UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 14516 |
TRUAX
& HOVEY DRYWALL CORP., |
|
Respondent. |
|
June
6, 1978
DECISION
Before CLEARY, Chairman: BARNAKO, Commissioner.
BARNAKO, Commissioner:
The
Secretary of Labor cited Respondent (Truax) for allegedly violating three OSHA
construction safety standards dealing with scaffolds. The citation alleged as
one item violations of 29 C.F.R. 1926.451(a)(13) (improper access),
1926.451(a)(14) (planks extending too far over end supports), and
1926.451(d)(10) (inadequate perimeter protection).[1] Administrative Law Judge
Seymour Fier found that Truax violated the standards as alleged, and assessed a
penalty of $1000. We reduce the penalty to $650, but otherwise affirm his decision.
Truax
was a subcontractor on a construction site, responsible for the installation of
drywall. This case arose following the accidental electrocution of one of
Truax’s employees.[2]
At the time of the accident, the employee was installing drywall from a tubular
welded frame scaffold. The platform of the scaffold on which the employees were
working[3] was thirteen feet high and
was located on a mezzanine approximately seven feet above the building’s first
floor.
The
scaffold stood in a corner of the mezzanine. The south side abutted a concrete
block wall, and the east side was several inches from the wall on which the
employees were erecting drywall. The framework of the scaffolding served as
guardrails for the east and west sides. At the time of the accident, however,
there was no guardrail on the north side, which was adjacent to the edge of the
mezzanine. When the scaffold was erected, it had been equipped with a guardrail
on the north side, but the employees working on the scaffold had removed this
guardrail in order to ‘lean out the side’ while installing the drywall. The
scaffold was not equipped with any toeboards.
There
was no stairway leading from the floor to the mezzanine; the employees reached
the mezzanine by climbing a stepladder. They then obtained access to the
platform by climbing the framework of the scaffolding.
On
the day following the accident an OSHA compliance officer measured the planks
on the scaffold and found that they extended over their end supports by 14 to
24 inches. One of the employees who had been working on the scaffold, William
Truax, Jr., testified that the planks were approximately 1 ½ to 2 feet longer
than the scaffold supports, and that the configuration of the scaffold planks
when the compliance officer measured them was approximately the same as when
the scaffolding was being used the day before. There was also testimony by
Truax employees and by a witness who helped give emergency assistance after the
accident that the planks were rearranged to facilitate removal of the
electrocuted worker.
Judge
Fier found that Truax violated all three of the cited scaffolding standards.
Truax takes exception to his findings. It contends that it did provide an
access ladder to the scaffold platform because the employees, after ascending
the step ladder to the mezzanine, could then pull the stepladder up to that
level and use it to climb to the platform. As to the planks, Truax challenges
the relevance of the measurements made by the compliance officer because at
least some of the planks had been moved between the time the scaffold was used
and the time the measurements were made. Truax also contends that, for a
variety of reasons, the testimony of Truax, Jr. concerning the planks is
unreliable and should be discounted. Regarding the guardrails and toeboards,
Truax concedes it failed to comply with the standard but argues that, because
of the short time the scaffold was in use, and particularly because the
scaffold was used for only a few minutes without a guardrail on the side adjacent
to the edge of the mezzanine, the violations were ‘so relatively insignificant
that they could be classified as excusable.’
We
reject these arguments. It is true, as Truax points out, that 1926.451(a)(13)
requires only that a ladder be provided. That standard, however, must be read
in conjunction with 1926.450(a)(1), which states that ‘ladders described in
this shall be used to give safe access to all elevations.’ (emphasis added).
Thus, a requirement that ladders be used is implicit in1926.451(a)(13).[4] Ray Boyd Plaster &
Tile, Inc., No. 76-814 ($03R 1978). Since the employees did not use a
ladder, and climbing the framework of the scaffold was not equivalent safe
access,[5] we conclude that Truax
violated 1926.451(a)(13).
With
respect to the question of how far the scaffold planks extended over the
framework, the compliance officer’s measurements alone are not conclusive
because some of the planks were moved between the time the scaffold was used
and the time the measurements were made. Truax, Jr., however, testified that
the planks were in approximately the same position when the compliance officer
conducted the inspection as when the scaffold was in use, the Judge
specifically credited his testimony, and Truax offers no persuasive reason why
we should, in this case, depart from our general policy of accepting a trial
judge’s credibility determination. See, e.g. CTM, Inc., 77 OSAHRC
136/C12, 5 BNA OSHC 1578, 1977-78 CCH OSHD para. 21,957 (No. 13008, 1976).
Moreover, we note that the Judge’s finding is supported by photographs taken
during the inspection which show that two planks running east-west had a
considerable overhang on the east side and could not have been in a
significantly different position when the scaffold was in use because they
almost abutted the wall on the west side of the scaffold. Considering all the
evidence of record, we conclude that Truax violated 1926.451(a)(14).
Regarding
the alleged lack of adequate perimeter protection, it is undisputed that for at
least a short period of time, the scaffold was not equipped with any guardrail
on the north side, and the scaffold was not equipped with toeboards during its
entire period of use. Accordingly, the scaffold did not comply with the
standard, and Truax does not argue otherwise.[6] Instead, Truax asserts
that the violation should be excused because of its minor nature.
