UNITED STATES OF AMERICA

OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION

 

 

SECRETARY OF LABOR,

 

                                             Complainant,

 

                         v.

OSHRC DOCKET NO. 13964

CONNECTICUT NATURAL GAS CORP.,

 

                                              Respondent.

 

 

June 30, 1978

DECISION

Before CLEARY, Chairman; and BARNAKO, Commissioner[1]


BY THE COMMISSION:

            A decision of Review Commission Judge Foster Furcolo is before the Commission for review pursuant to section 12(j) of the Occupational Safety and Health Act of 1970, 29 U.S.C. § 651 et seq. [‘the Act’]. In his decision, the Judge affirmed a citation alleging a serious violation of section 5(a)(2) of the Act for failure to comply with the construction safety standard published at 29 C.F.R. § 1926.652(b)[2] and assessed a $1000 penalty.[3] We affirm the Judge’s decision to the extent that it is consistent with the following, and reduce the penalty to $600.

            Respondent is engaged in the sale and distribution of natural gas. It had excavated a trench for the purpose of repairing a leak in a gas pipe. The trench was in the shape of two overlapping rectangles as depicted below.[4]

            While conducting an inspection of the worksite at a street intersection in Hartford, Connecticut, two compliance officers observed one of respondent’s employees in the east trench between sections E and F. The employee was straddling a six inch diameter pipe that he was repairing. The depth of section F of the east trench was 6 feet 8 inches and the width at the bottom of the trench between sections E and F was 2 feet 8 inches. The wall of section F of the trench was vertically cut below a concrete overhang that extended over the trench a distance of 2 feet 7 inches. The wall had line cracks in it. From the top of the wall of section F the concrete overhang measured 1 foot 2 inches vertically. Beneath the overhang was 1 to 1 ½ feet of compact processed stone, followed by an 18-20 inch deep by 4 foot long electric conduit, with compact natural clay silt filled with sand at the bottom. At the intersection of sections E and G of the trench, there was a conically shaped manhole 8 feet in diameter at the bottom, tapering to 4 feet in diameter at the top.

            Respondent’s expert witness, Dr. Clarence Welti,[5] and area foreman, Mr. Vail, testified that the soil in section F of the trench was stable clay silt. Dr. Welti took and tested soil samples. The only soil sample that he tested from the east trench was from the middle of section F; the soil sample tested as stiff, cohesive clay silt.[6]. Dr. Welti testified that there was sand at the bottom of the trench and that a large portion of the excavation was sand. Dr. Welti stated that the west wall (section E) of the trench was backfill and that backfill soil was generally unstable. Both Dr. Welti and Vail agreed that the trench walls in that area (sections E and F) were supported by the manhole and electric conduit so that no shoring was needed.

            Both compliance officers and the Area Director testified that the soil throughout the trench was unstable. The Area Director stated that he had seen this worksite dug up three to five times previously, the site being outside his office. He concluded that the soil was backfill sand, which was unstable due to the disturbed nature of the soil. Compliance officer Hatcher stated that he determined from his observations that the soil throughout the trench and walls was sandy, backfill soil. Hatcher stated that he had seen the site opened by respondent on two previous occasions. Compliance officer Normand bent over the edge of the trench to observe the soil; he described the soil as sandy. He stated that the west wall (section E) was composed of sand with loose material midway down the trench wall.

            The Area Director and compliance officer Hatcher claimed that the concrete overhang posed an additional hazard because of the possibility of it collapsing on the employee who was working in this area during the inspection. The maintained that the possibility of collapse was increased due to the vibrations caused by traffic coming within three feet of the trench. The Area Director also stated that vibrations from vehicular traffic increased pressure on the walls. Superintendent Colturi testified that the overhang was not dangerous because it was newly poured reinforced concrete. Dr. Welti claimed that the overhang could extend up to four feet without external support and it would be unlikely that the traffic vibrations would cause the overhang to break off.

            Vail, the area foreman, signed a Trench Excavation Field Form, stating that the trench was 32 inches wide and 6 feet 8 inches deep where the employee was observed working. The form also included a statement that the soil was unstable, sandy, and unshored. Vail testified that it was indicated to him that he was required to sign the form. Compliance officer Hatcher admitted that he did not inform Vail that he was not required to sign the form. The Area Director testified that this form had no official sanction.

            Respondent’s safety policy concerning trenches required that all trenches more than 5 feet deep be shored. After respondent received a second citation on a different worksite for failure to shore a trench, respondent hired Dr. Welti to make a general survey of its excavations to evaluate and correct possible dangers.

            In his decision, Judge Furcolo held that respondent had committed a serious violation of § 1926.652(b). He found that respondent’s supervisors had knowledge of the standard and the hazardous conditions. He found that the trench was 6 feet 8 inches deep and 2 feet 8 inches wide. Although he recognized there was conflicting testimony concerning the stability of the soil, he found that the soil was unstable, relying on several factors to reach this conclusion. The Judge was impressed by the ‘emphatic’ testimony of the compliance officers that the soil was unstable, as well as the uncontradicted testimony that the soil at the worksite had been excavated on several occasions. He noted that all witnesses agreed that backfill was less stable than undisturbed soil. The Judge also noted that the foreman had read and signed a statement that the soil was unstable. The Judge contrasted the testimony of respondent’s expert witness that the trench was stable with the expert’s other statements that some areas of the trench needed shoring, a large part of the excavation was sand, and one wall of the trench contained backfill. He also relied on the corroborated testimony that there was substantial amount of traffic near the site and the traffic came within a few feet of the trench. Although he did not specifically address respondent’s argument that the walls adjacent to where the employee was working were supported by a concrete manhole and conduit, he found that the sides ‘were not shored, sheeted, braced, or otherwise supported.’ The Judge did not give any reasons for his denial of respondent’s motion to dismiss on the grounds that the standard is vague.

