UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 13822 |
DONOVAN ELECTRIC COMPANY, |
|
Respondent. |
|
November 10, 1977
DECISION
BEFORE CLEARY, Chairman; and BARNAKO, Commissioner.
BY THE COMMISSION:
A
decision of Judge John S. Patton is before us for review pursuant to 29 U.S.C.
§ 661(i). The Judge affirmed a citation alleging the
Donovan Electric Company violated standards at 29 C.F.R. 1926.500(b)(1) and 29
C.F.R. 1926.500(f)[1]
in that a floor opening was inadequately guarded. The principle issue before us
is whether the Judge erred in concluding that he was not bound by the decision
in Anning-Johnson Co. v. OSHRC, 516 F.2d 1081 (7th Cir. 1975).
The
alleged violation concerns three elevator shaft openings in a building under
construction. The openings were equipped with guardrails and toeboards,[2] but not midrails. Employees of Donovan, the electrical
subcontractor, worked on the floors having the openings. They passed within three
to five feet of the openings so as to gain access to their work areas. The
maximum fall distance through any opening was 17 feet. The general contractor
had responsibility for installing and maintaining necessary guardrail
protection.
Donovan’s
policy, upon discovering unsafe conditions it could not itself correct, was to
ask the responsible contractor to correct the conditions. If this was not done,
Donovan warned its employees to avoid the unsafe areas. Donovan held weekly
safety meetings with its employees; at some of these meetings it warned its
employees to stay away from openings which existed on the jobsite, including
those involved in this case.
The
Judge affirmed the citation because Donovan’s employees were exposed to the
hazard, citing our decisions in Robert E. Lee Plumbers, Inc., 75 OSAHRC
56/C2, 3 BNA OSHC 1150, 1974 1975 CCH OSHD para. 19,594, (No. 2431, 1975) and Alcap Electric Corp., 75 OSAHRC 60/A3, 3 BNA
OSHC 1203, 1975 1976 CCH OSHD para. 19,640 (No. 1722, 1975). He rejected
Donovan’s argument that he should follow the decision in Anning-Johnson,
supra, in which the 7th Circuit held that a subcontractor on a
multi-employer construction site is not responsible for nonserious violations
it did not create or control, despite the exposure of its employees to the
hazard.
Subsequent
to the judge’s decision, the Commission decided Grossman Steel and Aluminum
Corp. 76 OSAHRC 54/D9, 4 BNA OSHC 1185, 1975 1976 CCH OSHD para. 20,691
(No. 12775, 1975), and Anning-Johnson Co. 76 OSAHRC 54/A2, 4 BNA OSHC
1193, 1975 1976 CCH OSHD 20,690 (No. 4409, 1976). In those cases we declined to
follow all aspects of the 7th Circuit’s Anning-Johnson decision. We held
that, where the usual criteria establishing employer liability have been shown,
a subcontractor on a multi-employer construction site who did not create a
violation and lacked the ability to abate within the literal terms of the
standard can defend by showing that it took realistic steps, as an alternative
to literal compliance with the standard, to protect its employees. See also Mayfair
Construction Co., 5 BNA OSHC 1877, (No. 2171, Sept. 26, 1977).
The
Commission members differ on whether Donovan has established such a defense.[3] Commissioner Barnako
concludes that Donovan’s warning to its employees to avoid the openings was
sufficient under the circumstances of this case. Donovan’s employees did not
work around the openings but only passed by them in going to their work
stations. In his opinion, the existence of the toprails
would in these circumstances have protected them generally against a fall. An
accident was extremely unlikely, and respondent’s warning was a realistic
alternative to literal compliance.
Chairman
Cleary agrees that Donovan’s warning was specific and effective enough to pass
muster, but he would conclude that Donovan should also have notified the
general contractor of the conditions and requested correction.[4]
It
has been the Commission’s policy, in cases of this type which were tried prior
to the issuance of our decisions in Grossman and Anning-Johnson,
supra, to afford the subcontractors an additional opportunity to establish
the defenses announced therein. Chairman Cleary would afford Donovan such an
opportunity. Commissioner Barnako thinks that Donovan has already established a
valid defense, and would therefore vacate the citation. However, in view of the
lack of a majority the judge’s decision is affirmed. Therefore, Commissioner
Barnako agrees to an order giving Donovan the opportunity to establish a
defense under Commission precedents.
Accordingly,
the Judge’s decision is affirmed unless Donovan requests a further hearing
within ten days of its receipt of this decision. In such event the order will
be withdrawn and the case remanded for further proceedings consistent with this
decision.
