SECRETARY OF LABOR,
Complainant,
v.
CONCRETE CONSTRUCTION CO., INC.,
Respondent.
OSHRC Docket No. 82-1210
DECISION
Before: BUCKLEY, Chairman; and CLEARY, Commissioner.
BY THE COMMISSION:
This case is before the Occupational Safety and Health Review Commission under 29 U.S.C.
§ 661(i), section 12(j) of the Occupational Safety and Health Act of 1970, 29 U.S.C. §§
651-678 ("the Act"). The Commission is an adjudicatory agency, independent of
the Department of Labor and the Occupational Safety and Health Administration. It was
established to resolve disputes arising, out of enforcement actions brought by the
Secretary of Labor under the Act and has no regulatory functions. See section 10(c) of the
Act, 29 U.S.C. § 659(c).
Item 1(a) of a citation issued by the Secretary alleged that part of a backhoe operated by
Concrete Construction Company came within ten feet of an energized power line, contrary to
29 C.F.R. § 1926.550(a)(15)(i). That standard requires that, unless electrical power
lines have been deenergized or insulated, a ten-foot clearance be maintained between the
lines and all parts of a crane. Item 1(b) specified that the worker designated by Concrete
to observe clearance of the backhoe was assigned additional tasks that prevented him from
ensuring that clearance was maintained, in alleged violation of section
1926.550(a)(15)(iv).
That standard requires that, where it is difficult for a crane operator to maintain
clearance visually, a person "be designated to observe clearance of the equipment and
give timely warning . . . . "[[1]] A hearing was held before Administrative Law Judge
Paul L. Brady, who affirmed both items.
As an initial matter, Concrete argues that section 1926.550(a)(15)--a crane standard--does
not apply to its backhoe, which it characterizes as excavation equipment. The employer
argues that backhoes are covered under a different subpart, Subpart O of Part 1926, which
deals expressly with excavation equipment. Concrete cites the Commission's recent decision
in Lisbon Contractors, Inc., 84 OSAHRC __, 11 BNA OSHC 1971, 1984-85 CCH OSHD ¶ 26,924
(No. 80-97, 1984), which held that a Caterpillar 235 backhoe identical to the one used
here is not a "crane" within the meaning of section 1926.550(a)(9), the crane
barricading standard.
Lisbon is not controlling, however, because that decision involved section 1926.550(a)(9).
Section 1926.550(a)(15), the section cited in this case, is different from section
1926.550(a)(9) and other sections of the crane standard in that it expressly was made
applicable to non-crane equipment, including backhoes, by a provision in Subpart O,
section 1926.600(a)(6). Section 1926.600(a)(6) provides that "[a]ll equipment covered
by this subpart [Subpart O] shall comply with the requirements of § 1926.550(a)(15) when
working or being moved in the vicinity of power lines or energized
transmitters."[[2]] It is clear that this Caterpillar 235 backhoe is covered by
Subpart O. Section 1926.602(b), a provision within Subpart O, is captioned
"Excavating and other equipment" and expressly mentions backhoe attachments at
section 1926.602(b)(1). Section 1926.602(b)(3) cross-references several other standards,
at least one of which-- Power Crane and Shovel Association Standard No. 3 of 1969, Mobile
Hydraulic Excavator Standards, section 2.0.1--specifically covers backhoes. Finally,
Concrete states that its backhoe is excavation equipment and asserts that it is covered by
Subpart O. We agree and find that section 1926.550(a)(15) applies.