            Respondent contends that the standard does not adequately inform it of the conditions under which protection is required because of the uncertainty in the term ‘unstable or soft material,’ because there is no guidance in the standard how the depth of five feet or more is to be measured when the composition of the trench walls is not uniform, and because the phrase ‘means of sufficient strength to protect employees’ is unduly vague. Because of these alleged deficiencies in the standard, respondent urges us to limit the applicability of the standard to situations in which a reasonably prudent person familiar with its industry would have protected against the hazard, citing Cape & Vineyard Division v. OSHRC, 512 F.2d 1148 (1st Cir. 1975).[7]

            We reject the argument. When the various terms of § 1925.652(b) are read in light of the other provisions of the trenching standards, their meaning is sufficiently precise to put employers on notice of what the standard requires.[8] First, we note that the phrase ‘unstable or soft material’ as used in § 1926.652(b) is contrasted with ‘hard or compact soil’ used in § 1926.652(c).[9] Read together, the standards inform employers that some protection is required in any trench 5 feet or more in depth dug in soil.

            The standards provide further guidance to enable employers to determine whether a particular trench is regulated by § 1926.652(b) or § 1926.652(c). In addition to the definitions of ‘unstable soil’ and ‘hard compact soil’ in § 1926.653, § 1926.652 contains Table P-1, which illustrates the approximate angle of repose for different types of earth material. This Table lists an angle of repose of ½ to 1 for compacted angular gravels, and less steep slopes for average soils, compacted sharp sand, and well rounded loose sand. Since § 1926.652(c) requires a slope of not steeper than ½ to 1 for hard or compact soil, it is evident that those materials listed in Table P-1 as having a less steep angle of repose must be considered soft or unstable, and are therefore regulated by § 1926.652(b).

            Similarly, Table P-2 in § 1926.652, entitled ‘Trench shoring-minimum requirements’, gives specific guidelines for the shoring requirements in trenches of different dimensions and soil types. An employer uncertain of the phrase ‘means of sufficient strength’ can look to Table P-2 for guidance. See Griffin & Brand of McAllen, Inc., 76 OSAHRC 148/A10, 4 BNA OSHC 1900, 1976-77 CCH OSHD para. 21,388 (No. 4415, 1976). 

            Finally, respondent’s objection to the phrase ‘5 feet or more in depth’ is not that it is incomprehensible, but that it does not provide guidance when the material in which a trench is dug is not uniform. Respondent would therefore have us interpret § 1926.652(b) as applying only when five feet or more of the depth of the trench is in unstable or soft material. We have previously rejected this argument, holding that as long as the trench is more than five feet in depth and the amount of unstable soil is not negligible, all _____ soil in the trench must be shored or sloped. W. N. Couch Construction Co., 76 OSAHRC 44/A2, 4 BNA OSHC 1054, 1975-76 CCH OSHD para. 20,574 (No. 7370, 1976). Based on Couch, we reject respondent’s suggested interpretation.

            Respondent contends that the Judge erred in concluding that the soil was unstable. Respondent takes specific exception to the factors on which the Judge relied: the compliance officers’ testimony that the soil was unstable; the testimony of the expert, Dr. Welti, that certain areas of the trench needed shoring and a large part of the trench was sand;[10] the testimony that the soil was backfilled; the signing of a form by its foreman stating the soil was unstable; and the traffic near the trench increasing the possibility of collapse.

            Respondent argues that its expert’s testimony that the soil in section F was stable and his analysis of soil samples where work was being performed should be given greater weight than the testimony of the compliance officers. While expert testimony is commonly given greater weight than lay testimony, expert testimony need not be accepted even if uncontradicted. U. S. Steel v. OSHRC, 537 F.2d 780, 783 (3rd Cir. 1976). Indeed, expert testimony is not conclusive; it is up to the trier of fact to determine what, if any, weight will be given to that testimony. Sartor v. Arkansas Natural Gas Corp., 321 U.S. 620, 627 (1944); see Daniel Construction Co., 77 OSAHRC 21/A2, 5 BNA OSHC 1005, 1976-77 CCH OSHD para. 21,521 (Nos. 7734 & 7672, 1977).

            The Judge realized that there was contradictory evidence with respect to the stability of the soil in various areas of the trench and chose to accord more weight to the testimony of complainant’s witnesses. Each of complainant’s witnesses testified from his previous knowledge of the worksite and his visual and tactile observations that the soil throughout the trench was unstable, specifically contradicting Dr. Welti’s testimony that the soil was stable in some parts of the trench.

            More importantly, complainant’s witnesses testified that the soil in the trench was backfilled. Dr. Welti admitted that backfill was generally unstable. Moreover, Dr. Welti testified that a large part of the trench was sand, specifically stating that the western wall (section E) near the bottom of the manhole was sandy. Furthermore, respondent’s exhibits, drawn by Dr. Welti, show sand in that wall and the two walls adjacent to it (sections D and G). Dr. Welti also admitted that certain areas of trench needed shoring. Finally, he stated that the western wall (section E) of the trench was backfill, and as noted, he admitted that backfill was unstable soil.[11]

 

We agree with the Judge’s assessment of the evidence and the weight that he assigned to the expert’s testimony. Although the Judge did not fully discuss his reasons for rejecting Dr. Welti’s conclusions about the stability of the soil in section F, his rejection was not arbitrary He recognized that there was contradictory evidence and stated the reasons for his determination. His findings are set forth in his decision and are supported by the evidence. See C. Kaufman, Inc., 78 OSAHRC 3/C1, 6 BNA OSHC 1295, 1977-78 CCH OSHD para. 22,481 (No. 14249, 1978); Administrative Procedure Act § 8(b), 5 U.S.C. § 557(c) (1966). In addition, it is uncontroverted that section E of the trench was comprised of backfill and that backfill is unstable.[12] We agree with the Judge’s determination that the soil was unstable.[13]

            Respondent also contends that the Judge failed to find that the trench walls were not ‘otherwise supported by means of sufficient strength to protect the employees working within them.’ The Judge made a specific finding that the trench walls were not otherwise supported; he did not, however, specifically address respondent’s arguments that the manhole and electric conduit supported the walls. While normally a remand would be necessary for the Judge to elucidate the reasons for his determination, P & Z Co., Inc., 77 OSAHRC 211/F5, 6 BNA OSHC 1189, 1977-78 CCH OSHD para. 22,413 (No. 76-431, 1977), there is sufficient evidence in the record for us to address the issue. Accordingly, we will decide whether the manhole and electric conduit were of sufficient strength to protect employees. Accu-Namics, Inc. v. OSHRC, 515 F.2d 828, 834 (5th Cir. 1975).