The
Commission has found some violations of standards to be so trifling that a
penalty should not be assessed and abatement not be required. See, e.g. National
Rolling Mills, Inc., 76 OSAHRC 121/D7, 4 BNA OSHC 1719, 1976-77 CCH OSHD
para. 21,114 (No. 7987, 1976); Rust Engineering Co., supra n. 4. In such
a case, the violation is said to be de minimis. In this case, however, we do
not regard the hazard resulting from the lack of guardrails and toeboards on
the scaffold as trifling. It was possible for an employee to fall 20 feet to a
concrete floor as a result of the complete absence of perimeter guarding on the
north side of the scaffold. Furthermore, even though that side was completely
unguarded for only a short time, at least one employee leaned over the
unguarded side and could well have fallen. The lack of toeboards existed during
the entire time the scaffold was in use and exposed the employees to the
possibility of being struck by falling material while climbing the framework of
the scaffold. Accordingly, we reject Truax’s argument that the violation was
insignificant or should be excused because of its brevity.
We
also conclude that the violation is properly classified as serious. Again, in
arguing to the contrary, Truax stresses the relatively brief duration of the
guardrail violation. It is, however, well-settled that a violation is serious
if the result of an accident would likely be death or serious harm, and that the
probability an accident will occur is irrelevant.[7] Here, any of the three
violations could have led to an employee falling up to 20 feet to a concrete
floor. Such a fall would probably have caused death or serious harm, and the
violation is therefore serious regardless of the duration of the violative
conditions. See Texaco, Inc., 77 OSAHRC 182/D8, 5 BNA OSHC 1962, 1977-78
CCH OSHD para. 22,246 (No. 13137, 1977).
Truax
also contends that the Secretary acted unconstitutionally by selectively and
arbitrarily inspecting its worksite while failing to cite other contractors and
subcontractors who had employees on the same job. This contention is based on
the fact that the Secretary chose to investigate the circumstances of the fatal
accident rather than conduct a general inspection of the entire worksite. We
need only note that such a choice is well within the Secretary’s enforcement
discretion, and we therefore reject Truax’s argument that it was improper. See Fleming
Foods of Nebraska, Inc., 77 OSAHRC 196/C12, 6 BNA OSHC 1233, 1977-78 CCH
OSHD para. $03R (No. 14484, 1977). Similarly, we conclude that the Judge did
not err in refusing to reopen the record to pursue the question of whether the
Secretary had cited similar scaffolding violations as nonserious in the past. Fleming
Foods of Nebraska, supra.
We
agree with Truax’s argument, however, that the Judge improperly based his
penalty assessment in part on the fact that a fatality had occurred. The
accident resulted from causes unconnected with the violations here at issue.
See note, 2, supra. Having considered the gravity of the violations together
with Truax’s size, good faith, and absence of any prior history of violations,
we conclude that a penalty of $650 is appropriate.
Accordingly,
the Judge’s decision is modified to assess a penalty of $650 and as so modified
is affirmed.
FOR THE COMMISSION:
Ray
H. Darling, Jr.
Executive
Secretary
BY:
Gloria W. White
Acting
Executive Secretary
DATED:
JUN 6, 1978
Commissioner
COTTINE took no part in the consideration or decision of this case for the
reasons set forth in his separate opinion.
SEPARATE OPINION
As
a new member of the Commission, I must resolve the issue of my participation in
pending cases. It is also necessary for me to set out the principles guiding my
decision on this important issue.
In
this case, Chairman Cleary and Commissioner Barnako reached a unanimous
decision on the merits before I received my commission on May 1, 1978. A
decision was already in preparation when I assumed office. I have concluded
that the wisest exercise of discretion is to decline to participate in this
case even though a new Commission member has authority to participate in
pending cases. It should be emphasized that by declining to participate I express
no opinion on the procedural or substantive issues in this case or on the
appropriateness of the accompanying order.
Discretion of Commission Members
As
a matter of law, it is not necessary for all Commission members to participate
for an agency to take official action. In Drath v. FTC, 239 F.2d 452
(D.C. Cir. 1956), cert. denied 353 U.S. 917 (1957), the Federal Trade
Commission issued a cease-and-desist order with only three of its five members
participating. The Court of Appeals rejected petitioner’s contention that the
FTC can act in its adjudicatory capacity only when all members participate,
except when there is a vacancy. The court ruled that official action can be
taken by the majority of the requisite quorum. Also Frisher & Co. v.
Bakelite Corp., 39 F.2d 247 (C.C.P.A. 1930) cited approvingly in FTC v.
Flotill Prod. Inc., 389 U.S. 179, 182-183 (1967). Similarly, section 12(f)
of the Occupational Safety and Health Act, 29 U.S.C. § 661(e), provides:
For
the purposes of carrying out its functions under this chapter, two members of
the Commission shall constitute a quorum and official action can be taken only
on the affirmative vote of at least two members.
Thus,
the unanimous decision already reached in this case satisfies the quorum and
official action requirements of the Act and my participation is not necessary
for the Commission to carry out its adjudicatory functions in this particular
case.
However,
it is also settled that a new member of an administrative agency may
participate in pending cases. For example, a new member of the Civil
Aeronautics Board who had not participated in previous proceedings was entitled
to vote and break an existing tie where he had familiarized himself with the
record. Western Airlines v. CAB, 351 F.2d 778 (D.C. Cir. 1965), citing United
Air Lines v. CAB, 281 F.2d 53 (D.C. Cir. 1960)[8]. In United the
court indicated that, where a member voting with the majority without hearing
oral argument ‘had the record before him and the benefit of briefs’, there was
no abuse of discretion in his participation, 281 F.2d at 56. There are numerous
other cases supporting this holding. The clearest statement of law is set forth
in Gearhart & Otis, Inc. v. SEC, 348 F.2d 798 (D.C. Cir. 1965):
The
decisions of numerous courts and administrative agencies establish that, even
without agreement of the parties, a member of an administrative agency who did
not hear oral argument may nevertheless participate in the decision where he
has the benefit of the record before him. [footnotes omitted]
348 F.2d at 802.[9] See Au Yi Lau v. U.S.
Immigration and Naturalization Service, 555 F.2d 1036, 1042 (D.C. Cir.