FOR THE COMMISSION
Ray H. Darling, Jr.
Acting Executive Secretary
Dated: November 10, 1977
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 13822 |
DONOVAN ELECTRIC COMPANY, |
|
Respondent. |
|
FINAL ORDER DATE: May 7,
1976
DECISION
AND ORDER
APPEARANCES
Edward B. Gaines,
Esq., and Stephen J. Simko, Jr., Esq., Office of the Solicitor, U. S.
Department of Labor, Atlanta, Georgia, on behalf of complainant
Donald E. Karraker, Esquire, Winter Park, Florida, on behalf of
respondent.
STATEMENT
OF THE CASE
Patton, Judge:
This is a proceeding pursuant to section 10 of the
Occupational Safety and Health Act of 1970 (29 U.S.C. § 651, et seq., 84 Stat.
1590, hereinafter referred to as the Act) contesting a citation issued by the complainant
against the respondent under the authority vested in complainant by section
9(a) of the Act.
The citation alleges that as a result of the inspection
of a workplace under the ownership, operation or control or the respondent
located at 875 Sterthaus Avenue, Ormond Beach,
Florida, the respondent had violated section 5(a)(2) of the Act by failing to
comply with Occupational Safety and Health Standard 29 C.F.R. 1926.500(b)(1)
and 29 C.F.R. 1926.500(f). Hearing was held in Daytona Beach, Florida, on
September 30, 1975. Both parties appeared and presented evidence. There was no
motion to intervene.
ISSUES
IN THE CASE
It was alleged that respondent, in a construction project
at a hospital at the above-described location, failed to provide standard guardrails
at the sixth and seventh floor service elevator openings and the sixth floor
west general elevator opening, in violation of standards 29 C.F.R.
1926.500(b)(1) and 29 C.F.R. 1926.500(f). Respondent defends on the ground that
the contractual obligation to maintain the property in accordance with the Act
rested upon the general contractor and not upon the subcontractor and that,
therefore, the subcontractor cannot be held to be in violation for failure of
the property to meet standards of the Occupational Safety and Health Act.
EVIDENCE
IN THE CASE
Respondent admitted in its answer that it is a
corporation having a place of business and doing business in Ormond Beach,
Florida. It was admitted that respondent has been, at all times relevant to
this cause, an electrical contractor and is a business affecting interstate
commerce within the meaning of the Act. The evidence establishes that
respondent was performing electrical work in construction of a hospital, and
that there were four elevator openings on floors six and seven, one of which
had proper rails as required by the statute. The compliance officer, Mr. James
R. Stock, testified that three of the openings did not have rails which
complied with the standard. On the seventh floor, there was an elevator
opening, which had a one-by-eight-inch wooden top rail, whereas the standard
requires a two-by-four-inch rail, and it also had a toeboard,
which was two by eight inches in size. There was no centerboard. On the sixth
floor, there was a service elevator shaft with an opening, which had a top rail
and toeboard, the top rail being two by eight inches,
which was satisfactory, and the toeboard was
satisfactory, but there was no middle rail (Tr. 31, 32, 33). There was another
opening with a two-by-four-inch top rail and a two-by-four inch toeboard but no intermediate rail (Tr. 33). Seven of
respondent’s employees worked these two floors, said employees having to pass
within close proximity of said openings (Tr. 14, 15, 22, 43).
Mr. Dennis Swanson, who worked for respondent, stated
that they regularly used the east stairwell to gain access to the seventh floor
level, and after coming off of the seventh floor stairway, they passed in the
area of a service floor elevator opening. If they wanted to walk into the center
of the building and turned left, they walked right by the elevator opening. If
they passed down the corridor in the regular manner, going to and from the
jobsite on that floor, in the center of the floor, they came within several
feet of the opening (Tr. 43, 44). They did not work in the shafts in front of
the openings (Tr. 44). There was a distance of approximately six feet between
the sixth floor and fifth floor of the elevator shaft (Tr. 45). The fall
distance from the seventh to the fifth floor elevator opening was approximately
17 feet (Tr. 45). The top of the elevator area on the fifth floor is metal
grade and on top of that for four or five inches is foam and then tar and
gravel (Tr. 46).
Mr. Swanson was a union job steward and, prior to the
issuance of the citation, he went to the general contractor probably once a
week with a complaint; twice the employees walked off the sixth and seventh
floors to work on the first floor because of the unsafe condition of the
floors. These complaints were about things other than the guardrails. He could
never recall making a complaint about the guardrails (Tr. 50, 51). Respondent
took the position that men were to stay away from these unsafe areas until they
were corrected. If Mr. Swanson and the foreman felt in area was unsafe, they
would move the employees to a safe area until the hazard could be corrected. It
was Mr. Swanson’s policy to go to the foreman and show him the dangerous area
and then to the general contractor, and if the general contractor did not correct
it, to move the men (Tr. 54). The respondent talked about the openings at
safety meetings. Employees were told to stay away from openings, but it was
impossible to completely do so, as they had to walk by them (Tr. 54, 55).