            The electric conduit in section F was four feet long, but there is no evidence indicating where it was located along the 6 foot long wall. There is also insufficient evidence showing how a 1 foot 6 inches high conduit can support a wall that is 6 feet 8 inches high. On the western wall, the manhole only protected the end of the wall (intersection of sections E and G). It was not large enough to support the entire wall. A major portion of the backfilled wall had no support (intersection of sections E and D). We hold the evidence does not establish that the walls were supported by other means of sufficient strength. See Wes Construction Corp., 76 OSAHRC 103/A2, 4 BNA OSHC 1536, 1976-77 CCH OSHD para. 20,996 (No. 4106, 1976). Accordingly, we find that a violation of § 1926.652(b) was proven as to section E of the trench.[14]

            Respondent argues that, if a violation exists, it is not serious. First, respondent submits that there is no proof that the violation would result in a substantial probability of death or serious physical injury. We reject this contention because, as complainant’s witnesses testified, it is probable that if the trench were to collapse, an employee could be buried or suffocate. Second, respondent contends that it lacked even constructive knowledge of the violation because Potvin, the working foreman, made the decision to excavate deeper than 5 feet without consulting any of his supervisors. We have held, however, that an employer is responsible for any violation that its supervisor creates or of which it has actual or constructive knowledge, unless the employer can show that the supervisor himself was adequately supervised regarding safety matters. Constructora Maza, Inc., 78 OSAHRC 6/E2, 6 BNA OSHC 1309, 1977-78 CCH OSHD para. 22,487 (Nos. 13680 & 14509, 1978). Respondent had adduced no evidence on this point.

            We believe, however, that the Judge’s assessment of a $1000 penalty is too high. Respondent was aware of its safety problems with trenches. In order to provide additional safety precautions, it retained Dr. Welti to advise of possible dangers associated with excavations and to recommend methods of eliminating the dangers. As a result of this evidence of good faith, we reduce the penalty to $600.

            It is ORDERED that the Judge’s decision be affirmed and a $600 penalty be assessed.

 

FOR THE COMMISSION:

 

Ray H. Darling, Jr.

Executive Secretary

DATED: JUN 30, 1978

 

            Commissioner COTTINE took no part in the consideration or decision of this case for the reasons set forth in his separate opinion.


SEPARATE OPINION

            As a new member of the Commission, I must resolve the issue of my participation in pending cases. It is also necessary for me to set out the principles guiding my decision on this important issue.

            In this case, Chairman Cleary and Commissioner Barnako reached a unanimous decision on the merits before I received my commission on May 1, 1978. A decision was already in preparation when I assumed office. I have concluded that the wisest exercise of discretion is to decline to participate in this case even though a new Commission member has authority to participate in pending cases. It should be emphasized that by declining to participate I express no opinion on the procedural or substantive issues in this case or on the appropriateness of the accompanying order.

Discretion of Commission Members

            As a matter of law, it is not necessary for all Commission members to participate for an agency to take official action. In Drath v. FTC, 239 F.2d 452 (D.C. Cir. 1956), cert. denied 353 U.S. 917 (1957), the Federal Trade Commission issued a cease-and-desist order with only three of its five members participating. The Court of Appeals rejected petitioner’s contention that the FTC can act in its adjudicatory capacity only when all members participate, except when there is a vacancy. The court ruled that official action can be taken by the majority of the requisite quorum. Also Frisher & Co. v. Bakelite Corp., 39 F.2d 247 (C.C.P.A. 1930) cited approvingly in FTC v. Flotill Prod. Inc., 389 U.S. 179, 182-183 (1967). Similarly, section 12(f) of the Occupational Safety and Health Act, 29 U.S.C. § 661(e), provides:

For the purposes of carrying out its functions under this chapter, two members of the Commission shall constitute a quorum and official action can be taken only on the affirmative vote of at least two members.

 

            Thus, the unanimous decision already reached in this case satisfies the quorum and official action requirements of the Act and my participation is not necessary for the Commission to carry out its adjudicatory functions in this particular case.

            However, it is also settled that a new member of an administrative agency may participate in pending cases. For example, a new member of the Civil Aeronautics Board who had not participated in previous proceedings was entitled to vote and break an existing tie where he had familiarized himself with the record. Western Airlines v. CAB, 351 F.2d 778 (D.C. Cir. 1965), citing United Air Lines v. CAB, 281 F.2d 53 (D.C. Cir. 1960)[15]. In United the court indicated that, where a member voting with the majority without hearing oral argument ‘had the record before him and the benefit of briefs’, there was no abuse of discretion in his participation, 281 F.2d at 56. There are numerous other cases supporting this holding. The clearest statement of law is set forth in Gearhart & Otis, Inc. v. SEC, 348 F.2d 798 (D.C. Cir. 1965):

The decisions of numerous courts and administrative agencies establish that, even without agreement of the parties, a member of an administrative agency who did not hear oral argument may nevertheless participate in the decision where he has the benefit of the record before him. [footnotes omitted]

 

348 F.2d at 802.[16] See Au Yi Lau v. U.S. Immigration and Naturalization Service, 555 F.2d 1036, 1042 (D.C. Cir. 1977); Arthur Lipper Corp. v. SEC, 547 F.2d 171, 182 & n.8 (2d Cir. 1976). Thus, a new member possesses the necessary authority to participate in all cases pending before the Commission on assuming office.