Item 1(a): Section 1926.550(a)(15)(i)--Clearance
Section 1926.550(a)(15)(i) requires that, where electrical distribution or transmission
lines have not been deenergized or insulated, the "Minimum clearance between the
lines and any part of the crane or load shall be 10 feet." Three electric power lines
above Concrete's backhoe were neither deenergized nor insulated. The judge found that the
required clearance from energized lines was not maintained, for the backhoe contacted a
power line, a fact not in dispute. The only issue on review is whether the Secretary
proved that Concrete knew or with the exercise of reasonable diligence could have known of
and prevented the violation. See, e.g., Scheel Construction, Inc., 76 OSAHRC 138/B6, 4 BNA
OSHC 1824, 1976-77 CCH OSHD ¶ 21,263 (No. 8687, 1976). We find that he did.[[3]]
Concrete was putting in a waterline alongside a road in Groveport, Ohio. A Caterpillar 235
backhoe excavator was used to dig a trench and lay pipe sections. The trench was located
under three power lines, each carrying 7,620 volts. At one point the lines were about 28
feet above ground level. Given the standard's requirement of a ten foot clearance,
Concrete had 18 feet in which to maneuver the entire backhoe under that point. At another
point, the three lines hung 22 feet off the ground, leaving only 12 feet in which to
maneuver the backhoe. At the time of the alleged violation, approximately 1500-2000 feet
of pipe had been laid underneath the power lines. Each section of the steel- lined utility
pipe was 20 feet long, 50 inches in diameter, and weighed 11,800 pounds.
The trench was dug in sections 11 or 12 feet wide and was long enough for one piece of
pipe to be laid at a time. After digging a new section of trench, the backhoe operator
would move the backhoe twenty feet back from the opening, in a line parallel to the road.
The operator then rotated the backhoe's superstructure 90 degrees clockwise and extended
the backhoe arm about 30-35 feet across the road to where the pipe sections were stored.
Concrete had designated an employee to observe the clearance of the backhoe from the
overhead power lines and to assist in lowering the pipe section into the trench. The
observer would attach a sling around the pipe and hook the sling and pipe to the backhoe
bucket. The backhoe operator then dragged the pipe toward the machine until enough
leverage was gained to raise the pipe off the ground. The arm could be extended a maximum
of about 25 feet and still maintain leverage to raise the pipe. The operator then pivoted
the arm with its load back (not quite a full 90 degrees) toward the open trench, moved the
backhoe forward until the pipe was next to the trench, again pivoted the arm until the
pipe was above the trench, and lowered it into the trench.
While the pipe was suspended near the trench, the observer would grasp the end of the pipe
closest to the backhoe to steady it. When the pipe was about to be lowered into the
trench, the observer would be standing in front of the backhoe at the edge of the trench.
This observer or a worker in the trench would signal the backhoe operator to lower the
pipe. The backhoe operator testified that the observer's assistance was necessary to
ensure that safe clearance was maintained. In his words: "I told him to watch the
wires overhead. And, he'd have to signal me when I got next to the trench because I
couldn't watch him and watch the people below [workers in the trench] too." The
intrusion into the ten-foot zone occurred as the operator was about to lower a pipe
section into the trench in the usual manner. As the arm of the backhoe was swung toward
the center of the trench and the 28-foot-high power lines, its knuckle joint made contact
with one of the lines, electrocuting the observer.
Before trenching operations were begun, Concrete met with employees of the electric
utility. They reviewed the locations of utility poles and underground power lines and
discussed ways of ensuring that the trenching operation would not undermine the footings
of the poles. The height of the lines, the adequacy of the clearance from them, and the
possibility of deenergizing or temporarily insulating the lines were not discussed,
because Concrete's representative believed there would be sufficient room for the backhoe
to safely perform its work. The electric utility could have deenergized the lines at
Concrete's request and at Concrete's expense, as it later did. The record does not show
whether the lines could have been insulated.
After the meeting but before it began digging operations, the company also conducted a
"dry, run" with the Caterpillar 235. On the basis of "eyeball"
estimates during this "dry run," Concrete's job superintendent, Lusignolo,
concluded that the wires ranged from 25 to 35 feet in height and that there would be about
13 feet of clearance. The record does not reflect whether the dry run was con ducted under
a midpoint, where the lines would hang lowest, or whether a pipe and sling arrangement
similar to that being used at the time of the alleged violation were employed. No
measurements were taken during the dry run.