1977); Arthur Lipper Corp. v. SEC, 547 F.2d 171, 182 & n.8 (2d Cir.
1976). Thus, a new member possesses the necessary authority to participate in
all cases pending before the Commission on assuming office.
Though
a new member may participate in all pending cases, particularly those involving
an impasse, the decision remains a matter of discretion since adjudicatory
decision may be upheld on a majority of a quorum. In FTC v. Flotill prod.,
389 U.S. 179 (1967) rev’g 358 F.2d 224 (9th Cir. 1966), an FTC member
appointed to fill one of two vacancies, declined to participate because he had
not heard the oral argument. Thus, three of the possible four Commissioners
actually participated in the decision. As a result, the FTC issued a
cease-and-desist order based on the affirmative vote of only two members.
Despite its obvious impact on the number of members constituting a majority,
the Court did not review the exercise of discretion by the new member. Instead,
the Court accepted the abstention at face value and upheld the action of the
two members of the FTC. See also La Preyre v. FTC, 366 F.2d 117 (5th
Cir. 1966); Atlantic Refining Co. v. FTC, 344 F.2d 599 (6th Cir. 1965).
In addition, administrative decisions involving two or more abstentions have
been upheld by reviewing courts without question or comment on the grounds for
these abstentions. All that was necessary to sustain the agency decision was a
majority of the required quorum. E.G., Greater Boston Television Corp. v.
FCC, 444 F.2d 841, 848, 861 (D.C. Cir. 1970), cert. denied 403 U.S.
923 (1971).
Decision Not to Participate
I
decline to participate in this case because a majority of the Commission has
reached agreement on the merits and my vote would have no effect on the
outcome. Moreover, in cases where Chairman Cleary and Commissioner Barnako have
reached a unanimous decision, my participation would delay the issuance of
decisions and conflict with the goal of a prompt and efficient decision-making
process. See generally Atlas Roofing Co. Inc. v. OSHRC, 430 U.S. 442, 97
S.Ct. 1261, 1272 (1977); Keystone Roofing Co., Inc. v. OSHRC, 539 F.2d
960, 964 (3d Cir. 1976); Nader v. FCC, 520 F.2d 182, 205-207 (D.C. Cir.
1975), citing 5 U.S.C. § 555(b). Since abatement is stayed until the Commission
enters a final order, 29 U.S.C. § 659(b), additional deliberations would delay
the control of hazardous working conditions in any case where the Commission
has determined that a violation of the Act exists. That result would be
inconsistent with the statutory purpose to assure so far as possible safe and
healthful working conditions for every working man and woman. 29 U.S.C. §
651(b).
I
will, however, participate fully in all cases in which previous Commission
deliberations have resulted in a one-to-one deadlock. Decisions by an equally
divided Commission are without precedential value, e.g., Life Sciences
Products Co., 77 OSAHRC 200/A2 (microfiche), 6 BNA OSHC 1053, 1977-78 CCH
OSHD ¶22,313 (No. 14910, Nov. 11, 1977), appeal filed, No. 77-1014 (4th Cir.
Jan. 6, 1978), and, therefore, do not serve as guidance to the Commission’s
administrative law judges. Moreover, these decisions also promote needless litigation
in the U.S. Courts of Appeals to decide issues which should initially be
determined by the Commission, because its members have specialized training,
education, and experience in occupational safety and health. 29 U.S.C. §
661(a). See generally Atlas Roofing Co. v. OSHRC, supra at 1264, 1272; Keystone
Roofing Co. Inc. v. OSHRC, supra at 963-964. Administrative resolution of
pending issues also promotes a more uniform application and development of
occupational safety and health law. After reading the record, I will
participate in the consideration and decision of these cases.
Conclusion
My
decision not to participate in pending cases which have reached a unanimous
decision by my colleagues, but to participate in those cases with unresolved
issues, promotes the prompt adjudication of cases. It also assures the parties
and the public of the full benefit of Commission review. Both of these results
are essential in deciding cases affecting the lives, health and safety of
American workers, the operation of American business, and the effective
adjudication of cases by the administrative law judges.
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NOS. 14516& 14721 (CONSOLIDATED) |
TRUAX
& HOVEY DRYWALL CORP., |
|
Respondent. |
|
FINAL ORDER DATE: April 21, 1976
Appearances:
Francis V. LaRuffa, Regional Solicitor
United States Department of Labor
1515 Broadway, Room 3555
New York, New York 10036
Attorney for complainant by Barnett
Silverstein, Esq.
Grasso, Rivizzigno & Woronov, Esps.
647 South Warren Street
Syracuse, New York 13202
Attorney for respondent by Howard J.
Waronov, Esq.
Welch, Welch & Carr, Esqs.
Camillus Professional Building
5100 West Genesee Street, Box 175
Syracuse, New York 13209
Attorney for respondent by Anthony
Adorante, Esq.
DECISION AND ORDER
Fier, Judge:
PRELIMINARY STATEMENT
This
is a proceeding pursuant to section 659 of the Occupational Safety and Health
Act of 1970 (29 U.S.C. § 651 et seq., hereinafter called the Act), wherein the
respondents contest the citations and penalties for one serious violation
against respondent Pearson Electric Company, Inc. (hereafter referred to as
Pearson), and two serious violations against Truax & Hovey Drywall Corp.