            Though a new member may participate in all pending cases, particularly those involving an impasse, the decision remains a matter of discretion since adjudicatory decision may be upheld on a majority of a quorum. In FTC v. Flotill prod., 389 U.S. 179 (1967) rev’g 358 F.2d 224 (9th Cir. 1966), an FTC member appointed to fill one of two vacancies, declined to participate because he had not heard the oral argument. Thus, three of the possible four Commissioners actually participated in the decision. As a result, the FTC issued a cease-and-desist order based on the affirmative vote of only two members. Despite its obvious impact on the number of members constituting a majority, the Court did not review the exercise of discretion by the new member. Instead, the Court accepted the abstention at face value and upheld the action of the two members of the FTC. See also La Preyre v. FTC, 366 F.2d 117 (5th Cir. 1966); Atlantic Refining Co. v. FTC, 344 F.2d 599 (6th Cir. 1965). In addition, administrative decisions involving two or more abstentions have been upheld by reviewing courts without question or comment on the grounds for these abstentions. All that was necessary to sustain the agency decision was a majority of the required quorum. E.G., Greater Boston Television Corp. v. FCC, 444 F.2d 841, 848, 861 (D.C. Cir. 1970), cert. denied 403 U.S. 923 (1971).

Decision Not to Participate

            I decline to participate in this case because a majority of the Commission has reached agreement on the merits and my vote would have no effect on the outcome. Moreover, in cases where Chairman Cleary and Commissioner Barnako have reached a unanimous decision, my participation would delay the issuance of decisions and conflict with the goal of a prompt and efficient decision-making process. See generally Atlas Roofing Co. Inc. v. OSHRC, 430 U.S. 442, 97 S.Ct. 1261, 1272 (1977); Keystone Roofing Co., Inc. v. OSHRC, 539 F.2d 960, 964 (3d Cir. 1976); Nader v. FCC, 520 F.2d 182, 205-207 (D.C. Cir. 1975), citing 5 U.S.C. § 555(b). Since abatement is stayed until the Commission enters a final order, 29 U.S.C. § 659(b), additional deliberations would delay the control of hazardous working conditions in any case where the Commission has determined that a violation of the Act exists. That result would be inconsistent with the statutory purpose to assure so far as possible safe and healthful working conditions for every working man and woman. 29 U.S.C. § 651(b).

            I will, however, participate fully in all cases in which previous Commission deliberations have resulted in a one-to-one deadlock. Decisions by an equally divided Commission are without precedential value, e.g., Life Sciences Products Co., 77 OSAHRC 200/A2 (microfiche), 6 BNA OSHC 1053, 1977-78 CCH OSHD ¶22,313 (No. 14910, Nov. 11, 1977), appeal filed, No. 77-1014 (4th Cir. Jan. 6, 1978), and, therefore, do not serve as guidance to the Commission’s administrative law judges. Moreover, these decisions also promote needless litigation in the U.S. Courts of Appeals to decide issues which should initially be determined by the Commission, because its members have specialized training, education, and experience in occupational safety and health. 29 U.S.C. § 661(a). See generally Atlas Roofing Co. v. OSHRC, supra at 1264, 1272; Keystone Roofing Co. Inc. v. OSHRC, supra at 963-964. Administrative resolution of pending issues also promotes a more uniform application and development of occupational safety and health law. After reading the record, I will participate in the consideration and decision of these cases.

Conclusion

            My decision not to participate in pending cases which have reached a unanimous decision by my colleagues, but to participate in those cases with unresolved issues, promotes the prompt adjudication of cases. It also assures the parties and the public of the full benefit of Commission review. Both of these results are essential in deciding cases affecting the lives, health and safety of American workers, the operation of American business, and the effective adjudication of cases by the administrative law judges.

 


 

UNITED STATES OF AMERICA

OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION

 

 

SECRETARY OF LABOR,

 

                                             Complainant,

 

                         v.

OSHRC DOCKET NO. 13964

CONNECTICUT NATURAL GAS CORP.,

 

                                              Respondent.

 

 

June 14, 1976

APPEARANCES

Robert J. Murphy, Esq.

For Complainant

 

Harold N. Mack, Esq.

For Respondent

 

DECISION AND ORDER

Furcolo, Judge:

            This is a proceeding pursuant to the Occupational Safety and Health Act of 1970, as amended (29 U.S.C. § 651, et seq.), hereinafter called the Act. The Complainant alleges that the Respondent has violated § 5(a)(2) of the Act (§ 654) by not complying with occupational safety and health standard 29 C.F.R. 1926.652(b).

            The Respondent is a corporation engaged in the business of the sale and distribution of natural gas, and its business affects the commerce of the United States.

            The Respondent’s worksite at the corner of Charter Oak Avenue and Prospect Street, Hartford, Connecticut, was inspected by the Occupational Safety and Health Administration (hereinafter called OSHA) on June 20, 1975.

            On June 24, 1975, the following citation, together with notice of proposed penalty, was issued against the Respondent:

            Citation #1, Item #1: The willful violation of standard 29 C.F.R. 1926.652(b).....$6,000.

            On July 2, 1975, the Respondent filed notice of contest to the citation and the penalty proposed therefor.

            The pertinent words of the standard involved are:

1926.652(b): ‘Sides of trenches in unstable or soft material, 5 feet or more in depth, shall be shored, sheeted, braced, sloped, or otherwise supported . . ..’

 

Section 17 of the Act (§ 666) has the following pertinent words:

(a) Any employer who willfully or repeatedly violates . . . section 5 of this Act . . . may be assessed a civil penalty of not more than $10,000 . . ..

 

(b) Any employer who has received a citation for a serious violation . . . of section 5 of this Act . . . shall be assessed a civil penalty of up to $1,000 . . ..

 

(k) . . . a serious violation shall be deemed to exist . . . if there is a substantial probability that death or serious physical harm could result from a condition which exists . . . unless the employer did not, and could not with the exercise of reasonable diligence, know of the presence of the violation.

 

Correction of Transcript

            Transcript Vol. II, page 92, line 4, is corrected by changing the word ‘bearing’ to ‘burying.’