Safety meetings were held once a week. It was brought up at one of the safety
meetings that these openings were not properly guarded (Tr. 55). Mr. Swanson
testified that he was an electrician and was not skilled in other tasks,
therefore, would not have had the competence to install guardrails (Tr. 52).
The respondent introduced the contract between the general contractor and the
subcontractor, if being the position of the respondent that the general
contractor had the responsibility of making corrections.
EVALUATION
OF THE EVIDENCE
It is undisputed that the requirements for guardrails
over openings were not complied with adequately. It is also undisputed that
some guardrails existed over all openings. There were no middle guardrails on
any of the openings, and the sizes of the boards did not, in all instances,
meet the requirements of the standard. It also would appear that the employees
had to pass in close proximity to the openings, and that the condition was
considered serious enough that it was brought up in at least one of the
company’s safety meetings. It was not controverted that the primary contractual
responsibility to maintain the premises rested not upon the respondent but upon
the general contractor. The sole issue for determination, therefore, is whether
the respondent may be held in violation because it permitted its employees to
work in conditions prohibited by the standard but
which were not the contractual responsibility of the respondent.
In the case of Secretary v. Robert E. Lee Plumbers,
Inc., 17 OSAHRC 639 (1975), the Review Commission stated: (at 639, 640)
Lee argues that,
because it did not create the violative conditions or control those areas of
the worksite where these conditions existed, it should not be found in
violation. We have consistently rejected this argument. R. H. Bishop Co.,
8 OSAHRC 930, BNA 1 O.S.H.C. 1767, CCH E.S.H.G. para. 17,930 (1974); California
Stevedore & Ballast Co., 8 OSAHRC 811, BNA 1 O.S.H.C. 1757, CCH
E.S.H.G. para. 17,931 (1974). As we said in R.H.Bishop:
In the usual case
an employer is in violation of section 5(a) when his employees are affected by
a violative condition. It is no defense that others created the condition, were
responsible for its existence, or had control of the site where such condition
exists. 8 OSAHRC at 931.
The Review Commission held in the case of Secretary v.
Alcap Electrical Corp., 18 OSAHRC 1 (1975), as
follows:
‘At issue is
whether a subcontractor can be held liable under the Act if its employees are
exposed to hazards resulting from conditions it did not create or control. We
have consistently answered that affirmatively. See Secretary v. City Wide
Tuckpointing Service Co., OSAHRC DOCKET NO. 247 (May 24, 1973), Secretary
v. Gilles and Cotting, Inc., OSAHRC DOCKET NO.
504 (October 9, 1973), Secretary v. Hawkins Construction Co., OSAHRC
DOCKET NO. 949 (May 20, 1974).’
However, the United States Court of Appeals for the
Seventh Circuit has refused to approve the above-stated position of the
Occupational Safety and health Review Commission. In the case of Anning-Johnson
Co. & Workinger Electric, Inc. v. OSAHRC &
Secretary of Labor, 516 F.2d 1081 (7th Cir. 1975), the court, in reversing the
Occupational Safety and Health Review Commission, stated: (at 1085, 1090–91)
‘. . . In Robert
E. Lee Plumbers, Inc., OSHRC DOCKET NO. 2431 (Jan. 30, 1974) (Commission
Review Ordered), it was said:
Admittedly, the
respondent is responsible for the ‘place of employment,’ yet no one should
conclude that such responsibility imposed by the Act embraces the entire work
project as shown in this case. This responsibility is the responsibility of the
prime contractor. . . .
Assuming as we
have just found that requiring abatement of hazards by subcontractors not
responsible for the violating conditions is impractical, the only other
alternative available is for such a subcontractor to remove his employees from
the job after a violation is discovered and prior to a citation being issued.
This again not only requires a subcontractor to be able to recognize
non-serious violations outside its field of expertise, but is an unrealistic
and economically unfeasible solution.
On many
construction jobs the withdrawal of a single subcontractor, upon whose work
future construction depends, could conceivably cause an entire project to shut
down. The subcontractor who wants to avoid OSHA liability must guess at his
peril that in fact a violation exists. . . .
For all of the
foregoing reasons we have determined that the Secretary’s and Commission’s
position cannot be sustained.