(hereafter referred to as Truax). The citation against Pearson dated August 5,
1975, was based on an inspection conducted from July 18th through August 4,
1975. The citations against Truax, dated August 6, 1975, were based on an
inspection conducted from July 18, 1975 through August 1, 1975. The citations
and proposed penalties were issued pursuant to sections 9(a) and 10(a) of the
Act.
Pursuant
to section 10(c) of the Act, 29 U.S.C. § 659(c) respondent Pearson through a
letter dated August 27, 1975, noted its timely contest to the citation and
proposed penalty. Truax through its attorney, on August 14, 1975, noted its
timely contest to the citations and penalties.
On
November 11, 1975 the Secretary made a motion to have the above cases
consolidated for trial on the grounds that both cases have common questions of
law and facts and the witnesses are the same for both cases. Accordingly, on
November 18, 1975 an order was issued consolidating both cases for trial.
The
citation for alleged serious violation against Pearson sets forth the
following:
Citations No. 1
Item
No. |
Standard
|
Description |
1 |
NEC-NFPA
70–1971 Article 320–5(a) p. 70–124 as adopted by 29 CFR 1926.400(a) p. 22831,
FR# 122, dated June 24, 1974 |
(A)
Temporary 277 and 115 Volt A.C. conductors originating in electrical power
distribution panel (located approximately 21 feet from north east corner of
welding area) which ran along mezzanine and along west wall of welding area
were not supported on noncombustible, nonabsorptive insulating material. The
temporary conductors are being supported by pieces of electrical wire
throughout their entire length. |
|
NEC-NFPA
70–1971 Article 320–9 p. 70–125 as adopted by 29 CFR 1926.400(a) p. 22831 FR#
122, dated June 24, 1974 |
(b)
Temporary 277 and 115 Volt A.C. open conductors are not separated from
contact with walls or partitions through which they pass by tubes or bushings
of noncombustible, nonabsorptive insulating material. Conductors pass through
wall on east side of power distribution room, along floor of mezzanine, and
through concrete block wall, west of weld area. |
|
NEC-NFPA
70–1971 Article 320–10 p. 70–125 as adopted by 29 CFR 1926.400(a) p. 22831
FR# 122, dated June 24, 1974 |
(c)
Temporary 277 and 115 Volt A.C. open conductors, running along floor of
mezzanine and west wall of weld area, are not separated at least 2 inches
from metallic conduit, or other conducting material (metal ceiling grid
supports, metal scaffold frame, metal conduit) or from each other. |
The
above combined alleged violations constitute one serious violation, in that
they exposed employees to accidental electric shock which could result in death
or serious physical harm.
A
penalty of $600.00 was proposed.
Standard
as promulgated:
29 CFR § 1926.400 General requirements.
(a) All electrical work, installation. and
wire capacities shall be in accordance with the pertinent provisions of the
National Electrical Code, NFPA 70–1971; ANSI CI–1971 (Rev. of C1–1968), unless
otherwise provided by regulations of this part.
NEC-NFPA 70–1971:
Article—320–5. Supports.
(a) Conductors shall not be in contact
with any object other than their insulating supports. They shall be rigidly
supported on noncombustible, nonabsorptive insulating material as follows:
(1) Under ordinary circumstances, supports
for wiring over flat surfaces shall be not more than 4–1/2 feet apart. Where
the conductors are likely to be disturbed, the distance between supports shall
be shortened sufficiently to provide adequate support for conductors;
(2) Conductors shall be supported within 6
inches of a tap;
(3) Conductors shall not be dead ended at
a rosette, lampholder, or receptacle unless the last support is within 12
inches of the device.
Article—320–9. Passing Through Walls and
Floors. Open conductors shall be separated from contact with walls, floors,
timbers or partitions through which they pass by tubes or bushings of
noncombustible, nonabsorbative insulating material. Where the bushing is
shorter than the hole, a waterproof sleeve of noninductive material shall be
inserted in the hole and an insulating bushing slipped into the sleeve at
either end in such a manner as to keep the conductors absolutely out of contact
with the sleeve. Each conductor must be carried through a separate tube or
sleeve.
Article—320–10. Separation from Metal
Work. Open conductors shall be separated at least 2 inches from metallic
conduit, piping, or other conducting material, and from any exposed lighting,
power or signal conductor, or shall be separated therefrom by a continuous and
firmly fixed nonconductor additional to the insulation of the conductor. Where
any insulating tube is used, it shall be secured at the ends. Deviation from
this requirement may, when necessary, be allowed by the authority enforcing
this Code.
Citation
No. 1 against respondent Truax is identical with the above citation against
Pearson. The penalty proposed against Truax for the above is $650.00.
Citation
No. 2 against Truax for alleged serious violation sets forth the following:
Item
No. |
Standard |
Alleged
violation |
1 |
29
CFR 1926.451(a)(13), (14), (d)(10) |
(A)
Access ladder or equivalent safe access was not provided to the platforms of
the scaffold located on the mezzanine approximately 10 feet from northeast
corner of weld area. (B)
Planks of the scaffold (located on the mezzanine approximately 10 feet from
Northeast corner of weld area) extend over their end supports more than 12
inches. (C)
Guardrails and toe boards (or equivalent) are not installed at all open sides
and ends of scaffold more than 10 feet above the floor. Scaffold located on
the mezzanine approximately 10 feet from the northeast corner of weld area. |
The above combined alleged violations constitute one
serious violation, in that they exposed employees to falls and falling objects
that could result in death or serious physical harm.