            Transcript Vol. III, page 121 line 20, is corrected by changing the letters ‘F-F’ to ‘E-F.’

Motions

            1. At the hearing the Respondent moved to amend its answer to allege that standard 1926.652(b) is vague and does not apply to the Respondent’s obligation. No objection having been interposed to the motion to amend the answer, it was allowed. Insofar as interpreted to quash the citation, the motion was denied . . . Tr. Vol. I, pages 7–8.

            2. The Complainant’s motion to sequester witnesses was granted with regard to all witnesses . . . Tr. Vol. I, pages 5–7.

            3. The Complainant’s motion to amend the complaint to alternatively allege a violation of standard 652(c) was denied for the reasons stated herein. The hearing was begun on October 3, 1975; and the witnesses, Smith (direct examination only), Collins, and Vail, testified on that day. On October 6 the witnesses, Hatcher and Normand, testified; and the Complainant then rested (because of illness, the witness, Smith, was to be cross-examined at a later date). The hearing was continued until February 10, 1976. On that date, near the conclusion of the cross-examination of the witness, Smith, the Complainant moved to amend the complaint to charge, in the alternative, a violation of standard 652(c). The Respondent objected on the grounds of late notice and prejudice. The Complainant’s motion was denied for the reasons that the Respondent had prepared and tried its case on standard 652(b) and would be prejudiced by the allowance of the motion . . . Tr. Vol. III, pages 76–79.

Evidence

            It was stipulated that the total sales in business done by the Respondent for the fiscal year of 1974 was $48 million and that the Respondent employed 575 persons in Connecticut . . . Tr. Vol. I, pages 3–4.

            The Respondent admitted that its employees regularly received, handled and worked with goods that have been moved across state lines and that it is an employer engaged in a business affecting commerce within the meaning of the Act . . . Answer, paragraphs 1 and 2.

            Joseph Colturi, called by the Complainant, testified that he is the Distribution Superintendent for the Respondent and that he had discussed trenching standards with Respondent’s supervisors and foremen (including Robert Vail, foreman of the worksite in question) before June 20, 1975 . . . Tr. Vol. I, pages 22 and 23. He does not recall saying to the Compliance Officer: ‘There is no excuse that it (the trench) is not shored’ . . . Tr. Vol. I, pages 25, 26 and 28.

            Robert Vail, called by the Complainant, testified that he is the Respondent’s area foreman. He said that the trench was 6 feet 8 inches deep and 2 feet 8 inches wide . . . Tr. Vol. I, pages 37, 38 and 54 . . . had sandy soil in sections, Tr. Vol. I, page 40 . . . but had stable soil, such as clay, where the work was being done . . . Tr. Vol. I, page 62. He testified that he had read and signed a statement saying the soil was unstable and trench was not shored . . . Tr. Vol. I, pages 45 and 46. He also testified that the trench had shoring from structures in it, such as a manhole and an electric light duct . . . Tr. Vol. I, page 57. He said that, before June 20, 1975, he was aware of the standard requiring shoring in unstable soil over 5 feet in depth . . . Tr. Vol. I, page 51.

            Harold R. Smith, called by the Complainant, testified that he has been the OSHA Area Director for four years; has supervised over 150 trenching inspections, and himself conducted over 40; took a four-week course in soil mechanics in the United States Department of Labor Training Institute; and had extensive trenching experience in private industry. He has worked in trenches and is very familiar with trenches and soil stability . . . Tr. Vol. I, pages 91, 99 and 102; Vol. III, page 74. The Respondent was familiar with trenching standards, including standard 652(b) . . . Tr. Vol. I, pages 68, 73, 75 and 77; Vol. III, pages 16–18, 21 and 30. The Respondent had been cited for a violation of standard 652(c) in Wethersfield, Connecticut, Docket No. 10537 . . . Tr. Vol. I, pages 70, 77 and 78; Vol. III, pages 38, 39 and 45. He has seen this general worksite dug up three to five times, and most of the soil there was backfill sand, including the exact locus of the instant citation . . . Tr. Vol. I, pages 80, 81, 84 and 90; Vol. III, page 59. Backfill or nonvirgin soil cannot be relied on for stability because it is not cohesive due to foreign objects, air pockets and basic looseness . . . Tr. Vol. I, pages 92 and 93; Vol. III, page 60. There is nothing to support the soil in the undercut area (the ‘overhang’), and it is very probable that it will come down because of that plus vibration from traffic . . . Tr. Vol. I, pages 84 and 88; Vol. III, page 67. There is substantial traffic in that area . . . Tr. Vol. III, page 60. The probability of an accident is great and death could result. . . Tr. Vol. I, page 83; Vol. III, page 62. At the worksite here, according to the Compliance Officers’ report to him, the Respondent’s supervisors told the Complainant’s Compliance Officers that the trench should have been shored . . . Tr. Vol. I, page 81. He gave copies of the Federal Register containing this standard to the Respondent at a seminar in 1971 . . . Vol. III, page 16. The soils here are mostly sand and backfill from other areas. He is familiar with the specific site and has seen trucks dump sand there. Backfill is very unreliable for stability and is basically loose. There have been seven citations to contractors at that site or within a distance of 50–60 feet. The whole corner has been torn up curb to curb; that whole street has been torn up on quite a few occasions . . . Tr. Vol. III, pages 58 and 60.