At the hearing, the height reached by the backhoe arm, particularly its knuckle joint,
became a focus of attention. The operator of the backhoe testified that the knuckle joint
was about 18 feet high during the pipe-lowering portion of the operation. Concrete's job
superintendent, Lusignolo, estimated that the knuckle joint reached a height of 14 to 15
feet. Concrete also introduced a photograph showing the height of the knuckle joint as 16
feet and the height of two hydraulic lines attached to the backhoe arm's knuckle joint as
nearly 18 feet during a purported simulation of the operation.[[4]]
The judge found that the trenching operation was conducted in a manner that Concrete
reasonably should have known would encroach on the 10-foot zone around the power lines, as
it did. This finding is fully supported by the facts. The sling that Concrete used
extended about eight feet from the top of the pipe to the hook on the backhoe. The pipe
was over four feet in diameter and was carried one foot off the ground. The height of the
rigging and load together was therefore at least thirteen feet. This meant that in order
to maintain a 10-foot clearance under a 28-foot-high power line, the operator had only
five feet in which to maneuver the arm of the backhoe. Under a 22-foot-high line, there
would have been no room at all in which to maneuver without encroaching into the 10-foot
zone.[[5]]
That there was no margin for error is apparent from an examination of the specifics of the
pipe-lowering operation. Both the backhoe operator and Concrete's superintendent testified
that, after the backhoe arm picked up a pipe section but before the backhoe and the pipe
moved forward to the open trench, the backhoe arm was extended 25 feet horizontally. Once
the pipe was next to the trench, the backhoe arm was pivoted horizontally several feet to
the left until the fifty- inch-wide pipe section cleared the edge of the twelve-foot-wide
trench.[[6]] The pipe section was then lowered vertically into the trench. The closest
energized power line was nearly directly above the trench's centerline.
The operator thought and Concrete argues that the knuckle joint was then 18 feet high.
This meant, under the employer's own view, that only inches of clearance from the ten-foot
zone were left when the backhoe was operated under lines slightly higher than 28 feet, and
that no clearance whatsoever was left when it was operated under 28-foot-high lines. Under
25-foot- high lines, which was the lower end of the range of heights estimated by
Concrete's supervisor during the dry run, the backhoe arm assembly would encroach three
feet into the ten foot zone. Under the 22-foot height measured in the area in which
Concrete was working the backhoe arm would encroach six feet.
We find that, had Concrete exercised reasonable diligence, it could have known of and
prevented the violation. Concrete was conducting a series of operations under three
energized power lines that it knew varied in height and were close enough to pose a grave
danger. It elected not to have the lines deenergized by the local power company and chose
instead to maintain a ten-foot clearance from the lines. Yet, with a minimum of foresight
and effort, Concrete could have discovered that its rigging arrangement and pipe-laying
procedure left no room in which to maneuver the backhoe arm even assuming the accuracy of
its own estimate of the height of the lines, the height. reached by the backhoe arm and
its ability to maneuver the machine precisely within very narrow limits. In fact,
Concrete's backhoe could not be operated with such precision, as evidenced by the fact
that its knuckle joint contacted a line that was nearly 28 feet high, at least ten feet
higher than any of Concrete's witnesses thought the knuckle joint would be. The
circumstances of this case demonstrate that Concrete failed to exercise reasonable
diligence in maintaining a ten-foot safety margin. We therefore affirm item 1(a).
Item 1(b): Section 1926.550(a)(15)(iv)--Observer
Section 1926.550(a)(15)(iv) requires that "[a] person shall be designated to observe
clearance of the equipment and give timely warning for all operations where it is
difficult for the operator to maintain the desired clearance by visual, means[.]"
Chairman Buckley and Commissioner Cleary are divided over whether, the observer
requirement was violated.