A
penalty of $650.00 was proposed.
Standard
as promulgated:
29 CFR § 1926.451(a) Scaffolding.
(13) An access ladder or equivalent
safe access shall be provided.
(14) Scaffold planks shall extend
over their end supports not less than 6 inches nor more than 12 inches.
(d)(10) Tubular welded frame
scaffold guardrails made of lumber, not less than 2 x 4 inches (or other
material providing equivalent protection), and approximately 42 inches high,
with a midrail of 1 x 6 inch lumber (or other material providing equivalent
protection), and toeboards, shall be installed at all open sides and ends on
all scaffolds more than 10 feet above the ground or floor. Toeboards shall be a
minimum of 4 inches in height. Wire mesh shall be installed in accordance with
paragraph (a)(6) of this section.
29 CFR § 1926.451(a)(6)
Where persons are required to work
or pass under the scaffold, scaffolds shall be provided with a screen between
the toeboard and the guardrail, extending along the entire opening, consisting
of No. 18 gauge U.S. Standard wire 1/2 inch mesh, or the equivalent.
ISSUES
The
following issues are pertinent to a disposition of this case.
1.
Did either or both respondents violate section 5(a)(2) of the Act by failing to
comply with the standards published at 29 CFR § 1926.400(a); NEC-NFPA 70–1971
Article 320–5(a), 320–9, 320–10?
2.
Did the respondent Truax violate section 5(a)(2) of the Act by failing to
comply with the standards published at 29 CFR § 1926.451(a)(13), 29 CFR §
1926.451(a)(14) and 29 CFR § 1926.451(d)(10)?
3.
What penalty, if any, should be assessed for any violations of the Act?
STATEMENT OF THE EVIDENCE
The
respondent Pearson, is a New York corporation with approximately 15 employees.
Last year it had a net profit of $17,000 (Tr. 223)[†††]. It is considered to be
a medium sized business for its kind. The respondent Truax is also a New York
corporation of medium size. It employs approximately 75 to 100 employees.
The
inspection by the OSHA compliance officers (hereafter referred to as C.O.) was
occasioned as a result of a fatal accident of an employee. The deceased
employee of Truax was Grover Sweeting who was electrocuted while installing
plaster board on July 17, 1975. At the time of the accident he was working on a
platform 18 to 20 feet above the floor (stipulation paragraph 8). William
Truax, Jr. testified that he and Sweeting were installing dry walls when
Sweeting, on descending from a platform, stepped on some wires and shorted out
the power (Tr.39). The witness then stated that the electricians were told of
the short circuited wires (Tr. 40). Upon informing the job superintendent,
Truax and Sweeting took their afternoon coffee break (Tr. 40). Upon returning
from the break, the job superintendent and a Pearson employee advised the
workers that the broken wires were fixed and cautioned them to be careful
because the wires were of a high voltage (Tr. 40). Shortly thereafter, while
using a Black & Decker drywall screwdriver, Truax employee, Grover Sweeting
was electrocuted as he was working on the elevated scaffold platform.
As a
result of this, the United States Department of Labor was duly notified and an
investigation and inspection of the accident scene followed. The above
citations were subsequently issued to the respondents. The testimony concerning
the electrical violations, issued to both respondents revealed that loose wires
carrying electricity were in close proximity of the subject scaffold (Tr. 60).
The wires were lying loose on the floor and were observed being ‘hung there by
nails’ (Tr. 77, 82, 144). Testimony also indicated that the shorted wire was
observed by the Truax foreman who stated, ‘I remember seeing the wire that had
shorted hanging on a nail’ (Tr. 136). The wire in fact was wrapped around a
nail. The C.O. testified that on his inspection he saw that the light fixture
in exhibit C–21 was not adequately suspended (Tr. 156). The C.O. also observed
that the 277 volt line and the 115 volt line were hung together, not adequately
separated, and connected to the electrical conductors and not the support (Exh.
C–21; Tr. 156). In addition, the wires were observed in contact with grillwork
and temporary grille structures, steel supports on the ceiling and in contact
with conduit (Tr. 152, Exhs. C–20, 21, 34, 42). The wires were also noted to be
crossing over conduit (Exh. C–37). No tubing or other insulating material was
provided for the wires to pass through walls or partitions (T. 111, Exh. C–31,
43). The evidence also shows the two wires were tied together with a piece of
wire to a conduit and dropping down in contact with the grillwork (Exh. C–34,
Tr. 158–159).
The
evidence concerning the access to the platform by means of a ladder has
disputed testimony. The C.O. at the time of his inspection, the day after the
accident, recommended that a citation be issued to Truax because the respondent
did not provide an access ladder or equivalent safe access to the platform. The
respondent’s employee, who was working on the platform, testified that he at
first had a ladder to get up to the platform but did not use it. He testified
that,
A. There was two sections of scaffolding,
I think and there was a half section on top that we climbed up. We went up by
the stepladder, crossed over the wall and got onto the scaffold and went up.
Q. And how did you go up the scaffold?
A. Up the sides.
Q. Did you use a ladder?
A. No, sir.
Q. No ladder. Okay. Then what happened?
You had a break and went back to work’ (Tr. 42).
On cross examination the same witness
testified:
Q. ‘You used a ladder to get up to the
scaffold after your lunch break—your coffee break, I mean?