            Joseph F. Hatcher, called by the Complainant, testified that he has been an OSHA Compliance Officer for almost two years and had a construction course that included four days in shoring. Beyond that, as a staff sergeant with the Army Engineers for six years, he had had extensive experience in bridge building where there had to be a firm foundation that would not be on loose or unstable soil. This work did not include shoring of trenches . . . Tr. Vol. II, pages 24 and 26. The Respondent’s employee, Carmine Arcari, was 6 feet 8 inches down in the trench . . . Tr. Vol. II, page 7. The trench had no support system whatever . . . Tr. Vol. II, page 9. The soil throughout the trench and walls was sandy, backfill material . . . Tr. Vol. II, pages 10 and 11. The trench had a 90° wall with an undercut or overhang of about 2 feet 7 inches . . . Tr. Vol. II, pages 16 and 21. Traffic, including work trucks and cars, were passing within 3 to 4 feet of the trench . . . Tr. Vol. II, page 13. The Respondent’s Foreman, Vail, agreed the soil was sand and unstable and the trench unshored . . . Tr. Vol. II, page 20. The Respondent’s employee, Potvin, said the Respondent had opened this particular spot before, and he (Hatcher) has seen the Respondent open it on two other occasions . . . Tr. Vol. II, pages 23, 53 and 61. The Respondent’s Foreman, Vail, signed and understood the trenching form, Exh. C–12 . . . Tr. Vol. II, pages 18, 19 and 46. He heard the conversation between the Respondent’s Foreman, Vail, and the Distribution Superintendent, Colturi, in which Colturi asked why the trench was not shored, and Vail said he had not realized he was down to a depth of 5 feet 8 inches; and Colturi told the Compliance Officers that there was no reason for the trench not being shored . . . Tr. Vol. II, page 17. The site was on a main street in Hartford, and the traffic vibrations would cause movement of earth and be unsafe . . . Tr. Vol. II, pages 16, 54 and 55.

            Joseph P. Normand, called by the Complainant, testified that he has a Master’s Degree in Mechanical Engineering and has been an OSHA Compliance Officer since March 1975. He took a month’s course in OSHA procedures which did not include shoring or soil mechanics, and he had inspected two trenches . . . Tr. Vol. II, pages 94 and 97. The soil in the trench and walls was sandy backfill and appeared to be unstable, and there were small cracks in the walls of the trench . . . Tr. Vol. II, pages 75 and 76. Traffic came within 3 feet of the trench . . . Tr. Vol. II, page 71. Where the Respondent’s employee, Arcari, was working was 2 feet 8 inches wide. . . Tr. Vol. II, page 88. The sloping of the trench did not conform to OSHA regulations . . . Tr. Vol. II, pages 87 and 88. The Respondent’s Foreman, Vail, signed the trenching form after Compliance Officer Hatcher went over the items with him. Vail said he did not know they were going that deep . . . Tr. Vol. II, page 84. The Respondent’s Distribution Superintendent, Colturi, said there was no excuse for not shoring the trench . . . Tr. Vol. II, page 84. There were no supports in the trench . . . Tr. Vol. II, page 85. The hazard was that the trench would collapse, burying the employee in it, the cause being the soil’s unstable condition and vibrations from the traffic . . . Tr. Vol. II, pages 79, 92 and 106.

            Romeo Potvin, called by the Respondent, testified that he has been a chief street man for the Respondent for seven years, a member of the street crew for 12 years before that, is familiar with sloping of trenches, has participated in training sessions on shoring and safety of excavations, and over his 19 years of employment has been involved in work assignments that included shoring . . . Tr. Vol. II, pages 157 and 158. One of his responsibilities is determining safety of trenches . . . Tr. Vol. II, page 137. The east side wall of the trench in question had an 18-inch electric conduit encased in concrete and the west side had a concrete manhole in it. From the surface of the road there were 14 inches of concrete reinforced with steel, then a foot or foot and a half of packed gravel below that, and then the 18-inch electric conduit . . . Tr. Vol. II, pages 137–139. It was his opinion that, because of these items, the trench had its own natural shoring, was sufficiently shored, and was safe . . . Tr. Vol. II, page 159. Steel plates that weighed about a ton each were put over the excavation Friday and were removed on Monday without any change in the excavation . . . Tr. Vol. II, page 157. On June 26, the condition of the trench and soil was the same as June 20 . . . Tr. Vol. II, page 160. The trench measured 5 feet 6 inches at its deepest point and 4 feet 6 inches at all other points . . . Tr. Vol. II, page 153. He and the employee, Arcari, were the only two who had been in the trench . . . Tr. Vol. II, pages 165 and 166. The Respondent had told him trenches over 5 feet will be shored . . . Tr. Vol. II, page 170. As chief street man, he is not a supervisor; but he is the working foreman. He did not bring shoring equipment because he would not know if it was necessary until the trench was open. The decision not to shore was made by him without consulting the Respondent’s management. It was his responsibility . . . Tr. Vol. III, pages 4–7. He did not consider the ‘overhang’ to be hazardous . . . Tr. Vol. II, page 169. Before June 20, he was familiar with trenching standards. Before April of 1974, he had attended OSHA briefings on standards. In April 1974, at another of the Respondent’s worksites, he was in a trench that was 6 feet 2 inches at one point but was not shored. At the time, he was responsible for safety of employees. The Respondent did not contest that citation . . . Tr. Vol. III, pages 4 and 7.

            Frank H. Livingston, called by the Respondent, testified that he is a vice president for the Respondent, in charge of employee relations. The discussion about OSHA regulations referred to by the witness, Smith, had very little to do with standard 652(b); were mostly on posting, and so forth; and there was very little on shoring. He wrote the letter (Exh. C–14) which says in part: ‘A meeting was held for all Distribution Division employees on April 30, 1974, and shoring of ditches . . . were covered.’ . .. Tr. Vol. III, pages 93–99.