Commissioner Cleary agrees with the judge's finding that the employer failed
to comply with the standard. In Commissioner Cleary's view, the standard requires more
than the mere provision of an observer. It requires that the observer not be assigned
additional duties that prevent him from assuring that no part of the equipment or its load
comes within ten feet of energized power lines. Here, Concrete's job superintendent
assigned its observer the additional task of assisting the backhoe operator in lowering
the pipe into the trench by having him steady the load and guide it into the trench. The
so-called observer appears to have been, in actuality, a helper or rigger. The backhoe
operator testified without contradiction that when a pipe section was about to be lowered
into the trench--the moment when the backhoe boom was closest to the power line --it was
"crucial" that the attention of the observer be directed at the pipe. In
Commissioner Cleary's view, this unrebutted testimony establishes that the employer did
not designate a person to "observe clearance" and "give timely
warning" to the backhoe operator within the meaning of the standard.[[7]] In any
event, as the Commission's discussion of the clearance violation demonstrates, Concrete
had set up its pipe-laying procedure in such a way that repeated violations of the
ten-foot safety zone were inevitable. Its "observer" could therefore have
reasonably been expected to give warning only of impending contact with a power line,
rather than intrusion into the safety zone. So hollow a "designation" of an
observer violates the standard. Commissioner Cleary would therefore affirm item 1(b).
In Chairman Buckley's view, the judge erred in affirming this citation item. Contrary to
the Secretary's argument to the judge, the standard does not require that an observer have
no other, duties to perform and that he devote all his attention to observing clearance.
The standard requires only that an employee be designated to observe clearance and give
timely warning. The record does not show that this was not done. Although the Secretary
claimed that an observer was assigned duties that prevented him from adequately ensuring
that clearance was maintained, the record shows at most that he had some other duties to
perform. During the pipe-laying operation, the observer would, in the operator's words,
"glance" at the workers in the trench. The record does not show that the
observer's other duties prevented him from effectively carrying out his task of observing
clearance. At most it shows that he was required to perform separate tasks during the
operation. That these tasks did not interfere with each other is demonstrated by the job
superintendent's unrebutted testimony that he occasionally substituted for the observer
and was able both to maintain the required clearance and steady the pipe. Furthermore, the
observer was positioned where he could clearly and closely observe the proximity of the
overhead power lines to the slowly-moving arm of the backhoe. At the point where the pipe
would be lowered into the ground and the observer's gaze would shift to the pipe fitters
in the trench, the arm of the backhoe had already reached the point at which it was
closest to the power lines. There is no evidence to support a finding that the observer
could not timely warn the operator that the backhoe arm was within ten feet of the
overhead wires. At most it can be inferred from the fact of the accident that, warning was
given or that a warning was given but ignored. Yet, neither inference could support a
finding that the observer's duties, if properly discharged, precluded a timely warning.
Accordingly, Chairman Buckley would conclude that the judge erred in finding a violation
of section 1926.550(a)(15)(iv).
To resolve this impasse and to permit this case to proceed to a final
resolution, the members have agreed to affirm this portion of the judge's disposition but
accord it the precedential value of an unreviewed judge's decision.[[8]] See Life Science
Products Co., 77 OSAHRC 200/A2, 6 BNA OSHC 1053, 1977-78 CCH OSHD ¶ 22,313 (No. 14910,
1977), aff'd sub nom. Moore v. OSHRC, 591 F.2d 991 (4th Cir. 1979). The judge assessed a
total penalty of $500 for both the clearance and observer violations. Chairman Buckley
would assess a penalty of $500 for the clearance violation alone and would assess no
penalty with respect to the observer item, which he ordinarily would vacate. Commissioner
Cleary agrees with the judge's combined assessment. Accordingly, the two Commissioners
affirm the judge's decision with respect to citation item 1(b) but accord this affirmance
the precedential value of an unreviewed judge's decision. The judge's decision with
respect to citation item 1(a) is affirmed without qualification. A total penalty of $500
is assessed.
FOR THE COMMISSION
Ray H. Darling, Jr.
Executive Secretary
DATED: JAN 25 1985
FOOTNOTES:
[[1]]The standards provide:
Subpart N--Cranes, Derricks, Hoists,
Elevators, and Conveyors
§1926.550 Cranes and derricks.