A. We used a ladder to get up to the
cement block wall. (Tr. 85)
The
Pearson foreman testified that when he went to make the electrical repairs
during the coffee break, he obtained access to the mezzanine by use of a ladder
‘On the floor below the scaffold.’ (Tr. 110). The evidence shows a ladder
located at the side of the platform in exhibit photographs (Exhs. C–19, C–21)
taken the day after the accident. The respondent Truax’ employee further
testified that a ladder device capable of reaching the top platform of the
scaffold was not at the scaffold when the platform was first used. The crank
ladder was brought over only five or ten minutes before the accident (Tr. 62).
The
matter of the planks of the scaffold is also in dispute. The C.O. measured the
planks and found that there was an overhang of the platform of 14 to 24 inches
(Tr. 155). Respondent’s employee testified that the planks used on the scaffold
are usually ‘approximately a foot and a half to two feet, usually longer, maybe
a foot longer than the scaffold itself so that they hang out a little on each
end’ (Tr. 45). The respondent asserts that at the time medical assistance was
being administered to the employee on the scaffold, planks were rearranged and
exchanged to facilitate removal of the worker (Tr. 204, 219).
The
C.O. at the time of inspection, also cited the respondent for failure to have
guardrails and toeboards on all open sides of the scaffold. He testified,
Q. ‘Did you observe such toeboards and
guardrails or midrails on the top platform of the scaffold?
A. There were none there and I was
informed by Mr. Truax that there were none there at the time of the accident.
Q. How about the mid or lower platform of
the scaffold?
A. Same thing.’ (Tr. 156)
The
respondent Truax’ employee testified in substantial agreement that there was no
toeboard (Tr. 49). He also stated that the guardrail on one side was removed to
permit him to work (Tr. 52). There was also testimony from the First Aid
witness that when he was on the platform assisting the injured employee, there
was nothing directly behind him that he recalls (Tr. 127, 130).
OPINION
The
Secretary has cited the above respondents, Pearson and Truax, for identical
violations of the standard 29 CFR § 1926.400(a) specifically based on the
National Electrical Code of 1971. The respondent Truax employee upon discovering
the break in the electrical wires notified the respondent Pearson and the
Superintendent on the job of the defect. At this point it is apparent that
Truax relied upon Pearson to provide a safe work area for its employees.
Although Pearson states that the Truax employees were later told to be careful
and report any other electrical problems, this could not serve to relieve
Pearson from complying with the standards. The evidence clearly shows that the
respondent Pearson failed to comply with the standard NEC-NFPA 70–1971 Article
320–5(a) as adapted by 29 CFR § 1926.400(a). The photographs and testimony as
previously mentioned support the observation of the C.O who recommended the
issuance of the citation. The electrical lines were shown to be supported by
pieces of electrical wire in violation of the standard.
The
temporary 277 and 115 Volt open conductors were similarly in violation of the
standard by failure to have them separated from contact with the walls through
which they passed. This was not only apparent from the testimony but also from
the photographs in evidence.
The
open conductors are also observed in the photographs to be in contact with
metallic conduit, metal frames, and were not separated from each other. The
testimony of the C.O. as to his observations at the time of inspection shows
that the practice of the wiring violations was not restricted to a singular
contact of the wires. It is significant that after the first incident of the
wires shorting the lights, the respondent Pearson’s employees failed to, at
that time, provide the respondent Truax employees with a safe place for the
workers to perform their trades. The respondent Pearson asserts that its
foreman together with the general superintendent, warned the Truax employees of
the dangers of electricity. The warning was ‘I told them that when they were
working in and around wires, if they found any that didn’t look safe, to notify
myself or one of the Pearson electric people on the site and we would have it
repaired’ (Tr. 199). It is obvious from the foregoing that an open high voltage
line in contact with another metallic surface gives little or no warning to the
person who touches it until it often is too late. It is reasonable to assume
that a worker who enters a construction area should be able to ply his trade in
a safe environment free from hidden dangers.
The
evidence is overwhelming that the respondent Pearson failed to comply with each
of the above standards for which it was cited. The respondent Truax on the
other hand, did notify the Superintendent of the incident and permitted its
employees to return to work after the coffee break on the assumption that it
was now safe to do so. The talk given by the Superintendent and the Pearson
foreman can easily be construed as an assurance by them that it was safe for
the Truax employees to return to the work area (Tr. 146). In addition, the
statement of Pearson that it would correct any obvious hazards if notified
cannot relieve Pearson and shift responsibility for compliance over to Truax.
Under the circumstances and particular facts of this case, the citation against
Truax for violation of the National Electrical Code must be vacated.
The
respondent Pearson raises the argument that the Secretary has applied the wrong
standard of the National Electric Code. It states that the proper standard
should be Article 305 instead of Article 320 of the National Electric Code. The
Review Commission adapted the findings of Judge Goldstein in a similar
situation where the same defense was raised. The decision held;
‘It was undisputed that open wiring was in
contact with equipment and with duct-work at the employer’s worksite, contrary
to Article 320.5 of the National Electric Code. The employer argued, however,
that Article 320.5 of the Code was inapplicable because the wiring was
installed in a building under construction and that the applicable provision
was Article 305 entitled ‘Temporary Wiring’.
Nothing
in Article 305 specifically modified the requirements of Article 320.5 for
permanent wiring to permit the type of wiring utilized by the employer, and
unless specifically modified, all the requirements of the Code for permanent
wiring apply to temporary installations.’ Secretary of Labor v. Amelco
Electric. 4 OSAHRC 827 (1973) Docket #2462.