            Clarence Welti, called by the Respondent (the Complainant agreed that he qualified as a soils expert), testified that he was retained by the Respondent to investigate the worksite after the OSHA inspection. He had previously been retained by the Respondent sometime before to make a survey in general of the Respondent’s excavations to evaluate possible dangers . . . Tr. Vol. III, pages 100–102. He went to the instant worksite on June 26, 1975, and drew a cross section of the excavation (Exh. R–4) from it. On Exh. R–4, in the F-F area, from the top of the excavation, going down, was 1 foot 2 inches of concrete; then compact processed stone; then 18 to 20 inches of duct; and then compact clay silt filled with sand. From the bottom of the processed stone to the bottom of the trench was 3 feet to 3 feet 6 inches; and from the bottom of the concrete to the bottom of the trench was about 5 feet or a little less . . . Tr. Vol. III, pages 113 and 114. He took samples and they tested out as follows: Sample No. 1, from the area marked A-A on Exh. R–4, was noncohesive sand; No. 2, from the same area but deeper, was coarser material, with some gravel, but was noncohesive; No. 3, between the areas marked C-C and F-F, was stiff, cohesive clay silt. The F-F slope was stable . . . Tr. Vol. III, pages 118–120. The manhold and the electric duct also helped stabilize the trench wall. . . Tr. Vol. III, pages 122 and 123. The clay silt would retain stability of the trench up to 10 feet, independent of the manhole and duct . . . Tr. Vol. III, pages 133 and 134. The A-A area would have to be shored . . . Tr. Vol. III, page 134. The soil beneath the duct was natural or nonplaced soil . . . Tr. Vol. III, page 141. The soil in the trench bottom was sandy; a large part of the excavation was sand . . . Tr. Vol. III, pages 152 and 154. Sandy soil or soil which has been backfilled is very unstable and requires sheeting . . . Tr. Vol. III, pages 154 and 155. One wall of the trench contained backfill; the other wall was totally different . .. Tr. Vol. III, page. 154.

            Various photographs were introduced, showing the worksite, and various exhibits, including C–11 and C–12. Exh. C–11 was the March, 1974, instructions of the Respondent to its employees. Section 5M of that document states in part:

‘While working in any area where the trench is 5 (60‘) or deeper, or other conditions are such that the trench is subject to cave-in, the side walls of the excavation shall be adequately shored . . ..’

            Exh. C–12, a form used by the Compliance Officer in excavation cases, described the soil as ‘unstable’ and ‘sandy.’ It was signed by the Respondent’s Foreman, Vail, under the typed words: ‘I hereby verify the above to be true and accurate.’

Discussion

            There is little doubt that Respondent specifically knew about standard 652(b). The Complainant’s witnesses were very positive about discussions with the Respondent’s personnel concerning it, and the Respondent’s witnesses remembered the discussions but in a less detailed way. In addition, the Respondent’s Foreman, Vail, testified that he was aware of standard 652(b) before June 20, 1975 (the date of the inspection). The Respondent’s knowledge is also corroborated by Exh. C–14 (the Livingston letter) and by Exh. C–11.

            There is virtually no controversy about the measurements of the trench: The Respondent’s Foreman, Vail, testified it was 6 feet 8 inches deep and 2 feet 8 inches wide; and I so find.

            There was contradictory testimony on the question of stability. However, in addition to the emphatic testimony of the OSHA Compliance Officers that the soil was unstable, there was the uncontradicted testimony that the general site had been torn up on several occasions by various contractors. Every witness who testified on ‘backfill’ agreed that it is less stable than ‘virgin soil.’ In addition, although he had an explanation as to why he had done so, the fact remains that Respondent’s Foreman, Vail, had read and signed a statement (Exh. C–12) saying the soil was unstable. Although the Respondent’s expert witness, Welti, said the trench was stable, he also testified that certain areas needed shoring, a large part of the excavation was sand, and one wall of the trench was very different from the other in that it contained backfill. The photographs (C–9, c–10 and R–1) of the worksite corroborated the testimony that there was substantial traffic there, some of it coming within a few feet of the excavation. The evidence was quite conclusive that the soil was unstable, and I so find.

            I found no need to refer to Exh. C–16 in coming to this conclusion, and it played no part in my decision.

            Was the violation willful? The evidence is clear that the Respondent had actual and specific knowledge of standard 652(b) and did not comply with the standard. However, while it is not necessary for the Complainant to show malice, ‘willful’ does require a conscious and deliberate decision, an intentional and knowing violation of the Act, or action taken knowledgeably in disregard of the action’s legality. Here, the Respondent had instructed its foreman to shore trenches over 5 feet or wherever the soil was such that it was necessary. It had also issued the instructions spelled out in Exh. C–11. In addition, some weeks before the inspection in the instant case, the Respondent had retained a soils expert to investigate possibly dangerous excavations (apparently so Respondent could take preventive measures in such places).

            The evidence here falls short of establishing willful misconduct, and I find there was no willful misconduct on the part of the Respondent.

            The parties have fully tried the case on the major issue of whether there was a serious violation where the hazard was death or serious injury because of unstable soil; and the Respondent has always been aware that that is the major issue . . . Tr. Vol. I, pages 83, 84 and 93; Tr. Vol. II, pages 16, 34, 49, 54, 62, 67, 79, 92, 98, 106 and 125–132; Tr. Vol. III, pages 20, 27, 29, 34, 37, 38, 41, 42, 43, 57, 58, 62, 69 and 70. I find that the Complainant has sustained the burden of proving such a serious violation of standard 652(b).

Findings of Fact

            Having heard the testimony, observed the witnesses, and examined the exhibits, the following Findings of Fact are made:

            1. At all times concerned, the Respondent regularly received, handled or worked with goods which had moved across state lines.

            2. As concerns Item #1 of Citation #1, the trench in question was over 5 feet in depth; its sides were in unstable or soft material; and they were not shored, sheeted, braced, sloped, or otherwise supported.

            3. The conditions described in Item #1 of Citation #1 exposed the Respondent’s employees to sustaining serious or fatal harm because of the hazard of collapse of the trench.

            4. One or more officers or supervisory personnel of the Respondent was aware of the hazardous conditions described herein and knew that employees were exposed to such hazard.

            5. The Respondent’s conduct was not willful or deliberate or intentional.

Conclusions of Law

            1. At all times concerned, the Respondent was an employer engaged in a business affecting commerce within the meaning of the Act; and the Occupational Safety and Health Review Commission has jurisdiction over the subject matter and the parties.

            2. At all times concerned, the Respondent knew, or with the exercise of due diligence should have known, of the alleged violation.

            3. On the date in question, the Respondent was not in compliance with 29 C.F.R. 1926.652(b); and the Complainant has sustained the burden of proving the Respondent violated § 5(a)(2) of the Act (§ 654).