The respondent maintains that the United States Court of
Appeals for the Seventh Circuit, having held that the subcontractor is not in
violation if the primary contractual duty of complying with the law was on the
general contractor, the Review Commission is bound by said decision, and the
complaint in this case should be dismissed. It should be noted, however, that
this case did not arise within the jurisdiction of United States Court of
Appeals for the Seventh Circuit but within the jurisdiction of the United States
Court of Appeals for the Fifth Circuit. This Judge is bound by the decisions of
the United States Circuit Court of Appeals within the area of said Court’s
jurisdiction. Decisions of the United States Circuit Courts of Appeals outside
the jurisdiction of the case at bar are only persuasive and not binding. Until
the Review Commission has reversed its position, this Judge is bound by the
decisions of the Review Commission in all areas other than those governed by
the United States Circuit Court of Appeals for the Seventh Circuit. The
respondent raises a number of very substantial arguments as to why
subcontractors should not be held in violation where respondent does not have
the contractual responsibility of maintaining the property. The respondent contends
that it should not be held in violation for the following reasons: for the
respondent to abate would, according to the respondent, interfere with the work
of others; furthermore, it is pointed out that ordinances make it unlawful to
contract or perform work outside the scope of operation of the skills of a
particular craft, it being required that contractors be licensed to work within
a certain craft framework. Union contracts require that only employees of a
certain craft be permitted to do work that is under the jurisdiction of that
craft. Once subcontractors know they must not only discover but abate all
hazards to which their employees are exposed, the immediate result will be a
great duplication of effort in searching for defects. Employers have to be
knowledgeable enough to detect a potential hazard and would not have that
knowledge, in many instances, outside their own craft and skill. Many
subcontracts provide that subcontractors shall do nothing to interfere with
work of other subcontractors. A removal of employees from the job to prevent
employees’ exposure to hazard would breach the contract with the general
contractor. To require the subcontractor to abate would be to require multiple
expenditures on discovery of violations, as well as cause duplicate
expenditures, in many instances, in actual abatement.
These arguments are ably
presented by the respondent and are persuasive. This Judge, however, feels
bound by the decisions of the Occupational Safety and Health Review Commission
until and unless said decisions are reversed by the Review Commission or until
they are reversed by a court of higher jurisdiction within the area in which
the case arises.
The contention of the respondent that a subcontractor
would lack the skills to correct a hazardous condition does not absolve the
respondent of the responsibility to correct such a condition. It is not
necessary for an employer to do said work with his employees for the condition
to be corrected. If the respondent’s employees lack the requisite skill, the
employer must contract to have the work done by others. There is certainly
nothing in the law that places an obligation for safety on a company only if it
has people within its own employ who can make the corrections. As to the
respondent being controlled by a contract with the general contractor, it
should be noted that the Occupational Safety and Health Act has now been
enacted for approximately five years. There would be very few, if any,
construction contracts which would have been entered into prior to the time of
enactment of the law. Any dilemma that an employer finds itself in as a result
of a contractual obligation could very easily have been avoided by providing in
the contract for the contingency of a violation of the Occupational Safety and
Health Act. It could very easily be provided that the employees of an employer
would not be required to work under conditions which the general contractor has
not corrected, and it could be provided that if a subcontractor removes its
employees from the job to avoid a hazardous situation there would be no breach
of contract. Any other contractual provisions, such as that an employer cannot
do work which would interfere with the work of another subcontractor, could
certainly have been taken care of in the negotiation and execution of the
contract. If the law places a pre-existing obligation upon parties, that
obligation cannot be destroyed by a contract entered into by and between the
parties subsequent to enactment of such legislation and subsequent to promulgation
of such standards. To permit parties to enter into contracts which make
compliance impossible, from a contractual standpoint, with the law would
definitely be opposed to public policy. The dilemma that the respondent finds
itself in because its hands may be contractually tied is of its own making. The
enforceability of a contract which would require the respondent to violate
federal law is also seriously open to question.
It should further be noted that there is no indication in
the record that the respondent made any request of the general contractor that
the guardrail situation be improved or that the respondent made any request of
the general contractor for permission to erect adequate guardrails itself.