See
also Secretary of Labor v. Bertke Electric Co., Inc., 18 OSAHRC 840
(1975) Docket No. 3409. In this case the Review Commission not only rejected
the respondent’s theory as to temporary wiring but saw fit to raise the
proposed penalty because of the hazard.
Another
argument raised by the respondent Pearson is that the 1975 National Electric
Code has a revised interpretation as against the 1971 National Electric Code.
This argument also must be rejected. See Secretary of Labor v. Bethlehem
Steel Corp. —— OSAHRC —— (July 9, 1975), Docket No. 9968 (CCH 9968) in this
decision, Judge Chodes resolved a similar allegation where; ‘The employer
produced an interpretation of the standard from the ANSI committee which
drafted it. * * *. While entitled to careful consideration, Judge Chodes ruled
the ANSI interpretation is not controlling because it is contrary to the plain
language of the standard.
The
citation against Truax for violations of 29 CFR §§ 1926.451(a)(13),
1926.451(a)(14) and 1926.451(d)(10) are concerned with the scaffold used by the
Truax employees. The testimony of William Truax, Jr., is worthy of greater
weight since he not only helped construct the scaffold but also used it. The
testimony supported by that of the other evidence clearly indicates that the
above standard was violated. The access ladder or other safe means of getting
up to the top platform was not by the scaffold. The testimony of the witnesses
and other evidence was sufficient to establish the absence of a safe means of
access to the scaffold platform. The testimony and evidence also demonstrated
that the planks used on the platform violated the standard by exceeding the
amount of overhang permitted and created a hazard not only to the employees but
also to the rescue workers in their effort to reach the top platform. The
absence of toeboards is clearly established. However, the presence of
guardrails has been disputed. Testimony of several of the witnesses lends
sufficient credibility to show that the guardrails were not installed at all
open sides and ends of the scaffold as required by the standard. Accordingly,
the evidence and testimony are sufficient to establish the violations of 29 CFR
§§ 1926.451(a)(13), 1926.451(a)(14) and 1926.451(d)(10) by the respondent
Truax.
We
are next concerned with the imposition of penalties. The Secretary proposed an
unadjusted penalty of $1,000.00 against respondent Pearson. The unadjusted
penalty was then reduced to a proposed penalty of $600.00. After considering
all of the evidence and testimony, and the fact that a worker was electrocuted,
together with the criteria set forth in section 17 of the Act, I am persuaded
to conclude that a penalty of $1,000.00 would be appropriate under the
circumstances.
The
imposition of a penalty against respondent Truax for violation of the standards
29 CFR §§ 1926.451(a)(13), 1926.451(a)(14) and 1926.451(d)(10) has also been
weighed against the evidence, testimony and criteria of section 17 of the Act.
After giving due consideration to all of the above, I find that an unadjusted
penalty of $1,000.00 should be assessed. The fact that an employee was killed
while at work, requires that an appropriate aura of awareness be established
for compliance with the standards of the Act by the respondents. The gravity of
the violations by Pearson and Truax justify the assessment of an unadjusted
penalty under the circumstances of this case.
Any
motions and objections not previously disposed of are denied.
FINDINGS OF FACT
The
credible evidence and the record as a whole establishes preponderant proof of
the following specific findings of fact:
1.
Respondent Pearson Electric Company, Inc., is a New York Corporation doing
electrical contract work in the construction business and employs approximately
15 employees. Many of the materials used are manufactured outside the State of
New York.
2.
Respondent Truax and Hovey Drywall Corporation is a New York Corporation in the
drywall construction business and employs approximately 75 to 100 employees.
Many of the materials used by it are manufactured outside the State of New
York.
3.
The evidence shows that respondent Pearson permitted temporary 277 and 115 volt
open conductors on the jobsite that were supported by pieces of electrical wire
and hung on bent nails throughout in a loose manner.
4.
The evidence shows that respondent Pearson permitted temporary 277 and 115 volt
open conductors which were not separated from contact with walls and passed
through said walls without tubes of non-combustible, non-absorptive insulating
material.
5.
The evidence shows that respondent Pearson permitted temporary 277 and 115 volt
open conductors to run along the floors, walls, and ceiling in a loose manner,
coming in contact with conduit, grillwork, steel supports on ceilings, and with
each other.
6.
The evidence shows that respondent Truax notified the Superintendent and
Pearson’s foreman of the break in the wires prior to the afternoon coffee break
on July 17, 1975.
7.
The evidence shows that respondent Truax relied upon the Superintendent and
Pearson’s foreman that the worksite was safe as far as any electrical hazards
for its employees to return to work after the coffee break on July 17, 1975.
8.
Respondent Truax did not know of the hidden hazard presented by the faulty
electrical wiring.
9.
Respondent Truax did not provide safe access to the top platform of the
scaffold on which its employees were working.
10.
Respondent Truax used planks on its scaffold which extended more than 12 inches
over the end supports.
11. Respondent Truax permitted its employees to use a
scaffold that did not have toeboards and guardrails at all open ends of the
scaffold.
CONCLUSIONS OF LAW
1.
The respondents Pearson Electric Company, Inc., and Truax and Hovey Drywall
Corporation, were at all times herein engaged in a business affecting commerce
within the meaning of section 3 (5) of the Occupational Safety and Health Act
of 1970.
2.
The Occupational Safety and Health Review Commission has jurisdiction over the subject
matter and parties to this action.
3.