            4. The Complainant has not sustained the burden of proving the Respondent willfully violated 29 C.F.R. 1926.652(b) but has sustained the burden of proving the Respondent committed a serious violation of 29 C.F.R. 1926.652(b).

Order

            The whole record having been considered, and due consideration having been given to 29 U.S.C. § 666(j), it is ORDERED:

            Citation #1 is affirmed insofar as a serious violation is alleged, and a penalty of $1,000 assessed therefor.

 

 

So ORDERED.

 

FOSTER FURCOLO

Judge, OSHRC

Dated: June 14, 1976

 

Boston, Massachusetts

 



[1] Commissioner COTTINE took no part in the consideration or decision of this case for the reasons set forth in his separate opinion.

[2] The standard reads as follows:

§ 1926.652 Specific trenching requirements.

(b) Sides of trenches in unstable or soft material, 5 feet or more in depth, shall be shored, sheeted, braced, sloped, or sheeted, braced, sloped, or otherwise supported by means of employees working within them. See Tables P-1, P-2.

[3] The citation as issued alleged a willful violation of the standard and proposed a $6000 penalty. The Secretary did not except to the Judge’s recharacterization of the violation as serious. Accordingly, the Commission will not review this matter. See Water Works Installation Corp., 76 OSAHRC 61/B8, 4 BNA OSHC 1339, 1976-77 CCH OSHD para 20,780 (No. 4136, 1976); Crane Co., 76 OSAHRC 37/A2, 4 BNA OSHC 1015, 1975-76 CCH OSHD para. 20,508 (No. 3336, 1976).

[4] Throughout this decision that sections of the trench will be designated by the letters shown on this diagram. This follows the designations used by respondent in its exhibits.

[5] Dr. Welti was the only witness qualified and accepted as an expert; he was qualified as an expert in soil and foundations.

[6] The other two soil samples were from the west trench (section A & between sections C & F); both of these tested as noncohesive sand.

[7] Respondent moved at trial to amend its answer to include the affirmative defense of the vagueness of the standard. The Judge granted the motion to amend and interpreted the amendment as a motion to dismiss. He denied the motion to dismiss without stating any reasons at trial or in his decision.

[8] Commissioner Barnako notes, however, that the Commission, consistent with Cape & Vineyard, has limited the applicability of certain broadly drafted standards so as to assure that employers have adequate notice of the conduct such standards require. In such cases, the applicability of the standards is limited by external or objective criteria, such as other standards or the understanding of reasonable persons familiar with the circumstances of the employer’s industry regarding the hazard involved. See, e.g., B & B Insulation, Inc., 77 OSAHRC 49/A2, 5 BNA OSHC 1265, 1977-78 CCH OSHD para. 21,747 (No. 9985, 1977), appeal filed, No. 77-2211 (5th Cir. 1977); Grand Union Co., 75 OSAHRC 88/A2, 3 BNA OSHC 1596, 1975-76 CCH OSHD para. 20,107 (Nos. 7031 & 7533, 1975).

[9] The standard reads in pertinent part:

§ 1926.652 Specific trenching requirements.

(c) Sides of trenches in hard or compact soil, including embankments, shall be shored or otherwise supported when the trench is 5 feet in depth and 5 feet or more in length. In lieu of shoring, the sides of the trench above the 5-foot level may be sloped to preclude collapse, but shall not be steeper than a 1-foot rise to each ½-foot horizontal . . . .

[10] Respondent does not take exception to its own witness’ testimony but to the fact that the Judge relied on it to determine that the soil was unstable.

[11] The only soil sample analyzed by Dr. Welti which was relevant to the east trench was taken from the middle of the eastern wall [section F]. This was analyzed as cohesive clay silt. Dr. Welti’s testimony that the soil was stable refers specifically to section F of the trench. We note that one compliance officer testified that there were line cracks in this wall.

[12] Respondent’s employees were exposed to the hazard of a cave-in in section E of the trench. One of respondent’s employees was straddling a pipe located in the middle of the trench between sections E and F. Also, employees had access to that section of the trench as shown by complainant’s photographs of tools along the wall of section E. See Gilles & Cotting, Inc., 76 OSAHRC 30/D9, 3 BNA OSHC 2002, 1975-76 CCH OSHD para. 20,448 (No. 504, 1976).

[13] We also reject respondent’s contentions that the Judge erred in relying on the statement signed by the foreman and on the evidence of substantial traffic near the trench. Respondent had objected to the introduction of this statement on the grounds that counsel for the Secretary suggested that a violation was established by it. The Judge denied the objection, ruling that the statement was cumulative of the foreman’s testimony. The foreman was well aware of the statements concerning the trench as indicated by his insistence that the trench be remeasured before he signed the form. He also testified that he read the form before signing it. The Judge’s reliance on the fact that substantial vehicular traffic near the trench added to the instability of the soil was based on testimony that the traffic vibrations increased the possibility of collapse. Both of these factors constituted additional evidence cited by the Judge in support of his determination that the soil was unstable. This evidence was not decisive. The Judge’s finding that the soil was unstable is supported by evidence of record without resort to these factors, and undisputed evidence establishes the instability of section E of the trench.

[14] We do not decide whether a violation of sections A, B, C and D was proven. Although there was proof that the soil was unstable, there was no evidence of employee access to these sections of the trench. See n. 11, supra. Furthermore, there was insufficient proof concerning the depth of these sections of the trench.

[15] A Commissioner may vote simply to avoid an impasse. Public Service Commission of State of N.Y. v. FPC, 543 F.2d 757, 777 (D.C. Cir. 1974). See generally Screws v. United States, 325 U.S. 91, 134 (1945) (Rutledge, J., concurring in result).

[16] The Court distinguished WIBC, Inc. v. FCC, 259 F.2d 941 (D.C. Cir.) cert. denied, sub nom. Crosley Broadcasting Corp. v. WIBC, Inc., 358 U.S. 920 (1958), because oral argument was statutorily required if a party requested it. 348 F.2d 798, n. 14.