There is some evidence of complaint to the general contractor by the labor
organization, but this would not be an action by the respondent. There is no
indication in the record that permission to erect adequate guardrails would
have been denied by the general contractor. It would appear that the addition
of a mid-rail and the substitution, in certain instances, of a larger board for
the top or bottom rail is not the type of activity that would have damaged,
impaired or interrupted the work of either the general contractor or the
subcontractors. It would seem a very simple thing to nail a board securely
across an elevator shaft opening. It would certainly not appear to be a
situation where interference with work of subcontractors and of the general
contractor would result from remedying the situation or where there would be
any damage to the premises or any actual interference with anyone. Therefore,
even if, in instances where the above factors are present a respondent should
be absolved from violation of the Act, it would appear that in the case at bar,
many of the problems suggested in the arguments of the respondent have not been
shown to be present. It must therefore be held that the complaint has been
sustained.
the proposed penalty for said violation is $30. It would
certainly appear that, in view of the possibility of serious injury resulting
from a fall, a penalty of $30 would be most minimal. It is alleged that said
violation is a non-serious violation. It might be questionable as to whether
the violation, under the circumstances, would be a serious violation; but, in
view of the fact that only a non-serious violation is alleged, the question of
whether the violation would be a serious violation cannot be considered in this
case.
FINDINGS
OF FACT
1. Respondent is a corporation having a place of business
and doing business in Ormond Beach, Florida, where it is engaged in the
business of an electrical contractor.
2. Respondent is engaged in a business affecting
interstate commerce within the meaning of the Act.
3. On or about June 3, 1975, respondent permitted its
employees to work in close proximity to openings to an elevator shaft which had
inadequate guardrails. None of said openings had a mid-rail, and several of
said openings had inadequate wooden rails at the top or bottom of said openings.
4. Said openings to the elevator shaft were on the sixth
and seventh floors, and the distance from which an employee could have fallen
from the sixth floor was six feet, and the distance from which an employee
could have fallen from the seventh floor was 17 feet.
5. The primary contractual obligation to maintain the
premises rested upon the general contractor. The fact that said openings to the
elevator shaft were unsafe to employees of respondent was called to the
respondent’s attention at a safety meeting.
6. The evidence does not establish that the respondent at
any time requested the general contractor to correct said condition, nor does
the evidence establish that the respondent requested permission of the general
contractor to correct said condition itself.
7. The evidence does not establish that to correct said
condition would have damaged the property or interfered with another
contractor.
CONCLUSIONS
OF LAW
1. Respondent is engaged in a business affecting
interstate commerce and is within the jurisdiction of the Occupational Safety
and Health Act.
2. A subcontractor is in violation of the Act if its
employees are permitted to work in conditions which violate an occupational
safety and health standard, notwithstanding the fact that the contractual
responsibility for maintaining the premises is upon the general contractor
rather than the subcontractor.
3. On or about June 3, 1975, respondent violated section
5(a)(2) of the Act and Occupational Safety and Health Standards 29 C.F.R.
1926.500(b)(1) and 29 C.F.R. 1926.500(f).
ORDER
Respondent, on or about June 3, 1975, violated section
5(a)(2) and Occupational Safety and Health Standards 29 C.F.R. 1926.500(b)(1)
and 29 C.F.R. 1926.500(f). A penalty in the amount of $30 is assessed for said
violation. The requirement that said violation be immediately abated is
affirmed.
Dated this 7th day of April 1976.
JOHN S. PATTON
[1] These standard
provide, in relevant part:
29
C.F.R. 1926.500
(b) Guarding of floor openings and floor
holes. (1) Floor openings shall be guarded by a standard railing and toeboards
or cover, as specified in paragraph (f) of this section. In general, the
railing shall be provided on all exposed sides, except at entrances to
stairways.
(f) Standard specifications: A standard
railing shall consist of toprail, intermediate rail, toeboard, and posts, . . .
(i) For wood railings, the post shall be of at least 2-inch by 4 inch stock
spaced not to exceed 8 feet; the toprail shall be of at least 2-inch by 4-inch
stock.
[2] The Judge found, with respect to the toprails and toeboards, that ‘several of said openings had inadequate wooden rails at the top or bottom . . .’ The evidence shows, however, that all of the toeboards and the toprails surrounding two of the openings were unquestionably adequate. The toprail around the remaining opening was of 1 x 8 stock instead of the 2 x 4 material specified in 1926.500(f). It is not clear whether the Secretary alleged that this railing was inadequate. In any event, it is clear that the absence of midrails is the heart of the Secretary’s case.
[3] Donovan contends
that the evidence shows that it did ask the general contractor to install
adequate guardrails, citing testimony by one of its employees that he did, on
occasion, ask the general contractor to correct safety violations. This
witness, however, could not recall whether he mentioned these particular
openings to the general contractor. Thus, the Commission members agree the
Judge correctly found that the evidence did not establish Donovan requested the
general contractor to correct the conditions involved in this case.
[4]. See note 3.