Respondent Pearson violated 29 U.S.C. 654(a)(2) by failing to comply with 29
CFR § 1926.400(a) in that all electrical work was not in accordance with the
National Electrical Codes, N.F.P.A. 70–1971, A.N.S.I. C1–1971 to wit: N.F.P.A.
70–1971 Article 320–5; Article 320–9; Article 320–10.
4.
Respondent Truax did not violate 29 CFR § 1926.400(a) and in particular the
pertinent provisions of the National Electrical Code, N.F.P.A. 70–1971,
A.N.S.I. C1–1971 to wit: N.F.P.A. 70–1971 Article 320–5; Article 320–9 and
Article 320–10.
5.
Respondent Truax violated 29 U.S.C. 654(a)(2) by failing to comply with 29 CFR
§§ 1926.451(a)(13), 1926.451(a)(14) and 1926.451(d)(10).
6.
All of the above violations are serious violations within the meaning of 29
U.S.C. 666.
ORDER
Upon
the basis of the foregoing findings of fact and conclusions of law, and upon
the entire record, it is hereby ORDERED that;
Pearson
citation number one, item one, is affirmed. A penalty of $1,000.00 is assessed.
Truax citation number one, item one, is vacated.
Citation number two, item one, is affirmed. A penalty of $1,000.00 is assessed.
SEYMOUR FIER
JUDGE, OSAHRC
Dated: March 22, 1976
New York, New York
[1] The standards
provide:
1926.451(a)(13)
An access ladder or equivalent safe access shall be provided.
(a)(14)
Scaffold planks shall extend over their end supports not less than 6 inches nor
more than 12 inches.
(d)(10)
Guardrails made of lumber, not less than 2 x 4 inches (or other material providing
equivalent protection), and approximately 42 inches high, with a midrail of 1 x
6 inch lumber (or other material providing equivalent protection), and
toeboards, shall be installed at all open sides and ends on all scaffolds more
than 10 feet above the ground or floor. Toeboards shall be a minimum of 4
inches in height. Wire mesh shall be installed in accordance with paragraph
(a)(6) of this section.
[2] In addition to
the scaffolding violations here at issue, Truax was cited for several
electrical violations relating to the circumstances of the fatal accident. The
Judge found that Truax did not commit these violations. No party has taken
exception to this aspect of the Judge’s decision, and the alleged electrical
violations are therefore not before us for review.
[3] The scaffold was
built in two levels: the level on which the employees were working at the time
of the accident, and a lower level approximately six feet above the mezzanine.
The Secretary argues in his brief that Truax violated the standard on both
levels. The pleadings, however, did not refer to two levels, and the parties
stipulated to facts concerning only the upper level. Moreover, although the
lower level was mentioned during the testimony, the vast bulk of the evidence
concerned the upper level, and the Judge did not make specific findings with
respect to the lower level. Considering the entire record, we conclude that the
parties, at the hearing, did not understand that the question of a violation on
the lower level was in issue, and we therefore do not address whether a
violation occurred on that level.
[4] But see Kennecott
Copper Company, 76 OSAHRC 81/A2, 4 BNA OSHC 1400, 1976-77 CCH OSHD para.
20,860 (No. 5958, 1976), aff’d, No. 76-1735 (10th Cir., Dec. 23, 1977). In
Kennecott, a divided Commission held that 29 C.F.R. 1910.28(a)(12), a general
industry standard worded identically to 1926.451(a)(13), did not impose a use
requirement. The general industry standards, however, contain no counterpart to
1926.450(a)(1), and Kennecott is therefore distinguishable from this
case.
Chairman Cleary would not rely on
the ‘use’ language in another standard. He would hold that a standard that
requires an employer to ‘provide’ a safety device implicitly requires that the
device be used. Kennecott Copper Co., supra, (Cleary dissenting); Hillsdale
Lumber & Manufacturing, Inc., 77 OSAHRC 54/D2, 5 BNA OSHC 1281, 1977-78
CCH OSHD para. 21,766 (No. 5815, 1977) (Cleary, dissenting).
[5] In Rust
Engineering Co., 77 OSAHRC 37/C8, 5 BNA OSHC 1183, 1977-78 CCH para. 21,693
(No. 12200, 1977), employees climbed ladder-like rungs in the framework of a
scaffold to gain access to the scaffold platform. Because the rungs deviated
from the requirements for ladder rungs established by the applicable standards,
the Commission concluded that using them as a means of access violated the
standard. In Rust, however, the violation was found to be de minimis because
the configuration of the rungs made the hazard trifling. In this case, the scaffold
framework does not contain rungs similar to those in Rust, and the violation is
therefore not de minimis.
[6] In particular,
Truax does not contend that it was necessary for the employees to remove the
guardrail to perform their work.
[7] See, e.g. California Stevedore & Ballast Co., 73 OSAHRC 39/B5, 1 BNA OSHC 1305, 1973-74 CCH OSHD para. 16,520 (No. 14, 1973), aff’d, 517 F.2d 986 (9th Cir. 1975).
[8] A Commissioner
may vote simply to avoid an impasse. Public Service Commission of State of
N.Y. v. FPC, 543 F.2d 757, 777 (D.C. Cir. 1974). See generally Screws v.
United States, 325 U.S. 91, 134 (1945) (Rutledge, J., concurring in
result).
[9] The Court
distinguished WIBC, Inc. v. FCC, 259 F.2d 941 (D.C. Cir.) cert. denied,
sub nom. Crosley Broadcasting Corp. v. WIBC, Inc., 358 U.S. 920 (1958),
because oral argument was statutorily required if a party requested it. 348
F.2d 798, n. 14.
[†††] Transcript
references.