(a) General requirements.
* * *
(15) Except where electrical distribution and transmission lines have been deenergized and
visibly grounded at point of work or where insulating barriers, not a part of or an
attachment to the equipment or machinery, have been erected to prevent physical contact
with the lines, equipment or machines shall be operated proximate to power lines only in
accordance with the following:
(i) For lines rated 50 kV. or below, minimum clearance between the lines and any part of
the crane or load shall be 10 feet;
* * *
(iv) A person shall be designated to observe clearance of the equipment and give timely
warning for all operations where it is difficult for the operator to maintain the desired
clearance by visual means[.]
[[2]]In Kent Nowlin Construction Co., 80 OSAHRC 39/A10, 8 BNA OSHC 1286, 1980 CCH OSHD ¶ 24,458 (Nos. 76-191 & 76-192, 1980), and Tri-City Construction Co., 80 OSAHRC 62/C5, 8 BNA OSHC 1567, 1980 CCH OSHD ¶ 24,557 (No. 77-3668, 1980), the Commission applied the crane clearance standard through section 1926.600(a)(6) to backhoes that had been operated within ten feet of overhead power lines.
[[3]]Before we discuss the circumstances of this case, one point bears emphasis. The gravamen of this citation item is that Concrete failed to maintain ten feet of clearance between its backhoe and an overhead power line, not that the backhoe contacted the power line. Our inquiry here is therefore confined to whether Concrete exercised reasonable diligence in attempting to maintain this clearance, rather than in avoiding contact with the wire. The contact with the wire is merely evidence that the clearance was not maintained and that part of the backhoe in fact reached a height of 28 feet. See Concrete Construction Co., 76 OSAHRC, 47/A2, 4 BNA OSHC 1133, 1135 n.3, 1975-76 CCH OSHD ¶ 20,610, p. 24,664 n.3 (No. 2490, 1976).
[[4]]The photograph did not necessarily represent the conditions that existed at the time of the alleged violation. The photograph depicted the backhoe carrying a considerably shorter, and presumably lighter, piece of pipe than was actually installed, which may have permitted the am of the backhoe to be more extended and the knuckle joint lower than was the case during actual operations. In addition, a shorter sling than that actually used is shown, while the pipe in the photograph appears to have been suspended at ground level or in a shallow trench slightly below ground level. During the actual pipe-laying, the pipes were carried a foot off the ground. The Secretary objected to the introduction of this photograph on the ground that it did not fairly represent the actual pipelowering operation. The record demonstrates, however, that, even if the photograph's depiction of the backhoe arm's height as 18 feet is accepted, Concrete should have known that its backhoe would encroach upon the 10-foot zone.
[[5]]The violation in this case did not occur precisely at a midpoint. One of
the exhibits introduced into evidence shows that the backhoe contacted the power line some
28 feet west of its midpoint. Inasmuch as a section of pipe is lowered every 20 feet, and
the backhoe was working from west to east, the backhoe would have been maneuvered under
even lower-hanging power lines during the next pipelaying operation.
[[6]]On this point, we agree with Judge Brady's understanding of the testimony. The
employer claims that this understanding was erroneous. It argues that the operator again
"boomed out" the backhoe arm before or while lowering the pipe section. We find
that this version of events is not supported by the evidence. The job superintendent
testified that the backhoe arm would swing sideways from the side of the trench before
beginning to lower the pipe section. The operator testified that he "boomed out"
to nearly the maximum reach of the backhoe arm before he started to move the machine
forward, and that he lowered the arm after the observer signaled him to do so.
[[7]]Commissioner Cleary does not agree with the employer's contention that this citation item is duplicative of the allegation that it violated the clearance requirement.
[[8]]Under section 12(f) of the Act, 29 U.S.C. § 661(e), official action can
be taken by the Commission with the affirmative vote of two members. Presently, the
Commission has two members as a result of a vacancy.