); a half-page, written
section on fall protection as it relates to scaffolding; and a vaguely worded,
verbal 100% tie-off policy. The training
Respondent did provide apparently did not cover the hazards on the Elevate
Wolff-Havana site, and there is no evidence it was provided consistently to
account for new employees, such as Pezick, who started at Ovation within one
month of the inspection and missed the last Respondent-provided fall protection
training provided on June 6, 2016. (Tr. 255).
Finally, though Respondent had a disciplinary program, there was insufficient
evidence of the steps Respondent took to monitor compliance with safety
regulations and to detect violations.
Accordingly, the Court finds
Respondent failed to meet its burden to establish the defense of unpreventable
employee misconduct.
The Violation Was Serious
A
violation is “serious” if there was a substantial probability that death or
serious physical harm could have resulted from the violative condition. 29
U.S.C. § 666(k). Complainant need not
show that there was a substantial probability that an accident would actually
occur; he need only show that if an accident occurred, serious physical harm
could result. Phelps Dodge Corp. v. OSHRC, 725 F.2d 1237, 1240 (9th Cir.
1984). If the possible injury addressed
by a regulation is death or serious physical harm, a violation of the
regulation is serious. Mosser Construction, 23 BNA OSHC 1044
(No. 08-0631, 2010); Dec-Tam Corp.,
15 BNA OSHC 2072 (No. 88-0523, 1993).
CSHO Peterson credibly testified
that a fall from over 10 feet would cause injuries such as contusions and
broken bones. (Tr. 88). Respondent did
not dispute CSHO Peterson’s testimony.
Because the possible injuries caused by a fall from the balcony could
cause serious injuries, and possibly death, the Court finds Complainant has
proved the violation was serious.
Accordingly, the Court finds Complainant met its burden, and Citation 1,
Item 1 shall be AFFIRMED as issued.
Penalty
In
calculating appropriate penalties for affirmed violations, Section 17(j) of the
Act requires the Commission give due consideration to four criteria: (1) the size of the employer’s business, (2)
the gravity of the violation, (3) the good faith of the employer, and (4) the
employer’s prior history of violations.
Gravity is the primary consideration and is determined by the number of
employees exposed, the duration of the exposure, the precautions taken against
injury, and the likelihood of an actual injury. J.A. Jones Construction Co.,
15 BNA OSHC 2201 (No. 87-2059, 1993). It
is well established that the Commission and its judges conduct de novo penalty determinations and have
full discretion to assess penalties based on the facts of each case and the
applicable statutory criteria. Valdak Corp., 17 BNA OSHC 1135 (No.
93-0239, 1995); Allied Structural Steel,
2 BNA OSHC 1457 (No. 1681, 1975).
Complainant
assessed a penalty of $4,811.00. This
penalty is premised on CSHO Peterson’s determination the violation was of
medium- to high-gravity and the likelihood of an accident was low. While the Court generally agrees with
Complainant’s assessments, the Court finds the short duration of Wilson and
Pezick’s exposure, coupled with a low likelihood of injury, warrants a
reduction in penalty. Neither Wilson nor
Pezick worked on or near the edge of the balcony; instead, after they crossed
the guardrail, they cut across the back corner of the balcony and went straight
into the closet. By Wilson’s own
estimate, he and Pezick were on the balcony for no more than a minute, during
which time they occupied the closet.
Indeed, as Wilson testified, he was cognizant of the fall hazard and
made sure to keep close to the guardrail and the back corner of the balcony as
he walked into the closet. Considering
the totality of the circumstances, the Court finds a penalty of $1,000.00 is
appropriate.
Order
Based upon the foregoing Findings of Fact and
Conclusions of Law, it is ORDERED
that:
1. Citation 1, Item 1(a) is AFFIRMED,
and a penalty of $1000.00 is ASSESSED.
/s/ |
Date: April 17, 2018 Judge Brian A. Duncan
Denver, Colorado U.S. Occupational Safety and Health Review Commission
[1]. References to the parties’ stipulations shall be as follows: “(Stip. No. ___)”.
[2]. Safety First is a private safety consulting firm hired by MPC specifically for the Elevate Wolff-Havana project. (Tr. 143–44).
[3]. CSHO Peterson testified he had George call the individuals on the balcony so he could identify and speak to them. Wilson does not recall receiving a telephone call during his time on the balcony. (Tr. 73, 249).
[4]. The Court notes that Respondent’s safety program appeared only to supply fall protection instruction as it relates to scaffolding. (Tr. 213–14; Ex. C-12, C-14).
[5]. There appears to be a scrivener’s error in the narrative of the violation. The parties stipulated the inspection occurred on October 20, 2016, and the Citation indicates an inspection on “10/20/2016 – 10/20/2016”. Citation and Notification of Penalty at 6. But, the citation alleges the violation occurred on “November 20 and at times prior to”. Id. Throughout the trial, the parties consistently referenced the October 20, 2016 date, and the error in the citation narrative appears to have been overlooked. Further, Wilson testified the fall protection training illustrated in exhibit R-24, which occurred on October 28, 2016, took place after the inspection occurred. In essence, the parties amended the Citation by consent. See Fed. R. Civ. P 15(b)(2). Thus, the Court sua sponte amends the Citation to reflect the appropriate date of October 20, 2016.
[6]. As will be discussed in more detail below, this case was decided prior to the promulgation of the final rules for fall protection in construction. See 59 Fed. Reg. 40,672. Thus, the numbering and, to some extent, the content of the rules at issue will be different.
[7]. The exception was not discussed by either party or the ALJ prior to Commission review.
[8]. Some provisions in the prior version of subpart M were repealed, whereas some others were simply renamed and amended. See 59 Fed. Reg. 40,672.
[9]. In this regard, Wilson’s good faith belief that his actions were in compliance with the exception is not relevant to the question of whether Respondent had knowledge. However, to the extent that the morning’s presentation on the exception may have an impact on whether Wilson’s actions were foreseeable, the Court shall consider it as a factor.
[10]. Though there was some confusion regarding Wilson’s description of “lining it out”, the Court interprets this to mean to outlining the process of measuring and installing the regulator vents. (Tr. 82–83).
[11]. The assessment of foreseeability tracks the elements of unpreventable employee misconduct. See Horne Plumbing & Heating Co. v. OSHRC, 528 F.2d 564, 571 (5th Cir. 1976) (holding an employer may not be penalized “for the unforeseeable, implausible, and therefore unpreventable acts of his employees”).
[12]. After the inspection, Respondent updated its safety program to include extensive information on fall protection and conducted comprehensive fall protection training. (Ex. C-13, R-24).